4.2.1
Institutional Arrangements
In India the MoEF is the nodal agency for the planning, promotion and co-ordination
of environmental and forestry programmes (Singh et al. 1994). It is a relatively
new ministry constituted in 1985 (Banham and Brew 1995).
First serious exercise for establishing an agency to look after the environment
began in 1972, when a National Committee on Environmental Planning and Co-ordination
(NCEPC) was set up and a office of Environmental Planning and Co-ordination
was established under the Department of Science and Technology. Subsequently
in 1980 a committee was set up to recommend legislative and administrative
machinery for environmental protection. On the basis of the recommendations
of the Committee a separate Department of Environment was established in 1981.
In August 1979 the Central Government constituted a Working Group on Mining
and Environment. The terms of reference of the Working Group included, inter-alia,
the following (Ramanathan and Mehta 1982):
1. To evolve methodology for assessing the state of environment in and around
different kinds of mines.
2. To draft guidelines for integrating environmental protection measures with
mineral exploitation.
The Working Group prepared a questionnaire (checklist) for environmental appraisal
of mining operation. In the year 1982, the Department of Environment evolved,
with the active participation of mining experts, procedures and guidelines
for EIA of mining and quarrying projects (Ramanathan, 1982). Procedure for
environmental clearance was also laid down, which inter-alia, required submission
of an EIA/EMP report. The same guidelines are still being used with minor
modifications (Choudhury, 1995).
The Dhanbad Declaration 1982, a willing declaration of the Indian mining industry
professionals, issued on conclusion of the National Conference on Minerals
and Ecology organised at Indian School of Mines, Dhanbad in March 1982 was
another hallmark of concern and commitment.
During the sixth five-year plan, the Planning Commission adopted a system
whereby all projects requiring approval from the Commission were pre-reviewed
by the Department of Environment. It may be mentioned that only large projects
(termed "mega" projects) required approval from
the Commission. As has already been mentioned under 'PIB Rule' all public
sector projects seeking funding from the Public Investment Board also had
to obtain environmental clearance. Thus, though not legally required, EIA
of mega-projects and public sector projects were implicit under executive
orders since the late seventies. The guidelines under Forest (Conservation)
Act 1980 also insisted for environmental clearance of projects having proposal
to divert more than twenty hectare of forestland (Chowdhury 1996). It was
this stipulation that indirectly compelled the private sector mining projects
to undergo a process of scrutiny and evaluation from environmental angle (Datey
and Marwaha 1996).
Even earlier to 1980, some EIAs had been carried out in India as a requirement
of foreign donor agencies
4.2.2 EIA evaluation procedure
As has been mentioned before a system of giving environmental clearance to
mining projects has been in existence since 1982. The procedure of evaluating
EIAs of development projects has undergone only minor changes in 1994. Previously
the following types of mining projects were usually referred to an advisory
committee named 'Environmental Appraisal Committee (EAC) for Mining Projects'
(IBM 1994): -
1. All new mining projects of central public sector with capital investment
of fifty crore rupees or above.
2. All existing mines of the central public sector going for expansion/modernisation,
the total capital investment after expansion/modernisation being fifty crore
rupees or above.
3. Mining projects, of both public sector and private sector, financed partly
or wholly by international funding agencies.
4. Mining projects, of both public sector and private sector needing forest
clearance.
The environmental appraisal committee acted on advisory capacity and did not
have any statutory position. The terms of reference of the EAC for mining
projects generally comprised the following (IBM 1994): -
1. To examine the environmental aspects of mining projects along with their
environmental management plan referred to the MOEF and make recommendation
for their approval or rejection.
2. To suggest preventive and mitigation measures and pollution control devices
including choice of appropriate technology for projects recommended for approval.
3. To review and analyse the environmental management plans submitted in respect
of the new mining projects.
4. To ensure through appropriate monitoring mechanism that environmental safeguards
proposed/recommended are effectively implemented.
The MOEF used to take a decision on environmental clearance of mining projects
based on the recommendations of the Environmental Appraisal Committee. Such
clearances were granted with or without additional conditions stipulated in
the formal letters of clearance issued to project proponents.
As may be observed from the above, structurally the EIA assessment procedure
was more or less satisfactory. However, near-absence of monitoring mechanism
prevented the EIA system from being effective. Since environmental clearance
was not a legal requirement, once an environmental clearance was granted there
was little that could be done to ensure compliance of conditions imposed.
There was no requirement for submission of compliance reports. Just before
introduction of EIA guidelines, Ramanathan (1982) cautioned 'to be effective,
environmental management needs legal sanction'. It was only in 1994; measures
were taken by issuing the EIA Notification, to provide such a legal sanction.
The EIA Notification 1994 requires EIA/EMP reports to be prepared in accordance
with the guidelines issued by the Central Government from time to time. The
notification as such does not mention anything about allowing submission of
rapid EIA reports. However in a subsequent explanatory note issued by the
ministry (Singh et al. 1994) it has been clarified that project proponents
may furnish 'Rapid EIA' report to the Impact Assessment Agency (IAA) based
on one season data. Comprehensive EIA report will, however, have to be submitted
later, if so asked for by the IAA.
A project proponent is required to apply in prescribed application form for
environmental clearance of the project. Additional information to be furnished
along with the application include, amongst other things, the following:
1. 20 copies of EIA/EMP report.
2. Risk analysis report (20 copies).
3. Filled in questionnaire (as prescribed by the IAA) for environmental appraisal
of the project.
4. A comprehensive rehabilitation plan if more than 1000 persons are likely
to be displaced, otherwise a summary plan for rehabilitation of people to
be displaced.
5. Details of public hearing.
According to the EIA Notification 1994, the EIA/EMP reports (and all other
reports submitted with the application for environmental clearance) are to
be evaluated by the Impact Assessment Agency (IAA) which is the Ministry of
Environment and Forests itself. The EIA/EMP reports are therefore first assessed
by the staffs of sector specific impact assessment wing in the Ministry. For
example EIA of mining projects are scrutinised and initially evaluated by
the Impact Assessment Wing-II. If deemed necessary the IAA many consult a
committee of experts, having a composition as specified in Schedule III of
EIA Notification 1994. Normally the EIA reports are, as a rule, referred to
the sector specific expert committee. The expert committee evaluates the EIA
reports and if necessary undertakes site visits.
The Impact Assessment Agency takes a final decision on environmental clearance
of the project based on the evaluation and recommendations of the expert committee
and also based on the details of public hearing. The IAA may issue environmental
clearance with certain stipulations.
It is mandatory for the Central Government to issue site clearance within
30 days. Similarly assessment of a project for issuing environmental clearance
is completed and decision conveyed within ninety days from the date of receipt
of the requisite documents and data from the project authorities and completion
of public hearing. A half-yearly report is submitted by project authorities
regarding implementation of the recommendations and conditions subject to
which the environmental clearance has been given. The IAA for monitoring purposes
uses these compliance reports.