SEPARATE GARAGE (RCA BARN) CONSTRUCTION
Page 5
Monday, 21 Apr:  pumper and first of two concrete trucks arrives.
Began pour at corner sonotube, doing about 1 quarter of the pad at a time. 
Pad finished in about 3 hours. Nearly 20yds of concrete used, 2 full trucks. 
Pad hand finished by steel trowels. Still overcast, so crew had to wait awhile for surface water to evaporate.
Tuesday, 22 Apr:  Work being inspected by Boxer.  Damp areas are residue from concrete curing agent (sealer), applied by sprayer following hand finish.
Sat, 26 Apr: Concrete still curing. You can clearly see the corner pier. 