ESSENTIALS  OF  PROJECT  MANAGEMENT

 

 

PM_41551

Identifying Project Participants

1. Who are the project participants?

2. How do stakeholders influence a project?

Identifying Goals and Objectives

1. What is project planning?

2. What is the project objective, and why should I clearly define it?

Determining Project Constraints

1. What constraints affect a project?

§         Performance standards                  Time                             Budget

2. How should I prioritize project constraints?

Identifying Project Activities

1. Why and how should I identify project activities?

2. What is a WBS and how can it help me plan a project?

3. How do I create a WBS?

 

Sequencing Activities

1. What is the purpose of sequencing activities?

2. What types of activities exist in a project?

·       Predecessor and successor activities           Concurrent activities       Dummy activities

·       Lag activities          Milestones

3. How do I begin sequencing my project activities?

Identifying Dependencies

1. How do dependencies affect activity sequencing?

·       Mandatory dependencies     Discretionary dependencies        External dependencies

2. What other sequencing dependencies should I understand?

·         Finish-to-start dependency   Finish-to-finish    Start-to-start    Start-to-finish dependency

3. How do leads affect activity sequencing?

4. How do lags affect activity sequencing?

Managing Risk and Resources

1. How do dependencies affect risk?

2. What is slack, and how does it affect risk management?

3. How can I manage resources when sequencing dependencies?

 

Understanding Activity Analysis

1. What is activity analysis?

2. How can I determine the appropriate level of detail needed in my activity analysis?

3. How does activity analysis affect activity sequencing?

Performing Activity Analysis

1. How can I complete an activity analysis?

2. What items can I include on an activity analysis form?

3. What items must I include on an activity analysis form?

4. How should I assign work?

5. What is the purpose of estimating time duration and cost for activities?

6. How can I estimate the time duration and cost of an activity?

·       Top-down estimating              Bottom-up         Parametric        Phased estimating

7. What assumptions about activity completion time may be involved in estimating duration?

8. How can I identify the results an activity should produce?

9. What is the importance of identifying potential problems and opportunities?

10. What should be done in the planning phase about potential problems and opportunities?

 

 

 

PM_41552

Fundamentals of Schedule Development

1. What is schedule development?

2. What are the benefits of schedule development?

3. What are two major constraints to consider during schedule development?

Mathematical Analysis Techniques

1. What are the two most widely known mathematical analysis techniques for schedule development?

Critical Path Method                   Program Evaluation and Review Technique

Project Network Diagrams

1. What are project network diagrams?

2. Why are networks used during schedule development?

3. What types of arrow charting can I use to create project network diagrams?

Activity-on-node method Activity-on-arrow method

4. Which method of arrow charting is more common?

Gantt Charts

1. What are Gantt charts?

2. What are some advantages and disadvantages of using Gantt charts?

3. How can I create a Gantt chart?

4. What can I do if the resources and schedule do not coincide?

 

Understanding CPM and PERT

1. What are CPM and PERT?

2. What are the benefits of scheduling projects using CPM or PERT?

3. What are the critical path and critical activities?

4. How can I calculate project duration using a project's critical path?

5. What are float and free float?

6. How do resources affect CPM and PERT schedules?

Scheduling with CPM

1. What are the steps for Critical Path Method scheduling?

2. What terms and calculations are important when discussing the Critical Path Method?

·       Earliest start time        Earliest finish time         Latest finish time           Latest start time

3. How is float calculated?

Compressing Activity Duration

1. What are methods of duration compression used during schedule development?

·       Crashing         Fast tracking     Assigning limited overtime          Implementing shortcuts

 

Fundamentals of Cost Estimating

1. Why is it important to know the resource rates when estimating costs?

2. How is historical information used when estimating costs?

3. How do activity duration estimates affect cost estimates?

4. What types of supporting details are necessary when creating cost estimates?

5. How are labor estimates used to complete cost estimates?

6. What are some project estimating pitfalls?

7. What problems can produce errors when I complete cost estimates?

8. How can I estimate costs for projects that are R&D oriented?

Organizational Financial Systems

1. What types of costs will a project incur?

2. What organizational financial issues can affect a project?

3. Why should I be aware of company financial cycles?

Project Budget Optimization

1. What factors should I be aware of when negotiating for a larger budget?

2. What actions can help me make the most of available funds?

 

 

 

 

PM_41553

Change Control Systems

1. What is project control?

2. What is project change control?

3. What is a change control system?

4. What are the objectives of a change control system?

5. What are some characteristics of a good change control system?

·       An emphasis on project success                  A focus on what is important

·       A system for taking corrective action            An emphasis on timely response

Methods of Controlling Change

1. What items do I need to control changes to a project?

2. What role do status meetings play in controlling a project?

3. What process can I use to accommodate change?

1. Assess the potential change

2. Modify the project plan

3. Examine alternatives

4. Navigate project procedures

5. Deliver sufficient information

4. What is a change control board?

5. What are some results of project change control?

 

Methods for Measuring Performance

1. Why is it important to measure project performance?

2. How can I determine whether a project is meeting its quality standards?

3. How can I determine the level of morale of the project team?

4. What methods can I use to measure project performance?

·       Variance analysis               Trend analysis               Earned value analysis

5. What calculations are used during earned value analysis?

·       Cost variance                                  Schedule variance         

·       Cost performance index                   Schedule performance index

Schedule and Cost Control

1. What is project control?

2. What items are used to control project performance?

3. Why is it important to control the project schedule, and how can I do so?

4. What items are used to control a project's schedule?

5. Why is it important to control the project cost, and how can I do so?

6. What items are used to control a project's budget?

 

Fundamentals of Performance Reporting

1. What is performance reporting, and why is it important?

2. How does performance reporting facilitate project control?

3. What is a reporting period?

4. How often should performance reports be produced?

5. How can performance reports be classified?

·       Routine           Exception          Special analysis

6. What is a progress report?

7. What is a status report?

8. How can I determine which performance reports are necessary for a project?

9. What are some frequent problems with progress reporting?

10. How does performance reporting affect project costs?

Reporting the Project Close

1. What steps should I follow to close a project?

1. Create a task list                               2. Communicate about the close

3. Celebrate accomplishments               4. Release the resources

2. What are close-out reports?

3. What information should be included in a project's final report?

4. Why is close-out reporting often neglected?

 

Who are the project participants?

In a given project, the participants will include at least the project manager and the project originator. In rare instances, these roles may be filled by one individual, but usually the project manager is someone who manages the project for the originator. The project originator may be the manager's boss or a customer. Other individuals or groups that can be considered project participants include people assigned to work on the project; the public, if they are affected by the outcome of the project; the parent organization, who staffs the project; and customers, if they use a product created by the project.

 

Any individual, group, or organization involved in a project or whose interests may be influenced as a result of project achievement can be considered project stakeholders. As a project manager, it is important for you to identify all the stakeholders for your project and determine their expectations for it. Managing stakeholders' expectations reduces conflict and leads to project success.

 

How do stakeholders influence a project?

Stakeholders have various levels of influence on a project:

·       Some stakeholders simply need to feel appreciated throughout the project process.

·       Some stakeholders outline specific requirements they want the project to meet. You should advise the stakeholders if their requirements for a project are not going to be completely fulfilled.

·       Some stakeholders have specific requirements they want the project to meet, and their stake in the project is large enough that you should strive to meet their needs under most circumstances.

You should adjust the effort you put into meeting stakeholders' needs based on the level of influence they have on the project.

 

What is project planning?

Project planning is often considered the most important step of the project management process. During project planning, the project manager and stakeholders define the project's goals, then determine how to meet those goals. Planning helps you avoid costly changes during the process of completing the project by ensuring that the work is done correctly the first time.

 

What is the project objective, and why should I clearly define it?

A project's objective is a written statement that details what goals the project should accomplish. Clearly defining the project's objective enables you to know exactly what you need to accomplish. Regardless of how hard you work at project management, if the project does not accomplish the correct goal, the project fails. Therefore, you must have a clear objective you can work toward to ensure that you accomplish all that is expected of the project.

 

What constraints affect a project?

There are three constraints that affect a project:

Performance standards             Time                 Budget

·       Performance standards

Performance standards are the goals set forth for a project. Since a project cannot be successful if it does not accomplish the goals the stakeholders set for it, performance standards are vital to a project. Performance standards are constraints because they can dictate how project work must be completed. When considering the performance standards of a project, you should always look deeper than the initial goals the project originator or other stakeholders set.

 

Frequently, stakeholders do not explicitly state every goal they want a project to achieve. Nevertheless, you should understand that stakeholders will judge the success of the project based on their expectations, even if those expectations were not clearly defined. Therefore, while planning a project, you should discover as much information as you can about stakeholders' expectations.

·       Time

The amount of time you are given to complete a project will affect every aspect of it. Time can greatly affect the amount of resources needed to complete a project, as well as the order in which you complete tasks and activities. As you plan your project, you should keep in mind any organizational or political issues that could arise and affect your ability to complete the project on time.

·       Budget

Budget allocations will influence your ability to accomplish a project by determining what resources you can use to achieve your project's objective. Your project budget will also influence whether you can achieve the specified performance standards within the allotted time.

Often, before taking responsibility for a project, project managers act as consultants for project originators. The consultation is a valuable opportunity that can increase your chances for success as a project manager. If you are given an opportunity to work as a consultant before a project begins, be sure to research the project thoroughly before making a budget proposal. You should examine any organizational or political influences that could affect the project completion.

 

How should I prioritize project constraints?

Before you can effectively plan a project, you must prioritize the performance standard, budget, and time constraints. Prioritizing constraints is essential. You will make strategic decisions based on the constraints so that you can make the best use of the project resources.

 

As a project manager, you will have to make trade-offs based on one or more of the constraints. How well you compromise and make those trade-offs affects the success of the project.

 

Therefore, you should determine the most important constraint, or the driver, since it will drive the activities needed to complete the project. If you, as the project manager, fail to adjust for this constraint, the project will fail even if you adjust to the other constraints. The least important constraint, or the weak constraint, is not as important to the success of your project. The remaining constraint is the middle constraint.

 

As you prioritize project constraints, remember that you do not decide which constraint is most important; rather, you identify the relative importance of each constraint based upon the expectations the project originator has for the project. You must determine these expectations and how they influence the constraints, so you can manage the project appropriately.

 

Once you have identified the driver, middle, and weak constraints for your project, you will be prepared to begin planning your project. Understanding the level of importance of each constraint will provide you with a strategic tool for managing your project. For example, since the weak constraint is not as critical for project success as the driver and middle constraints, it often provides a source of flexibility for the project.

 

Imagine you are working on a project in which time is the driver and performance standards are the middle constraint. If your project falls behind schedule, you could make use of the flexibility in the weak constraint by using your budget to add resources that can move the project back on schedule.

 

Why and how should I identify project activities?

It is essential to the success of your project to identify all the activities, or elements of work, that must occur in order to complete the project. As you plan a project, it is important to identify every activity, so you can budget the time and resources needed to complete them. Failing to identify all of the activities can cause unexpected problems. One way to ensure that you identify all of a project's activities is to use a work breakdown structure.

 

What is a WBS and how can it help me plan a project?

A WBS is the foundation for project planning and is vital to project management. A WBS helps you identify complex project activities and divide those activities into smaller activities. Focusing on smaller activities simplifies estimating the duration, cost, and resource consumption for the project.

 

How do I create a WBS?

To create a WBS, the first step you should take is to brainstorm the different project activities. If other people will be working on the project with you, include them in the brainstorming process. Write down every possible activity that will need to be completed to achieve the project's goals. A helpful way to record the activities is to write individual activities on sticky notes. This method will facilitate grouping and arranging the activities later.

 

The second step you should take to create a WBS is to refine your activity list. It is possible that you will create multiple strategies for accomplishing a project's goals. Each strategy may consist of a different set of activities. If this is true for your project, you should choose the best approach for achieving the goals and make any necessary adjustments to the set of activities. In addition, you may discover that some activities need to be broken down into smaller ones, while others may need to be combined. Use your best judgement to determine a final set of activities.

 

After you have identified and recorded the project activities, group the sticky notes into logical categories, such as ''Purchasing,'' ''Installing,'' or ''Testing.'' As you do so, look for any places where you may have forgotten activities. Once you have completely organized the categories, review the entire set again to ensure that you have not forgotten any activities.

 

What is the purpose of sequencing activities?

The purpose of sequencing project activities is to arrange them in a logical order for completion. Since activity sequencing enables you to determine the order of activity completion that best manages the time and resources available for completing the project, it is an important part of scheduling.

 

What types of activities exist in a project?

Part of activity sequencing is recognizing that there are different kinds of activities and understanding the relationships among them. There are several types of activities that may be part of your project:

·       Predecessor and successor activities

·       Concurrent activities

·       Dummy activities

·       Lag activities

·       Milestones

·       Predecessor and successor activities

Predecessor activities must be finished before other activities can begin. The activities that follow predecessor activities are known as successor, or dependent, activities. Successor activities are ''links'' in the chain of activity flow from a project's start through its completion. Once a successor activity is completed, it can either be a predecessor for other activities, or it can be the final activity of a project. Some successor activities can be completed concurrently.

 

Since a dependency exists between predecessor and successor activities, they are said to produce sequence constraints. Since sequence constraints dictate a specific order in which some activities must be completed, they limit the flexibility you have in scheduling.

 

·       Concurrent activities

Concurrent, or parallel, activities are another type of activity that may be part of your project. Since concurrent activities can be completed simultaneously, they can shorten the duration of a project. When scheduling concurrent activities, be sure there are enough resources available to execute them at the same time.

 

·       Dummy activities

Another type of activity you may include in your project schedule is a dummy activity. Dummy activities are used to demonstrate how concurrent activities relate to one another, and they can be used to improve the layout of your project schedule. Dummy activities neither expend resources nor require time to complete.

 

·       Lag activities

Another type of activity you may encounter in your project is a lag activity. Lag activities do not require the use of any resources since they occur when there is a waiting period, or ''lag'' time, between the time that one activity is completed and the next one begins. Although there is no work associated with lag activities, it is helpful to include them in your project schedule so that you do not forget that the lag time exists.

 

·       Milestones

Milestones are another type of activity commonly used in project scheduling. Milestones do not require work, use time, or expend resources. They are used in project scheduling to indicate that a series of activities is complete, to represent progress points, or to denote when a meeting should be held. Although milestones appear along the project schedule, it is important to note that they do not affect work flow.

 

How do I begin sequencing my project activities?

You can begin sequencing your project's activities by creating a Program Evaluation and Review Technique (PERT) chart. A PERT chart will help you determine the best sequence for your project's activities. You can create a PERT chart by using the set of activities you identified in the work breakdown structure (WBS). The sticky notes you used for the WBS will facilitate the process of developing a PERT chart.

 

Begin by determining which of the activities have or do not have successors or predecessors. Activities that have successors but no predecessors are starting points for your PERT chart. Activities that have successors and predecessors comprise the pathways from the starting points to the end points of your chart. Activities that have predecessors but no successors are ending points for your PERT chart.

 

A good way to convert your WBS sticky notes into a PERT chart is to arrange them on a wall in the sequence in which the activities must occur. Using sticky notes allows you to arrange the activities in various ways to determine the best order of completion for a project.

 

When scheduling the activities in a project, you can make strategic choices about how you sequence the dependencies among activities. Therefore, you should try as many combinations as possible and analyze the benefits and drawbacks of each combination. Doing so will enable you to develop the best possible sequence for the activities in your project.

 

How do dependencies affect activity sequencing?

Dependencies dictate when an activity can be performed, which affects activity sequencing. There are three categories of dependencies you should understand:

Mandatory dependencies                       Discretionary dependencies                    External dependencies

·       Mandatory dependencies

Mandatory dependencies, or hard logic, are restrictions specific to an activity. They require that one activity be completed before another can begin. For example, when building a house, the foundation must be finished before raising the walls. Mandatory dependencies are static, which means that they never change.

 

·       Discretionary dependencies

Discretionary dependencies, or soft logic, are restrictions outlined by the project manager based on two factors. First, if there are multiple methods of doing an activity, the project manager should choose the best method. For example, if you have the option to use one of two software programs, you can use the program you think best suits your needs for activity completion. Secondly, if there are many activity sequences, you can pick the one most desirable for achieving the project's objective.

 

As a project manager, you should use discretionary dependencies only after careful consideration since they can affect the activity sequence throughout an entire project.

 

·       External dependencies

External dependencies are restrictions that result from activities outside the project itself. This type of dependency creates restrictions that are beyond your control. External dependencies include such things as unfavorable weather conditions at a construction site or an important package delayed in the mail.

 

What other sequencing dependencies should I understand?

There are specific relationships that occur between certain project activities. These relationships create dependencies between the activities and affect how you schedule activities. There are four dependency relationships that affect activity sequencing, and they may fall under the categories of mandatory or discretionary dependencies:

·       Finish-to-start dependency

·       Finish-to-finish dependency

·       Start-to-start dependency

·       Start-to-finish dependency

 

·       Finish-to-start dependency

The finish-to-start dependency is the most common activity relationship you will encounter when creating a project schedule. In the finish-to-start dependency, Activity X must finish before Activity Y can start. For example, if you were installing a LAN at your office, you would need to purchase cables before you could install them.

 

·       Finish-to-finish dependency

Another dependency you will encounter while creating a project schedule is the finish-to-finish dependency. In the finish-to-finish dependency, Activity X must finish before Activity Y can finish. This dependency can increase the efficiency of a project. For example, for a LAN installation project, you could begin connecting computers to the network before all of the offices are wired. By making the office wiring finish-to-finish dependent on connecting computers to the network, you allow work to begin sooner than if the activities were finish-to-start dependent.

 

·       Start-to-start dependency

The start-to-start dependency is another activity relationship that will affect how you schedule activities. In the start-to-start dependency, Activity X must start before Activity Y can start. In the LAN project, you could make developing training sessions start-to-start dependent on creating manuals since you could begin setting times for training sessions before all the training materials have been produced.

 

·       Start-to-finish dependency

A start-to-finish dependency can also occur between activities in a project. However, this relationship is usually less common than the finish-to-start, finish-to-finish, and start-to-start dependencies. In the start-to-finish dependency, Activity X must start before Activity Y can finish.

 

How do leads affect activity sequencing?

When two activities are controlled by a finish-to-start dependency, a lead represents an accelerated time-span between the completion of a predecessor activity and the start of its successor. For example, if Activity A is a predecessor to Activity B, and there is a five-day lead, then Activity B can start five days before Activity A is finished.

 

How do lags affect activity sequencing?

In a finish-to-start dependency, a lag is the time between the finish of a predecessor activity and the start of its successor. Suppose that Activity C is a predecessor for Activity D, and once Activity C has been completed, Activity D cannot begin until two days later. The two days between the completion of Activity C and the start of Activity D is a lag.

 

How do dependencies affect risk?

Activity dependencies can increase or decrease a project's risk of failure since they can influence whether a project remains on schedule, on budget, and within the performance standards. Therefore, as you sequence the activities, you need to determine how the activity dependencies will affect the outcome of the project.

 

What is slack, and how does it affect risk management?

Slack is the difference in time required to complete concurrent activities. Frequently, you may not need the same amount of time to complete two concurrent activities. As a general rule, you should remember that slack decreases risk since the extra time can often be used to enhance the quality of work being completed or to reduce costs by completing an activity more slowly and using fewer resources.

 

How can I manage resources when sequencing dependencies?

As you schedule the activities in your project and establish dependencies, you must keep in mind the amount of resources needed and available for each activity. For example, if you want to make two tasks concurrent to shorten the amount of time needed to complete them, you must first determine whether you have the necessary resources at your disposal to complete the activities at the same time.

 

Resource availability can also affect the time needed to perform an individual activity. If the ideal resource for an activity is unavailable, you may need to consider an alternate resource. The alternate resource may or may not affect the activity's duration.

 

What is activity analysis?

Activity analysis is the process of studying activities in your project so that you fully understand all aspects of the project. Activity analysis will help you gather data, write specifications, and develop estimates for activities. In addition, analysis will help you assign tasks appropriately and identify potential problems that could disrupt progress. Collecting extensive information about each activity will not only help you understand all the elements of your project but also help you manage the project and control its performance.

 

How can I determine the appropriate level of detail needed in my activity analysis?

The appropriate level of detail needed in your activity analysis is often determined by the complexity and expense of your project. Complex and expensive projects usually require more in-depth analysis than smaller, less sophisticated projects. A mistake in a costly project could have more serious consequences than a mistake in an inexpensive project.

 

There are two issues you should consider when determining the level of analysis to complete for your project. The first issue is how closely involved you will be with the project as it is completed. If you have a high level of involvement in the project work as it is completed, your activity analysis will not need to be as detailed as it would need to be if you have little involvement as the work is performed.

 

The second issue that can help you determine the level of activity analysis needed is the abilities of the people working on the project. If your project team is talented and motivated to achieve the project's goals, they will need less activity detail listed on the activity analysis forms in order to perform the work correctly.

 

How does activity analysis affect activity sequencing?

As you analyze the activities in your project, you may discover information that influences how you should schedule them. Therefore, as you perform activity analysis, you may need to return to your PERT chart and make changes to the dependency sequences. As a result, activity analysis helps you finalize the project schedule.

 

How can I complete an activity analysis?

The best way to analyze project activities is to create an activity analysis form and complete one for every activity. How you design an activity analysis form depends on the level of analysis you plan to do.

 

What items can I include on an activity analysis form?

Since the level of detail you need in your activity analysis will vary by project, there are many items you should consider adding to an activity analysis form:

·       An activity name. It is helpful to assign specific names to each activity. The activity name is usually the name it was given in the WBS. For example, some activity names might include ''Train employees'' or ''Install software.''

·       An activity number. Numbering each activity can help you organize the work for a project. Base your activity numbers on the WBS for the project. Start by numbering each of the categories into which you divided the WBS activities. Then, number the activities under each category. For example, imagine category two on your WBS is ''Purchasing'' and under this category the third activity is to ''Purchase printer.'' The number for this activity would be 2-3.

·       Predecessor and successor activities. Including an activity's predecessor and successor on the activity analysis form can be helpful since these activities are dependent on each other. You can simply list the predecessor and successor activities' names and numbers, which will help you locate them on the WBS.

·       Equipment and supplies. In order for each activity to be completed smoothly, it is helpful to list all the equipment and supplies needed. Forgetting equipment and supplies can cause problems or delays in the project. In addition, you may want to note on your activity analysis form where the equipment and supplies can be obtained.

·       ''Must finish'' or ''must start'' dates. Occasionally, activities may have dates upon which they must start or finish. These dates often depend on the scheduling of the surrounding activities. For example, if you want to train employees on a new task, and you intend to give them a handbook, you might assign a ''must finish'' date for printing the handbooks. A late activity completion time could disrupt the project schedule. Since you can only estimate how long most projects will take to complete, only use ''must finish'' and ''must start'' dates when necessary.

·       Milestones. Since a project manager must determine whether work is being completed on time, on budget, and within the performance standards, you should assign checkpoints, or milestones, at which progress can be monitored. The number of milestones needed will vary among activities based on activity duration and complexity.

 

What items must I include on an activity analysis form?

Regardless of the level of analysis you intend to complete, the activity analysis form should include four specific details:

·       Who is responsible for completing the activity

·       An estimate of activity duration

·       An estimate of activity cost

·       The results the activity will produce

 

How should I assign work?

Assigning who will complete each activity is a critical planning step. The person responsible for an activity has a great deal of influence on the outcome of the activity. As you assign work, you should ask yourself several questions to determine whether an individual is the right person to complete an activity:

·       Does the person have the skills needed to complete the activity within the specifications?

·       Does the person have time to work on the activity at the time specified in your schedule?

·       What factors, such as other responsibilities and commitments, will affect the person's ability to complete the activity?

 

If you do not have enough information about an activity to assign it, or if you cannot find the right individual, you should record as much information as possible about the skills an individual would need to complete the activity. Doing so will help you assign the activity at a later time.

 

What is the purpose of estimating time duration and cost for activities?

Estimating the time duration and cost of activities are important steps for successfully planning a project. The purpose of assessing activity duration is to determine how long a project will take to complete, as well as the number of work shifts needed for a project. Since they will be able to make the most reasonable estimates based on their experience, project team members should be involved in assessing activity duration.

 

Estimating cost involves identifying the cost of the resources needed to complete a project. When completing a cost estimate, you will always have a degree of uncertainty. The level of uncertainty depends on your experience, as well as the type of project. Generally, throughout the life of a project, more details become available and the cost estimate can be refined.

 

How can I estimate the time duration and cost of an activity?

There are several types of estimating you can use to determine the time duration and cost of project activities:

Top-down estimating     Bottom-up estimating     Parametric estimating    Phased estimating

·       Top-down estimating

Top-down estimating utilizes a previous project's work breakdown structure (WBS) to compute the duration of a similar new project. When using top-down estimating, you assume that estimates for the past project accurately apply to the new one. It is important that the degree of similarity between the projects is very close, or estimates for the new project will be inaccurate.

 

Top-down estimating is generally useful when you do not have a finely detailed WBS for a new project. Another name for top-down estimating is ''analogous estimating.''

 

·       Bottom-up estimating

Bottom-up estimating involves both duration and cost estimates. For bottom-up estimating, duration and cost estimates start at the lowest level of activity on the WBS, then work up toward the highest level of activity. Once duration and cost estimates are completed for each activity, they are combined into a single time and cost forecast for the entire project.

 

The benefit of this technique is that it yields accurate total time and cost estimates for a project. Accurate estimates allow for realistic project scheduling and budget planning.

 

·       Parametric estimating

The parametric estimating technique uses historical data and other variables to calculate statistical relationships, resulting in a cost estimate. This technique takes a basic variable and uses it as a multiplier to figure the cost for an entire project. For example, if homes in a specific subdivision generally cost $85 per square foot, and the home you are building is 1200 square feet, the total project cost estimate can be found by multiplying the two. The cost estimate for your home is $102,000.

 

When using parametric estimating, it is important to understand that the cost estimates are not always accurate. The estimates can range from less than 25 percent accurate to better than 75 percent accurate, depending on the statistical data used to make the calculations. Project stakeholders must understand that parametric estimates are susceptible to change; otherwise, they run the risk of finalizing project goals based on unrealistic estimates.

·       Phased estimating

Project managers may have difficulty estimating a project's entire cost at the outset of the project if there is not enough information available to understand all of the project details. The phased estimating technique allows a project to be broken into phases, with separate cost estimates for each phase, rather than completing an estimate for an entire project.

 

As each phase of a project is finished, estimates for the next phase are completed. This estimating method is generally easier to use than other methods and results in a more accurate cost estimate. In addition, phased estimating protects you from the risks involved with committing to cost estimates for the entire project before you have enough information to estimate the overall costs accurately.

 

What assumptions about activity completion time may be involved in estimating duration?

Estimating activity duration may involve three assumptions that are combined to determine the expected duration of an activity:

·       Optimistic completion time assumes that an activity will proceed from start to finish without interruptions or obstacles.

·       Pessimistic completion time assumes that every possible activity-related problem will occur prior to activity completion.

·       Most likely completion time assumes that some difficulties will arise during the course of an activity.

 

How can I identify the results an activity should produce?

Two types of results an activity may produce include specifications and deliverables. Specifications are detailed performance standards that must be achieved when an activity is completed. Deliverables are end products that are produced by an activity. On the activity analysis form, you should identify the most important specifications or the ones that will have the greatest influence on how the activity must be completed.

 

What is the importance of identifying potential problems and opportunities?

Within every activity exists the potential for problems and opportunities. Since potential problems can endanger the success of your project and potential opportunities can increase the chance of success, you must plan for both of these situations.

 

What should be done in the planning phase about potential problems and opportunities?

The more action you take during the planning phase to manage potential problems, the more likely problems can be resolved effectively or avoided completely. Similarly, you need to plan for opportunities in order to take advantage of them when they arise. Some project managers create a document called a Control Point Identification Chart, which helps them manage potential problems and opportunities for each activity.

 

The Control Point Identification Chart helps you identify what could go wrong or right, when something might go wrong or right, and how to overcome the problem or take advantage of the opportunity. To create a Control Point Identification Chart, brainstorm what problems or opportunities could occur while an activity is performed. Then, identify warning signals that can alert you if the problem or opportunity occurs during the activity. Finally, list strategies for managing the problem or opportunity.

 

 

 


What is schedule development?

Schedule development is the process by which a project manager arranges a project's main activities into a schedule. Project scheduling ensures effective time management during the project and ensures that a project is completed within a reasonable time frame.

 

During schedule development, you should assign a start and end date to each activity. When doing so, you must consider activity relationships, activity duration, and resource availability.

 

What are the benefits of schedule development?

Schedule development provides several benefits for a project:

·       A schedule establishes activity and project start and end dates. A project's life cycle begins with the first activity on the schedule, and ends with the final activity on the schedule. The end date for the final activity should reflect the end date for the entire project. Since the project end date is based on the time estimates for each activity, it should represent a practical goal for the project manager and team.

·       A schedule facilitates monitoring activity completion. A schedule can be used to monitor activity completion, which ensures that the project will be completed within a practical amount of time. Using the schedule as a monitoring tool is beneficial since incomplete activities can disrupt the timing of the rest of the project.

·       A schedule illustrates activity interdependence. Related activities are grouped together on a schedule enabling you to discover potential conflicts between activities. Recognizing conflicts before the project begins helps identify and avoid problems during the project life cycle.

·       A schedule dictates when project team members work. Since all project team members do not need to be present for each project activity, a schedule is beneficial because it establishes the dates and times when team members need to complete work.

 

What are two major constraints to consider during schedule development?

When developing a project schedule, you should consider two major constraints. First, a project completion date may be imposed by an outside entity. For example, if your company wants to redesign one of its products, management may dictate the design completion date.

 

A second constraint to consider during schedule development is the time frame expectations of project stakeholders. Since stakeholders expect to see progress, you should include milestones on project schedules. The milestones enable stakeholders to verify what progress has been made.

 

What are the two most widely known mathematical analysis techniques for schedule development?

The following are the two most widely known mathematical analysis techniques for schedule development:

Critical Path Method                             Program Evaluation and Review Technique

·       Critical Path Method

The Critical Path Method (CPM) is a schedule development technique used to identify the least flexible activities in a project based on float calculations. Float is the length of time that the start of an activity can be deferred without affecting the completion date for the entire project.

 

Float calculations are used to determine the longest sequence of activities that cannot be completed concurrently, which yields the earliest time of project completion. This long sequence of activities is the critical path. Any activity delays on the critical path affect the duration of the whole project.

 

Project managers use CPM to find a logical flow for project activities, identify where the critical path can be shortened, and determine where resources can be added to improve the project. In addition, CPM can be used to develop a crash plan for a schedule. Crash refers to the process of accelerating activity completion by adding resources. A crash plan illustrates the effects of crashing on individual activity duration and overall project cost.

 

·       Program Evaluation and Review Technique

The Program Evaluation and Review Technique (PERT) for schedule development is used to determine project duration based on three time estimates: optimistic, pessimistic, and most likely. PERT is used mainly for large-scale projects, since it can display considerable amounts of complex data in an orderly form. Project managers use PERT charts to determine which areas of a project require the most effort to stay on schedule.

 

 

 

 

 

 

What are project network diagrams?

Nodes and arrows on a project network diagram illustrate the activity relationships and completion sequences from the beginning of a project to the end. A network starts with an activity that does not have any predecessors and ends with an activity that does not have any successors. Network diagrams are generally constructed so that workflow starts on the left and proceeds to the right.

 

Why are networks used during schedule development?

Networks are used when planning a project's schedule for a variety of reasons:

·       Networks highlight dependencies among project activities

·       Networks identify the critical path

·       Networks indicate the time needed for each activity

·       Networks illustrate float and free float

 

What types of arrow charting can I use to create project network diagrams?

There are two methods of arrow charting used to create project network diagrams:

·       Activity-on-node method                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                     Activity-on-arrow method

 

·       Activity-on-node method

One way to create a project network diagram is to use the activity-on-node method. On an activity-on-node diagram, nodes, or boxes, represent activities, while arrows drawn between the nodes represent activity relationships.

 

·       Activity-on-arrow method

Another way to create a project network diagram is to use the activity-on-arrow method. This method uses arrows to represent activities, while the nodes represent events and demonstrate how activities relate to one another.

 

Which method of arrow charting is more common?

Activity-on-node is more commonly used than activity-on-arrow since many project management software programs use activity-on-node diagrams. In addition, activity-on-node diagrams can be created easily from a work breakdown structure created with sticky notes since the notes can become the nodes. Neither method is better than the other, and both allow you to schedule project activities and analyze dependencies among activities.

Gantt Charts

 

What are Gantt charts?

A Gantt chart is a bar chart that displays activity duration. The horizontal axis of a Gantt chart indicates the project schedule, while the vertical axis indicates the activities from the work breakdown structure. Symbols on Gantt charts denote such things as milestones and project concerns.

 

What are some advantages and disadvantages of using Gantt charts?

Using Gantt charts can be advantageous since they:

·       Incorporate the work breakdown structure to illustrate a project's activity sequence from start to finish

·       Show individual activity start and end dates

·       Summarize activity descriptions, which makes the charts easy to understand

·       Can be updated simply by adding or deleting lines and columns from the chart

·       Can be read easily by team members

 

Using Gantt charts also has some disadvantages, which include the inability to:

·       Illustrate activity dependencies

·       Exhibit the effects of early or late activity start times

·       Show variations in activity duration

 

How can I create a Gantt chart?

The information you need to create a Gantt chart is readily available in your activity analysis forms, which you should have created while planning the project. Use the following process to create a Gantt chart:

 

1. On the horizontal axis, create the headings Activity Name, Number, and Duration.

2. Add a fourth heading that includes time increments for the project schedule.

3. On the vertical axis, you should list all of the project activities.

4. Then, create bars that reflect the duration for each activity by matching the activities' start and finish times to the time increments on the horizontal axis.

 

You may find it helpful to differentiate the bars for critical activities from the bars for non-critical activities. You can do this by coloring or shading the bars. In addition, if an activity's duration is not as long as the time available for completing it, you can note the extra time, or float, with a line extending from the duration bar.

 

What can I do if the resources and schedule do not coincide?

After creating your Gantt chart, you may discover that there are certain periods of time in which you do not have enough resources available, such as project team members, to complete all of the activities. This is a common situation and can be remedied in one of two ways.

 

One way you can match your resources and schedule is to increase the number of resources. This practice is called resource loading. For example, if you do not have enough team members at certain times during the project, you may be able to use additional staff for a limited amount of time to complete all of the activities as scheduled.

 

The second way you can match your resources and schedule is to move the schedule so it accommodates the resources. This practice is called resource leveling. For the periods of time in which you do not have enough resources to complete the scheduled activities, you may be able to shift some of the work ahead or behind so that it can be completed when there are sufficient resources available.

 

 

 

What are CPM and PERT?

The Critical Path Method (CPM) and the Program Evaluation and Review Technique (PERT) are both techniques for network planning. Each shows a project as a sequence of activities, and each helps a project manager analyze an entire project or individual activities. In addition, CPM and PERT charts allow a project manager to analyze the relationships and dependencies among activities.

 

In the strictest sense, CPM is charted using activity-on-node diagrams, and PERT is charted using activity-on-arrow diagrams. However, in actual use, most project managers generally use a combination of features from PERT and CPM. In addition, most project management software programs combine aspects of the techniques as well.

 

What are the benefits of scheduling projects using CPM or PERT?

Using CPM, PERT, or a combination of the two provides several benefits. For example, both systems allow you to determine whether a project can be completed by a designated time. Another benefit is that CPM and PERT can show when individual activities need to be completed to achieve the overall project deadline. In addition, both systems can show which activities have leeway for when they need to start or end, and both systems can help you determine the critical path for a project.

 

What are the critical path and critical activities?

The critical path on a CPM or PERT chart is the longest chain of activities that cannot be completed concurrently. This path determines the minimum duration of the entire project. The activities on the critical path are called critical activities since missing a deadline on even one affects all subsequent activities and the overall project deadline. Identifying the critical path and critical activities on a project schedule can help you determine how priority changes affect a project and which activities are most affected by the changes. In addition, identifying the critical path and critical activities can help you determine where you can adjust the schedule to make up for lost time.

 

How can I calculate project duration using a project's critical path?

To calculate the project duration from an activity-on-node diagram, begin by adding the duration for each activity, represented by a node, from start to finish through the network. If there is more than one possible path to follow, determine the duration times for each path. The path that takes the longest amount of time to complete is the critical path, and it represents the earliest possible completion date of the project.

 

What are float and free float?

The term float refers to the length of time that the start of an activity can be deferred without affecting the completion date for the entire project. Free float, or slack, differs from float in that it refers to the length of time that an activity can be deferred without affecting the earliest start time of any immediate successor activities. Any activity that cannot be deferred without affecting the project completion date or another activity's start date is said to have zero float. Calculations of float and free float are completed for each activity in a network. These calculations are useful if a project manager has to change the project schedule.

 

It is important to understand that on a project network diagram, the critical path is the longest path with the least amount of float. Therefore, most of the activities along the critical path have little float time, but they do not necessarily have zero float.

 

How do resources affect CPM and PERT schedules?

You should keep in mind that resources are not shown on CPM and PERT charts. Your CPM or PERT schedule might look good on paper, but it also may be unrealistic. As you create a CPM or PERT chart, you should assume that the necessary resources are available so that you can develop the schedule without continuously checking on resource availability. However, once you have drafted the project schedule, you must take resource availability into consideration. The number and type of resources you use will affect whether activities can be completed within the specified durations.

 

What are the steps for Critical Path Method scheduling?

There are nine steps for CPM scheduling:

1. Develop an activity list that includes all main project activities.

2. Use the activity list to construct an arrow diagram.

3. Estimate activity durations for each activity on the network diagram.

4. Examine the activity sequence represented on the network diagram to ensure that it is realistic.

5. List the respective duration times and costs next to each activity.

6. Determine the critical path of the project.

7. Assign calendar dates to each activity on the diagram.

8. Compare the critical path of the CPM chart to the mandatory project dates to make sure you will complete the project on time according to stakeholder expectations.

9. When necessary, apply methods to reduce activity duration so that the project can be completed on time.

 

What terms and calculations are important when discussing the Critical Path Method?

When discussing CPM, it is imperative that you understand four terms and their respective calculations:

Earliest start time                                                         Earliest finish time                                                         Latest finish time                                                                      Latest start time

·       Earliest start time

The earliest start time (EST) of an activity is the soonest an actiivyt can start after the project start. Finding EST involves making a forward pass through a network diagram along the longest path toward the activity for which you are estimating EST. Making a forward pass means starting at the beginning of the diagram and calculating the duration of each activity preceding the activity for which you are estimating EST. The EST of an activity is equal to the sum of all predecessor activity durations.

 

Suppose Activity A is the first activity of a project, so it does not have predecessor activities. Since Activity A must begin on Day One of the project, it has an EST of zero. Suppose Activity C is the third activity of a project, and its predecessors are Activities A and B. If Activity A has a two-day duration and Activity B has a one-day duration, then the EST for Activity C is three days. This means three days must pass after the project start date before Activity C can begin.

 

·       Earliest finish time

The earliest finish time (EFT) of an activity is the soonest an activity can end after the project start date. Like EST, finding EFT involves making a forward pass through a network diagram. The EFT of an activity is equal to the sum of its EST and its own duration:

 

EFT = EST + activity duration

 

Suppose the EST for Activity D is four days into the project, and it has a six-day duration. This means the EFT for Activity D is 10 days from the first day of the project.

 

·       Latest finish time

The latest finish time (LFT) of an activity is the latest time an activity can finish after the project start without affecting the end date of the entire project. The latest finish time is calculated by making a backward pass through the network. In other words, LFT calculation starts at the end of a project and works backward to the beginning.

 

Suppose a project must be completed by the end of Day 50. The final two project activities are Activities Y and Z. The latest that Activity Z can finish without disrupting timely project completion is Day 50. If Activity Z cannot begin until Activity Y ends, and if Activity Z takes exactly 10 days to complete, then the LFT for Activity Y is no later than the end of Day 40.

 

·       Latest start time

The latest start time (LST) is the latest time that an activity can start after the project start date without affecting the end date of the entire project. The latest start time of an activity is equal to the difference between its latest finish time and its duration:

 

LST = LFT - activity duration

 

Suppose Activity Y has an eight-day duration and an LFT of Day 40 of the project. The LST for Activity Y is Day 32. If Activity Y does not begin on or before Day 32, then the project will not finish on time.

 

How is float calculated?

To calculate float for an activity, subtract the earliest finish time from the latest finish time:

 

Float = LFT - EFT

 

Suppose Activity D has an LFT of 25 days and an EFT of 11 days. Using the equation, the float for Activity D is 14 days. There are 14 days of float in scheduling the start for Activity D.

 

What are methods of duration compression used during schedule development?

Once you have created and analyzed your schedule, you may need to reduce activity duration to ensure that the project can be completed on time. Duration compression is the process of reducing a project's completion time without altering the project scope, or what the project is expected to accomplish. While the project scope should not change, duration compression often affects quality and cost and leads to additional risk. There are several methods of duration compression that project managers can consider during scheduling:

Crashing                                                                                              Fast tracking                                                                                                                Assigning limited overtime                                                                                                                      Implementing shortcuts

·       Crashing

One method is crashing, which accelerates activity completion by using more resources to complete activities on the critical path. Crashing alters the duration of activities on the original critical path and can lead to the creation of a new critical path. Since crashing uses more resources, it often results in a higher cost for activity completion. For that reason, crash plans should compare crash cost to the original cost, as well as changes in activity duration. Project managers can use a crash plan to determine whether crashing is compatible with the project's budget and goals.

 

Critical path activities are the only activities eligible for crashing, since crashing other activities will not affect the project completion date. Before crashing a project, always make sure that it is a feasible option for schedule compression.

 

·       Fast tracking

Another method of compressing activity duration is fast tracking. Activities that are put on a fast track are rearranged based on precedence relationships so that the activities are performed at the same time rather than in sequence. Performing activities simultaneously reduces project duration.

 

It is important to understand that fast tracking involves a high level of risk. A project's major stakeholders must know the risks before agreeing to fast tracking. Due to the risk involved, it should be used only when other schedule compression methods are inadequate for project completion purposes.

 

·       Assigning limited overtime

Assigning limited overtime to project team members for certain activities can also shorten overall project duration. It is important to carefully consider which project team members to include when assigning overtime. Too many hours of overtime leads to burnout. In addition, overtime should be carefully considered since it can increase overall project cost.

 

·       Implementing shortcuts

Shortcuts may include using a specialized computer program to design a construction model, acquiring resources based on availability rather than the project plan's original specifications, or reducing the amount of time allotted for product testing. It is important to note that there is risk involved when using shortcuts. When implementing shortcuts, you must ensure that they do not adversely affect the final project results.

 

 

 

Why is it important to know the resource rates when estimating costs?

Effective cost estimations require knowing what resources are needed and what rates are charged for each resource. For example, if it takes 12 team members 10 days to complete an activity, their wage-rate must be known in order to estimate the cost of that activity. Or, if the project goal is to produce a new software program and have 10,000 CD-ROM copies on the market, the cost per CD-ROM must be known in order to estimate the cost of reaching that goal.

 

How is historical information used when estimating costs?

When estimating costs for a project, you need to analyze historical information. Previous cost approximations are often available for the resources you plan to use in your current project. However, if you use historical information to estimate costs, remember to adjust for inflation. In addition, be sure that a previous project and your current project are similar enough that a realistic comparison can be made.

 

When looking for historical information on which to base cost estimates, you can use the following sources:

·       The knowledge of experts or team members with similar experience

·       A project database with your company's records from previous projects

·       Industry-wide cost estimate databases

 

How do activity duration estimates affect cost estimates?

It is important to understand that when you assign resources to a project, the activity duration can affect the cost estimates. For example, suppose you have leased a resource, such as several extra desktop computers, for three weeks. The computers are actually needed only during the first and third weeks, so the activity duration for this example is two weeks. However, since you will have the computers for three weeks, you must base your cost estimate on three weeks, which increases project costs.

 

What types of supporting details are necessary when creating cost estimates?

When you submit cost estimates for a project, they should be accompanied by supporting details. These details will give the estimates credibility and enable the project stakeholders to better understand them.

 

Some types of supporting details include the following:

·       A description of the scope of the work for which cost estimates were completed

·       A description of how estimates were made for each activity

·       A reference to any historical data used to make estimates

·       A list of assumptions made when estimating

 

How are labor estimates used to complete cost estimates?

When completing a cost estimate for a project, you have to consider labor estimates. To develop reasonable cost estimates for labor, identify the necessary man-hours for each activity on the work breakdown structure (WBS). Next, multiply the man-hours by the appropriate labor rates. You can determine the appropriate labor rates by basing them on historical costs for the most recent month or quarter.

 

Since the labor rates can fluctuate over time, be aware that they can be difficult to predict for projects that will take longer than one year to complete.

 

What are some project estimating pitfalls?

The following are several pitfalls you should avoid when completing project cost estimates:

·       Poorly defined project scope

·       Inadequately defined schedule

·       Incorrect work breakdown structure

·       Failure to account for inflation

·       Failure to account for overhead costs

 

What problems can produce errors when I complete cost estimates?

Some project managers prepare for the possibility of project cost errors by increasing all estimates by 5 to 10 percent. Although this is a fairly common practice, you may be able to avoid errors if you are aware of some cost estimating problems that occur on a regular basis.

 

One cost estimating problem is that the price of resources can change over the course of a project. Make sure you are aware of this possibility and, if at all possible, account for it in your estimate. In addition, some project resources can spoil or be wasted, so you should include a cost allowance for these problems and have more resources available than necessary.

 

Another cost estimating problem is that costs are frequently understated in order to make the project seem more attractive to stakeholders. Never understate project costs since doing so will have a negative affect on the project's end goal and on your credibility with the stakeholders.

 

And finally, sometimes problems occur without any warning. Always make sure the project has an allowance for contingencies.

 

How can I estimate costs for projects that are R&D oriented?

Occasionally, you may manage a project that relies heavily on research and development. In this case, you may have difficulty estimating the project cost because there are so many unknown variables. You can choose from three methods to help you estimate cost for an R&D project.

 

One method is to examine previous projects that are similar to the current project. After examining a previous project, you can estimate how much more difficult the current project is than the previous one. Suppose the current project seems to be three times more difficult than the previous project. Multiply the number you estimated by the budget for the previous project. For example, if the budget was $50,000, you would multiply that by your estimated number of three and arrive at a budget of $150,000 for you new project. Keep in mind that the more similar the previous and current projects, the more accurate your cost estimate.

 

A second method you can use to estimate the cost for an R&D project is to make your best guess. The accuracy of this estimate depends solely on your experience and judgement.

 

A third method is to estimate the cost for each activity in the project and add the estimates to find the cost of the entire project. Although time consuming, this method yields the most accurate cost estimate.

 

What types of costs will a project incur?

Projects can incur a variety of costs. First, a project may have fixed or variable costs. Fixed costs do not change and include the price of supplies needed to complete a project. Variable costs can change based on external factors. For example labor expenses are variable costs because they can change depending on the duration of the activities. For this reason, you should always estimate duration before cost.

 

What organizational financial issues can affect a project?

 

A number of organizational financial issues can affect a project. Overhead expenses, general and administrative expenses, and profit goals can be passed on to a project. Overhead expenses include items such as employee benefits. General and administrative expenses include items such as rent and utilities. Profit goals are built in to project costs to ensure that the company earns the desired amount on the project. You should determine whether these expenses must be included in your project's budget since they will affect how you manage the project. In addition, you should find out whether your project budget will be charged for all labor costs.

 

Why should I be aware of company financial cycles?

Since a company's financial cycles can affect how you manage a project budget, you need to be aware of them. The amount of operating cash in most organizations is seasonal to some degree, so the amount of available funds may fluctuate throughout the year. You should understand these financial cycles, so you can determine whether funds will be available for your project when they are needed.

 

What factors should I be aware of when negotiating for a larger budget?

If someone else has set your project budget, you may be able to negotiate for more funds. If you want to negotiate for a larger budget, you should do so as soon as possible. When you negotiate early in the project or before the project begins, there are usually more options available for adjusting the budget.

 

You should also keep in mind that if the final decision comes down to your estimate versus your manager's estimate, you will need data to make your case. If you do not have this information, you will have to settle for your manager's estimate. Before you negotiate for more funds, it is essential for you to prepare thoroughly.

 

What actions can help me make the most of available funds?

If your project budget is tight, you can use the following actions to make the most of the available funds:

·       Eliminate activities that are nonessential for project completion.

·       Shorten activity duration.

·       Use lower-priced resources when possible.

·       Spend from other budgets when acceptable.

·       Use activity slack.

Reduce the scope of the project as a last resort

 


What is project control?

Control involves measuring, monitoring, and adjusting aspects of a project to produce a desired outcome and achieve the project's goals. Since control requires knowledge of the project status, the project manager and team must continually monitor the project. Comparing the project's progress to the original plan enables a project manager to identify deviations from the plan and take corrective actions to put the project back on the plan. Project managers control projects by using change control systems, measuring performance, and analyzing reports.

 

What is project change control?

Project change control involves managing changes so they benefit the project and verifying that performance standards for the project are met. If tools are used to measure the performance of the project, change control verifies that the tools are properly configured to ensure accurate measurements.

 

In addition, project change control requires recording all changes to the scope of a project or the work that is required to complete a project. Since changes can have an impact on more than one area of a project, the project manager must ensure that all affected individuals are aware of the changes and how the changes affect them.

 

What is a change control system?

The processes used to control a project are defined and compiled by the project manager and team into an overall change control system. During project execution, the control processes are used to track progress and make changes when problems arise. A change control system should have specific guidelines for processing and executing changes to a project or project-related documents. This system should designate what forms should be filled out to request or make changes and to whom the forms should be given for approval and implementation.

 

A change control system should also indicate how and where changes should be documented. In addition, a change control system should provide a method for evaluating the benefits and drawbacks of potential changes, how to communicate changes to the necessary people, and how to monitor the implementation of changes.

 

What are the objectives of a change control system?

Change control systems have three basic objectives. The objectives are to screen project change requests, document the accepted changes, and update the project plan and other documents affected by changes.

 

What are some characteristics of a good change control system?

Good change control systems have several characteristics in common:

·       An emphasis on project success

·       A focus on what is important

·       A system for taking corrective action

·       An emphasis on timely response

 

·       An emphasis on project success

A change control system should emphasize the overall success of a project, so it does not inhibit progress. A project change control system should be flexible so the project manager can incorporate specific measurement techniques needed during each phase of the project. Therefore, a change control system should include provisions for changing performance measurement techniques as necessary. In addition, the performance measurement techniques, such as measuring cost and schedule variance, should be reasonably accurate and appropriate for the type of performance measured.

 

A change control system should also operate ethically and efficiently. It should not conceal actual performance results, and it should not waste resources or strain the project budget while measuring performance.

 

·       A focus on what is important

Since the goal of any project is to accomplish the project objectives, a change control system should focus on elements that can affect whether the objectives are met. Keep in mind that the elements you control in a project frequently become the most important elements to the team because more emphasis has been put on them. Be sure that the elements you control are the most important ones. Otherwise, you may unintentionally de-emphasize important project elements. For example, if you control cost and schedule, team members may accomplish the schedule and budget goals at the expense of quality.

 

Several questions can help you determine what elements should be controlled:

·       What is the project supposed to accomplish?

·       What elements are important to the organization?

·       Which activities are critical for project success?

·       Where should controls be placed in the process to ensure success?

 

·       A system for taking corrective action

Perhaps the most important function of a change control system is to give the project manger and team members rules for taking corrective action. A change control system that identifies problems without providing guidance to correct the problems will not ensure the success of the project. When data shows that the project is deviating from plan, the project manager needs to help put it back on plan. This does not mean that the project manager has to actually make the corrective actions, only that he or she needs to ensure that team members are taking steps to correct the problems.

 

·       An emphasis on timely response

Corrective action must be made in a timely manner. If corrections are made too late, they may be ineffective or even make the problems worse. For these reasons, a project manager always needs to know the current status of the project and, he or she needs to collect control data on a regular basis. For many projects, weekly status reports may be sufficient, but a control system should be based on the needs of each particular project.

 

 

What items do I need to control changes to a project?

You need the following items to control changes to a project:

·       The project plan and scope statement

·       A list of project factors that are necessary to control, such as performance, cost, and time constraints

·       Current and accurate performance reports

·       Documentation of changes or potential changes

·       Equipment to measure such things as performance and cost

 

What role do status meetings play in controlling a project?

Status meetings are used during project implementation to discuss status and find solutions to any problems. For example, if the project is behind schedule, a status meeting should be held to determine what can be done to put the project back on track. Or, if the project is going over budget, a status meeting can help identify ways to lower operating costs.

 

What process can I use to accommodate change?

Use the steps in the AMEND acronym to accommodate changes in a project:

1. Assess the potential change

2. Modify the project plan

3. Examine alternatives

4. Navigate project procedures

5. Deliver sufficient information

 

1. Assess the potential change

Before making any changes to a project, you should assess exactly what they should accomplish. Since changes should be implemented only when necessary to ensure project success, you need to determine the desired results they should produce. In addition, you should determine how to measure whether or not the changes create the desired results.

 

2. Modify the project plan

After you have determined the expected results of a change, modify the project schedule and budget to see how the change will affect them. In addition, determine whether the change will affect the project performance standards. If a change is imposed by an outside source, you should determine the effects before agreeing to making the change. Since project team members may be able to identify effects that you have overlooked, reviewing potential changes with them can be beneficial.

 

3. Examine alternatives

Before choosing a solution, you should examine alternatives. Usually, there is more than one way to achieve a goal. Re-examine your budget and schedule and decide whether the potential change is the best possible choice considering the available resources.

 

4. Navigate project procedures

When you have determined the best course of action, you should thoroughly document the change by adding it to the original project plan, and if necessary, submit the change for approval. For significant changes, you should provide all stakeholders with written notification of the change.

 

5. Deliver sufficient information

When you implement a change, you must notify everyone affected by it. Project team members need to understand how the change will affect the project and how expectations may have changed. You should also tell team members how the results of the change will be measured. Doing so will help them communicate with you as the change is implemented.

 

What is a change control board?

In addition to the process for accommodating change, you may need to seek approval for changes with a change control board. Some projects have a group of people, approved by major project stakeholders, who have the authority to approve or deny change requests. It is important that the members' roles are clearly defined, so they know the extent of their authority.

 

Generally, changes can be made on an emergency basis without prior approval from the change control board. Emergencies should be specified somewhere in a project's change control system. It is important to understand that changes made in response to emergencies require the same documentation and follow-up as other changes.

 

What are some results of project change control?

Results of project change control include updates to the project's plan, scope statement, and budget. Another result of change control is that all corrective actions taken during the project should be documented, as well as any lessons learned while implementing changes.

 

 

Why is it important to measure project performance?

Measuring the performance of a project is critical for its successful execution. You should gauge project performance based on the answers to the following questions:

·       Is the project meeting the quality standards?

·       Is the team's morale satisfactory?

·       Are activities completed as scheduled?

·       Is the project operating within its budget?

 

How can I determine whether a project is meeting its quality standards?

You can determine whether a project is meeting its quality standards by comparing performance reports to the objectives set for the project. If the performance reports indicate that the project is not accomplishing its objectives, you should try to determine when, where, and why actual results do not conform to the quality standards. When you identify the answers to these questions, you can take action to improve quality.

 

How can I determine the level of morale of the project team?

You can determine the level of morale of the project team by talking to its members. Pay attention to whether they put quality effort into fulfilling their responsibilities and take notice of any conflicts that arise.

 

What methods can I use to measure project performance?

 

There are several methods you can use to measure project performance:

Variance analysis                                                                                                                                                                                                         Trend analysis                                                                                                                                                                       Earned value analysis

 

·       Variance analysis

Variance analysis is used to gauge how closely a project adheres to its schedule, resource use, and budget provisions. Variance analysis can also be used to determine whether or not a project's quality standards are met.

 

·       Trend analysis

Trend analysis is used to evaluate the progress of a project over time. For example, trend analysis can be used to establish whether a solution to a problem is effective by determining if the problem still exists once a solution has been implemented. Trend analysis can also be used to show patterns of project resource consumption.

 

·       Earned value analysis

Earned value analysis measures overall project performance by calculating a dollar amount for every project activity. These dollar amounts are calculated using the following values:

·       Budgeted Cost of Work Scheduled (BCWS) is a portion of the project budget expected to be spent during a specific time period. For example, $6,000 is assigned to Activity A, which takes six days to complete.

·       Budgeted Cost of Work Performed (BCWP) is the total budgeted cost of all work completed to date on a project. For example, imagine that Activity B is allotted $1,000. Activity B is only 40 percent complete at the time that BCWP is calculated. As a result, of the $1,000 allotted for Activity B, only $400 is included in the BCWP.

·       Actual Cost of Work Performed (ACWP) is the amount of money actually spent completing a specific activity within a given time period. For example, if the six days worth of work completed on Activity A actually cost $5,000 instead of $6,000, then $5,000 is your ACWP.

 

Earned value analysis is important to performance reporting because it can give the project manager and team members the most accurate measure of whether or not a project's activities are being completed as planned.

 

What calculations are used during earned value analysis?

The following calculations are used during earned value analysis:

·       Cost variance                                                                                                                                                           Schedule variance                                                                                                                                        Cost performance index                                                                                                                    Schedule performance index

 

·       Cost variance

Cost variance (CV) occurs when the actual cost of an activity differs from the estimated cost. You can calculate cost variance by subtracting the Actual Cost of Work Performed from the Budgeted Cost of Work Performed, which is represented by the following equation:

 

CV = BCWP - ACWP

 

If the cost variance is a negative number, the activity is using more money than planned. If it is a positive number, the activity is using less money than planned. If the cost variance is zero, the activity is on track.

 

·       Schedule variance

Schedule variance (SV) occurs when the actual completion time of an activity differs from the scheduled completion time. You can calculate schedule variance by subtracting the Budgeted Cost of Work Scheduled from the Budgeted Cost of Work Performed, which is represented by the following equation:

 

SV = BCWP - BCWS

 

If the schedule variance is a positive number, then more work than originally planned has been completed up to that point. If it is a negative number, then less work than originally planned has been completed up to that point.

 

·       Cost performance index

The cost performance index (CPI) of a project is the ratio of the budgeted cost of a project to the actual cost, or the Budgeted Cost of Work Performed divided by the Actual Cost of Work Performed, which is represented by the following equation:

 

CPI = BCWP/ACWP

 

If the CPI is greater than one, then the cost performance of the project is efficient. If the CPI is less than one, then the cost performance is inefficient.

 

·       Schedule performance index

The schedule performance index (SPI) of a project is the ratio of the actual work performed to the scheduled work, or the Budgeted Cost of Work Performed divided by the Budgeted Cost of Work Scheduled, which is represented by the following equation:

 

SPI = BCWP/BCWS

 

If the SPI is greater than one, then the schedule performance of the project is efficient. If the SPI is less than one, then the schedule performance is inefficient.

 

 

Schedule and Cost Control

 

What is project control?

Project control involves measuring, monitoring, and adjusting aspects of a project to achieve specific goals. Comparing the project's progress to the original plan enables a project manager to identify deviations from the plan and take corrective action. Project managers control projects by using project change control systems, measuring project performance, and analyzing project reports.

 

What items are used to control project performance?

Some items used to control a project include change requests, test results, quality assurance measures, and rework. Additional items include resource consumption reports and maintenance reports.

 

Why is it important to control the project schedule, and how can I do so?

Through schedule control, project managers can ensure that schedule changes are in line with project objectives and are favorable to project completion. To control a project schedule, project managers should identify variances from the original project schedule. Then they should determine where, when, and why the project has fallen behind and take corrective action. The project schedule should be updated since corrective action can affect the execution of remaining project activities.

 

What items are used to control a project's schedule?

When controlling a project's schedule, it is important to always refer to the project's master schedule. To show schedule variances, it may be helpful to display additional schedules on Gantt charts or use graphs and process control charts. Project status reports can also be useful when controlling a project's schedule.

 

Why is it important to control the project cost, and how can I do so?

To control project costs, you should identify variances from the project's budget. You can follow these steps to control project costs:

1. Monitor spending by examining status reports.

2. Identify variances from the original project plan.

3. Determine when and why each cost variance occurred.

4. Obtain authorization from stakeholders before making any budgetary changes.

5. Record any budgetary changes you make.

6. Inform project stakeholders that the approved changes have been made.

 

What items are used to control a project's budget?

Some of the items used to control the budget of a project include receipts from contractors or vendors, income and account statements, and cost reports. In addition, records of wages paid, overtime hours worked, and absences from work are also helpful when controlling a project's budget.

 

 

What is performance reporting, and why is it important?

Part of a project's communication system includes performance reporting. The purpose of performance reporting is to collect and distribute information to project stakeholders about how effectively resources are being used. In addition, when combined with change control systems and project performance measurements, performance reporting helps a project manager control a project.

 

How does performance reporting facilitate project control?

Project control involves measuring, monitoring, and adjusting aspects of a project to accomplish specific objectives. A project manager cannot adequately control a project unless he or she knows the project's status at any given point, so project performance must be continually measured and reported.

 

Performance reports should record any variation between actual project results and expected project results. If variations exist, the project manager can take corrective action to return the project to its original plan.

 

What is a reporting period?

The time between one performance report and the next is called a reporting period. Frequently, a reporting period coincides with the beginning and end of a project phase.

 

When reporting periods do not coincide with project phases, it may help to include reporting period dates on the project schedule. Doing so helps team members know when they need to write performance reports.

 

How often should performance reports be produced?

The intervals at which performance reports are produced depend on the project. Lengthy projects may need formal status reports only once per month. Shorter projects may need a status report once every week or even more frequently.

 

Consider how often a report should be produced to provide stakeholders with information when they need it. A project manager's ability to control a project depends on timely information.

 

How can performance reports be classified?

Performance reports can be classified by frequency, purpose, or both. The following are common classifications of performance reports:

Routine                                                                                                                                                                                                                        Exception                                                                                                                                                                                   Special analysis

·       Routine

Routine, or regular, performance reports are not necessarily scheduled, but may be distributed at intervals that coincide with project phases or milestones. The frequency of performance reports depends on how smoothly a project functions.

 

·       Exception

Exception performance reports provide information project team members need to make decisions or they notify team members of changes that affect their work. Exception performance reports are also distributed to stakeholders to inform them that a decision has been made about some aspect of a project.

 

·       Special analysis

Special analysis performance reports contain information about the results of a study. Special studies may be conducted as part of a project or to determine a solution to a problem encountered during a project. Special analysis reports are useful to a current project and provide valuable documentation of lessons learned that can be applied to future projects.

 

What is a progress report?

One specific type of performance report is a progress report, which provides a detailed summary of what project team members have accomplished up to a given point and how they did it. Progress reports also should include the number of people who actually worked on an activity compared to the number of people who were scheduled to work on it.

 

What is a status report?

Another type of performance report is the status report. It covers a wider range of information than a progress report and provides a detailed account of a project's status up to a given point. The status report should include items such as activity completion for the current reporting period, resource consumption, budget expenditure, forecasted completion dates for activities in progress, problems encountered, and suggestions for improvement.

 

Status reports must include the current status of all activities completed during a given reporting period, so the project manager can determine whether problems exist and what corrective action to take.

 

How can I determine which performance reports are necessary for a project?

When trying to determine whether a report is necessary for a project, consider whether the report serves a purpose by answering the following questions:

·       What information will the report contain?

·       What is the reason for producing the report?

·       Who will write the report?

·       Who is the audience for the report?

·       How often will the report need to be produced?

·       Is the information in the report necessary for project control?

·       Is the information in the report valuable to you or other stakeholders?

 

When you determine which reports are necessary for a project, keep in mind that none of them will be beneficial if the information in them is inaccurate. You should stress the importance of accurate information to team members who will complete the reports.

 

What are some frequent problems with progress reporting?

Some frequent problems with progress reporting include the following:

·       Too much information

·       The wrong kinds of information

·       Not enough information

·       Out of date information

 

To avoid these problems when reporting progress, you can take the following actions:

·       Keep progress reports concise and accurate

·       Make sure information is current and relevant

·       Create reminders for yourself as to when progress reports are due

 

How does performance reporting affect project costs?

Performance reporting can affect project costs when time for writing the reports is not allocated in a project's schedule. If the time is not recorded, then the project's total cost will be inaccurate. Be sure to include the time spent for writing reports in the project budget.

 

What steps should I follow to close a project?

There are four steps you should follow to close a project:

1. Create a task list

2. Communicate about the close

3. Celebrate accomplishments

4. Release the resources

 

1. Create a task list

As a project nears completion, you should create a list of all the tasks that must be done to end the project. In addition to wrapping up the final project activities, there are a number of other tasks that need to be completed to close a project, such as writing the final report. Creating a task list can help you manage all the extra tasks.

 

In addition, task lists tailored specifically for your team members can help them focus on completing their activities. This is important, especially for any team members who may be apprehensive about the end of the project. These team members will frequently work on insignificant tasks in an attempt to prolong the project.

 

2. Communicate about the close

Communication is essential to the successful close of a project. As a project manager, you need to communicate several messages at the end of a project. First, you need to communicate to all stakeholders when the project will officially end. Second, you need to close out all contracts and communicate the project end date to suppliers and vendors to ensure that all bills will be sent as soon as possible. Third, if project team members have been borrowed from other teams or departments, you should notify the respective managers that the end of the project is near. The fourth and final message you need to communicate is to the finance department to ensure that the project books are closed.

 

3. Celebrate accomplishments

When a project has been successfully completed, it is important to take time to appreciate all that has been accomplished and thank team members for their work. A celebration is a fun way to wrap up a project, and it marks the official end of the project for all involved. Consider giving awards to team members whose contributions to the project were exceptional. In addition, acknowledge all team members' hard work to help them feel good about what they have accomplished and ease their transition back to their previous work or to their next project.

 

4. Release the resources

After a project is completed, any number of resources maybe left over. Leased equipment should be returned, unused supplies should be returned for credit, if possible, and supplies that have been used may need to be sold or incorporated into the organization.

 

What are close-out reports?

During the close of a project, a project manager and team members should write detailed reports, or close-out reports, about the processes used for phase and overall project completion, including any lessons learned. Writing these reports helps the team and the project manager evaluate how successfully they met the project's objectives. The reports are then archived for use as references for future projects.

 

What information should be included in a project's final report?

A project's final report, or ''project history,'' consists of the information recorded in performance, status, and close-out reports, as well as other project documents. A project's final report should include the following:

·       What organizational structure was used for the project

·       What project management techniques were used

·       Who was involved in the project and in what capacity

·       What went right and wrong during the project and why

·       What corrective action was taken to bring problems back in line with project goals

·       What activity completion processes were used

 

The information in the project's final report supplements a project's historical database, so the information can be used to help plan future projects.

 

Why is close-out reporting often neglected?

Close-out reporting is often neglected because concluding a project is not as exciting or interesting as beginning a project. The project manager or team members may not recognize the value of writing close-out reports, and they may become preoccupied with other tasks. Also, team members are frequently eager to start a new project, so they start looking ahead instead of focusing on the present.

 

It is important to complete close-out reports for every project since they assure stakeholders that the project is actually complete. As part of close-out reporting, a project manager should obtain signed confirmation from key stakeholders to ensure their awareness of the project status.