CHAPTER # 3
DESIGN CRITERIA FOR SEWERAGE SYSTEM
Purpose of this chapter is to outline basis of design against which evaluation of existing sewerage system will be made. Various consideration for design like design period, design flow, self-cleansing velocity minimum slope etc are discussed here in.
The local data available has been referred to; for this purpose.
3.2 INTRODUCTION
A system of sewers is provided for collecting domestic sewage, industrial wastewater and storm water. The designed system should be adequate enough and it should fulfill all the requirements for the community.
A comprehensive plan should be designed and all the sewers should be constructed according to the given plan.
3.3.1 Domestic sewage:
Generally 70-90% of domestic water consumption is taken as the average sewage flow.
Different criteria for the quantity of sewage flow from different agencies are given in Table 3.1:
Table # 3.1
Quantity |
WASA |
PPHED |
Domestic sewage |
80 90 % of average water consumption. |
80 % of average water consumption in residential area. 90 % of average water consumption in commercial area.
|
3.3.2
Infiltration:It is the water, which seeps into the sewer pipes used to convey sewage water.
Infiltration depends upon
Infiltration is generally taken equal to one third of average domestic sewage flow but for partially separate system, some storm water allowance is also taken into account. So in our local system infiltration is taken equal to 100% of average domestic sewage flow.
Different criteria for the quantity of infiltration from different agencies are given in the tables 3.2 & 3.3.
Table # 3.2
WASA LDA
Size |
Infiltration |
225 600 mm diameter > 600 mm diameter |
5% of average sanitary flow. 10% of average sanitary flow. |
Table # 3.3
PPHED
Description |
Infiltration |
Above sub soil water Below sub soil water |
40 lpd/mm-km 80 lpd/mm-km |
As in water consumption, the rate of sewage production will vary according to the season of the year, weather conditions, day of week and also time of day. So every system should be designed for peak sewage flow.
In a residential district the greatest use of water is in the early morning.
For moderate size of and city peak sewage flow=3* average sewage flow.
Some designers use the following formula:
Peaking Factor = 3.54 - Q 0.292
Where
Peaking Factor = Qp/ Q
Q
p = peak sewage flowQ = Average sewage flow
Criteria for Peaking Factor according to different agencies in Punjab are given in table 3.4 and 3.5:
Table # 3.4
WASA-LDA
AVERAGE SEWAGE FLOW |
Peaking Factor |
Up to 28 L/S |
4 |
28 56 L/S |
3.4 |
56 112 L/S |
3.1 |
112-280 L/S |
2.7 |
280 560 L/S |
2.5 |
560 1130 L/S |
2.3 |
1130 2800 L/S |
2.15 |
2800 5600 L/S |
2.08 |
> 5600 L/S |
2 |
TABLE # 3.5
PPHED:
Population (Thousands) |
Peaking Factor |
Up to 5 |
4.5 |
5 ------ 10 |
4 |
10 ----- 25 |
3.5 |
25 -----50 |
3.25 |
50 ----- 80 |
3 |
80 ----- 100 |
2.75 |
100 ---- 200 |
2.5 |
> 200 |
2 |
Sewers are designed to flow under gravity. All the equations applicable for open channel flows are valid for designing. Mannings formula commonly used is:
V= 1/n R2/3 S
½Where
n = Mannings roughness co-efficient depend upon type of material of pipe.
n = 0.013 ----- 0.015 (For R.C.C. Pipes)
R = hydraulic radius = flow area / wetted perimeter
S = slope of sewer line.
3.6
DESIGN OF SEWERSThe first step in design of sewers is the estimation of the flow, which they will receive.
Design flow:
The design flow can be calculated from the following formula.
Design flow = peak domestic flow + peak industrial waste water flow + infiltration + Storm allowance.
In our case peak industrial waste water flow is equal to zero.
Storm allowance = 100% of peak domestic flow.
Self cleansing velocity:
It is the minimum velocity that would keep the particles in waste water in motion in the bottom of the sewers.
For domestic sewage self cleansing velocity ranger from 0.6 ----- 0.8 m/s. For storm sewage higher velocity is desired, as the specific gravity of the particles in storm run off is more. So minimum recommended velocity for storm Sewers is 1.0 m/s.
Criteria for minimum self cleansing velocity according to different agencies are given in the table 3.6.
Table # 3.6
Description |
Minimum Velocity |
|
WASA LDA |
PPHED |
|
For domestic sewers |
0.6 m/s |
0.8 m/s |
Minimum slope:
It is the slope corresponding to the minimum velocity. The table 3.7 gives the slope for a velocity of 0.6 m/Sec for different sizes:
Table # 3.7
Size (mm) |
Slope (m/m) for 0.6 m/s |
225 |
0.0028 |
300 |
0.002 |
375 |
0.0015 |
450 |
0.0012 |
525 |
0.001 |
600 |
0.0008 |
675 |
0.0007 |
750 |
0.0006 |
900 |
0.00045 |
Maximum Velocity:
To avoid the erosion of pipe material there is a limit of maximum velocity, which is generally 2.4 to 3.0 m/s.
Minimum Size of Sewer:
By WASA LDA:
Minimum size of sewer is 225 mm.
Minimum Cover:
Minimum cover to the sewer is provided so that the house sewer may join the public server. House sewers are generally laid at 2% slope. Cover is also provided to protect the sewer from traffic load.
Usually 0.8 to 1.0 m cover is suitable for most suitable for most situations.
PPHED:
Cover = 0.8 m
Invert level:
The level of the inside bottom of the sewer is called invert level.
It is calculated by:
Invert level = Ground level cover thickness diameter of sewer pipe
3.7 DESIGN DEPTH OF FLOW
Sanitary sewers are designed to flow at depth from half to full at the design flow. In case of sanitary sewers, organic materials get decomposed evolving gases, so sanitary sewers are not designed to flow full. On the other hand, storm sewers are designed to flow full as they do not carry organic materials.
So in order to provide air space for sanitary sewer, the design flow may be increased by a certain factor. This increased flow is used to design the sewer.
Fa = Qf/Qd
Where
Fa = flowing full factor
Qf = flowing full flow
Qd = Design flow
The general criteria being used by WASA LDA and PPHED is given in table 3.8.
Table # 3.8
Sewer size (mm) |
Fa = Qf / Qd |
|
WASA LDA |
PPHED |
|
225 ----- 375 450 ----- 1200 > 1350 |
1.43 1.33 1.25 |
1.33 1.25 1.11 |
3.8 MANHOLES:
A manhole is an opening constructed in a sewer to provide a convenient access to the sewer for observation and maintenance purpose.
A typical sketch of manhole is shown in fig 4.1.
3.8.1 Requirements
3.8.2 Locations
Distances in straight depend upon cleaning method. Where mechanical means can be used then large distance b/w manholes, if manual cleaning then small distance b/w manhole.
Different criteria for the spacing of manholes by different agencies are given in table 3.9 & 3.10:
Table # 3.9
WASA LDA
Description |
Spacing |
Lateral & Secondary sewers For 375 mm diameter For 450 750 mm diameter For > 900 diameter |
30 m 100 m 120 m 150 m |
Table # 3.10
PPHED
Size (mm) |
Spacing (m) |
225 ---- 300 375 ---- 600 675 ---- 975 1050 --- 1500 > 1500 |
30 50 60 100 120 150 |
3.9 DROP MANHOLES
Drop manholes are provided when difference b/w the inverts of two sewers is more than 0.6 m.
The X-section of a drop manhole is shown in fig 4.2.
3.9.1
Purpose of Drop Manhole
3.10 SEWAGE PUMPING STATION
Pumping is required when basement are deep, terrain is flat, obstacles lie in the path of sewer, the receiving stream is higher then the sewer outlet, or when gravity flow is desired through an above ground treatment plant.
3.10.1
Need / Purpose of Pumping
3.10.2 Pumping Station
It consist of
Dry well is used to install machinery like motors, pumps switches etc. Dry well should be large enough to accommodate all the machinery.
Wet well receives sewage to be pumped. Ventilation is provided to wet well to prevent excessive condensation and accumulation of odour. Manholes or other means of entrance is provided.
The general design considerations are as follows,
In Pakistan 50% stand by capacity is provided.
There should be alternate arrangement for power as well.
WASA recommends having two different sources of electricity.
PPHED recommends an additional pump with 50% standby capacity.
3. Pumps should be of self priming type foot value is not provided.
4. Each pump should have its own suction pipe.
For small pumps = 10 min.
For large pumps = 20-30 min.
Also pump should run at least 2min.
Cycle time is defined, as the time required filling up and emptying the well.
Cycle time = to empty +time to fill.
Detention time should be less then 30 minutes otherwise sewage gets putrefied.
3.12 OPERATING VOLUME OF WET WELL:
Two important considerations for sizing of wet well.
Pumps should run at least for 2 minutes.
The time b/w successive starts called the cycle time, should be more than minimum time specified by the manufacturers.
Generally for small and large pimps cycle time is 10 minutes and 20-30 min respectively.
Formula to find out the operating volume of wet well.
Cycle time = Time to empty + Time to fill
Time to empty = V/(P-Q)
Time to fill= V/Q
Where V = Operating Volume Of Wet well.
P= Pumping rate (pumping capacity)
= Peak sewage flow
Q= Waste water flow
Cycle Time = t= V/(P Q) + V/Q .(A)
Differentiating W.R.T Q
dt/dQ =V/(P Q)2 V/Q2
Equating dt/dQ = 0
V/(P Q)2 V/Q2 = 0
V/(P Q)2 = V/Q2
(P Q)2 Q2 = 0
P2 Q2 2PQ Q2 = 0
P2 = 2PQ
Q = P/2
So cycle time will be minimum when wastewater flow is half of pumping rate.
Put Q = P/2 in equation (A)
tmin = V/ (P-P/2) + V/P/2
=V/P/2 + V/P/2
=2V/P/2
tmin = 4V/P
There are two extreme conditions.
i) For Q=0, t ® ¥
It implies that for Q = 0, the well dose not get filled and we do not need to start the pump.
ii) For Q=P, t ® ¥
In this Case, the level of sewage in the well remains constant and hence the pump can not be stopped.