4.5.1 When and for which time to plan
The very word plan means to chalk out the future activity, same is the time to develop a LUMP for a mining project. It is specially because, unless it is done prior to the total activity, the activity may stand out to be more expensive. The matter may be illustrated by the simple examples.

* If the LUPg exercise decides to form a big lake over an abandoned quarry to form a surface water resource for the community around, and before planning the quarry be backfilled by internal dumping, the implementation of LUMP will be too expensive uselessly.
* If the pre-mining LU is damaged before in-depth societal survey (i.e., knowing and forming a record about, which family was living on what earning, from which land, and how), huge number of families, much more than the actual, may claim that they were living on the same piece of land, working as a labour (on agricultural field) or a fisherman (on a water body) etc. Naturally to meet their demands will be too expensive.

Thus the total activity to select the most suitable LU (as in Fig. 4.2) should be completed before any of the premining LU is disturbed.

Next comes the consideration about for which time to plan. So-long the matter has been discussed as "what should be the use of the land after mining is over". Obviously the main consideration is about the post-mining land-use. But considering the fact that land is a very rare and worthy natural resource; and a big mining project may have a very long life, it is to be realized that if plans are made to develop only the post-mining LU, the total area under a big mining project will not have any use throughout its whole life. While the fact is, the actual mining activity at any time will run on only a part of it, and the remaining parts acquired, vacated and lying without any use will be highly prone to erosion, causing soil loss and many other environmental problems. The concept being extended here is, "to plan for some intermediate land-use for these parts". To consider in micro-scale, for some of these it will be pre-mining land-use, while for the others, it will be post-mining LU.

Thus while developing the total LUMP the planners should make integrated planning for 'ultimate LU' and 'intermediate LU'.

Mining has started in India in 18th century or still earlier. Some parts have already completed a century of mining history on official record. These areas have already been mined a lot without any LUPg or LUMP. Many areas in these fields are in serious danger and huge amount of land has lost its usability due to subsidence, scarcity of water etc (Ghosh, 1988). Question arises how the presently suggested LUPg system/concept can be applied under such conditions. Of course, the situation under such conditions is to be managed in a round about way. The problems and the exact quality of the degraded land may however vary from field to field as well as in different parts of the same field. There are even close combinations of opencast and underground mining. There is a rare scope to study premining land-use and no scope for required in-depth study of social conditions, in many areas.

It is being suggested that for such areas, whatever the existing conditions are, those should be studied thoroughly and LUPg should be done for future on the basis of the existing conditions only.

A flowchart showing the logical sequence of activities to be followed to achieve LUMP in already quarried areas (which are now covered by huge barren over burden dumps and abandoned quarries) is given in Fig.4.3 (c.f. Ghosh 2000a). It has been proposed that it may stand as a conceptual model for LUMP for other mining areas having alike problems. Those with other problems like subsidence, water scarcity will have to think otherwise, however following the concept to protect the interest of the society around.

Land reclamation plan should follow from implementation of LUMP.

Previous
Home
Next