Work beginning: |
NOV 11 2005 |
10% |
20% |
30% |
40% |
50% |
60% |
70% |
80% |
90% |
100% |
Ended: |
AUG 2008 |
- Welcome to the sailboat "Sirius" web page. Know the development of the amateur building of a Samoa 28 designed by Roberto Barros Yacht Design (Cabinho) that we are building in our own house, located in City Bell, Buenos Aires, Argentina. I will try to write how the dream transforms in reality, hoping help those who are for the same road, or for memory of those that participated of the construction in any way. |
||
2005 |
2006 |
2007 |
2008 |
NOVEMBER:plans/timbers/ molds/mounting. | JANUARY: hull building | JANUARY:fiberglassing deck / hatch. | JANUARY:paint/ironworks/keel |
MARCH: hull building |
MARCH: building the interior | MARCH: keel/rod/interiors/winches | |
MAY: sanding and external fiberglassing |
APRIL:external sanding/ building the interior | APRIL:interiors |
|
JULY: sanding /primer /putty /turning hull/fiberglass.int. |
MAY: sanding/primer/putty/building interior/acrilycs/hatchway/elctr.panel. | MAY: tile/keel/removing. | |
AUGUST:fiberglass.int/ sections0-8/ strengthen keel/ cabin estruct./ anchor box |
JUNE:ironworks/ gas box | JUNE:transport | |
SEPTEMBER: longitudinal reinfor. /cabin struct. /forward deck |
JULY: nav. table/ water tanks/ bathroom | ||
OCTOBER: cabin /hatchs /sections 9-11 |
AUGUST: port water tank | OCTOBER: launching |
|
NOVEMBER: cockpit /aft deck /swim deck |
SEPTEMBER: port water tank/table/kitchen |
|
|
DECEMBER: Dinghy /coamings /deck fiberglassing |
OCTOBER: interiors |
|
|
NOVEMBER: interiors/pulpit and iron works/hidraulics |