Entry Date |
Work Done |
September 7th, 2000 |
Discussed the basic plan to build the prototype for CRM in class, noting down all constratints to be taken care of. Furthermore, we decided our next group meeting would be on September 15th, 2000 (Friday) at 5:30, meeting place: Zaida Morales' House. |
September 15th, 2000 |
Meeting at Zaida's Place: We discussed about the project objective. Using the Software Management Plan template printed from the web site, we stepped through each section and discussed what was required and what resources were available to us. We also discussed how this prototype should be flexible for other countries. There was constant reference to the "Chinese Railway Passenger Reservation System" and other related articles. |
September 16th, 2000 |
Finished a rough draft prototype and set it up on the online account. |
September 19th, 2000 |
Zaida M. Morales checked the document of the Software Project Management Plan, and she made some correction marking the corrections in red. |
September 20th, 2000 |
The mistakes were corrected on the web site, and email was sent to Zaida M. morales to check the document for any more mistakes |
September 20th, 2000 |
The document was checked by Zaida M. Morales and few more mistakes were found. These mistakes were corrected and put on the web. |
September 22th, 2000 |
Meeting at Zaida's Place: We discussed the Reservation System in more detail and added more information to the SPMP document. |
September 25th, 2000 |
Zaida M. Morales checked the document of the Software Project Management Plan, and she made some corrections. |
September 27th, 2000 |
The mistakes were corrected on the web site, and email was sent to Zaida M. morales to check the document for any more mistakes. |
September 29th, 2000 |
Meeting at Zaida's Place: We discussed parts 4 and 5 of the Software Project Management Plan in more detail and decided to update some information in the SPMP document. The different parts of the document were divided between the team for updates. |
October 3th, 2000 |
Finished updating the rough draft prototype and set it up on the online account. Sent all team members email with link to latest copy of the document. |
October 4th, 2000 |
Zaida M. Morales checked the document of the Software Project Management Plan. The mistakes were corrected on the web site. The latest version of the document is available online. |
October 20th, 2000 |
Meeting at Zaida's Place: We met with the two new team members and discussed how to integrate their work into our SPMP document. We started discussing our first draft of the SRS document and decided to try to have a first pass at it within a week. |
November 3rd, 2000 |
Meeting at Zaida's Place, and decided that this was a point in time where all changes that need to done should be done to the SPMP this week and our focus should now be more on the SRS. We completed the discussion about the situation updates and we moved on to the SRS. We managed to complete until 2.3 |
November 7th, 2000 |
Completed compiling the SPMP together, however this document will be checked by another team member to varify that all changes have been addressed. The SRS was partly complete since there are problems downloading a picture. |