Plant relocation - Wave Solder Process (1993)
Developed facility layout and project plan for the wave solder process and water treatment plan; assisted the other production teams in their facility layout development; resolved process location in relation to the process' clients using the minisum location method; specified facilities requirements, including chemical yard specifications; procured and supervised internal and external facilities installation services; coordinated process relocation with the process' clients to minimize production downtime; supervised heavy-equipment relocation.
- Developed CAD drawings of process and associated facilites
- Utilized the PERT network model to manage project
- Generated air quality documentation in compliance to Maricopa county regulations
- Generated hazardous chemical documentation in compliance to OSHA regulations
- Installed a backup process to maintain production capability while the relocation was in progress.
HONEYWELL IAC
Wave Solder Process Modernization (1991)
Developed project economic justification, facility layout, and project plan; specified facilities requirements; procured and supervised internal and external facilities installation services; coordinated process changeover with the process' clients to minimize production downtime; developed and managed project contingencies; supervised heavy-equipment installation.
- Developed CAD drawings of process and associated facilities
- Utilized the PERT network model to manage project
- Successfully developed a contingency plan after discovering that a new Maricopa county air quality regulation would make illegal the new process installation
- Generated air quality documentation in compliance to Maricopa county regulations
- Installed the new process with only 4 hours of production downtime
- New process facilitated the phase-out of CFC solvents ahead of schedule