5. Technicality of Implementation of LUMP

5.0 Introduction
Implementation of LUMP requires land reclamation as per LUMP. This requires suitable reclamation techniques. Further, implementability of the LUMP obviously depends upon its technical feasibility. Hence a provision has been kept in the suggested LUPg system for assessing technical feasibility of developing any suggested scenario through a specific reclamation activity.

In this reference it appears justified to detail some reclamation technologies to be used to mitigate the environmental impacts of mining on land and LU together with technical feasibility of these reclamation technologies.

Land reclamation in mining areas concerns mainly reclamation of quarries, solid waste dumps and subsided areas. The reclamation method to be followed depends upon the depth (& real extent) of the quarry, geology of the quarry site and the volume of OB/spoil available. Thus the matter has been discussed next following the different possible conditions.


5.1 Shallow pit without topsoil/solid waste
There may be shallow pits without any (or much) of top soil or OB or SP as in case of clay quarries or other shallow deposits. The best way to reclaim these is to backfill with suitable soil or soil substitutes, greenmulch, compost etc. and renewed for agriculture. Some abandoned pits resulting from exploitation of float ores in the neighbourhood of Mansar mine of MOIL have been refilled by OB and reclaimed by spreading topsoil stored earlier (Anon, 2000, pp.10).

5.2 Deep quarry without solid waste
In case the quarry is deep without OB or any other form of solid waste or SP or has not been back filled due to some cause or other, the most economic way to reclaim the quarry is to form a lake. These generally form perennial water bodies, as in most cases such OC mines behade aquifers. These hence form a perennial water source for the region around and helps compensating water scarcity due to mining, (if any such is caused). These can be dressed to generate fishery, swimming pool or any recreational facility to form an economic resource even (Nelson et al. 1982). In Indian condition quarries from limestone, manganese, dolomite iron ore etc. are best suitable for such reclamation.

However, all quarries cannot be turned into lakes because that will cause huge number of water bodies disturbing the balance in the land-water-ecosystem in mining areas and will keep OB/SP-dumps unused, to be reclaimed separately. Hence, side by side, there should be an attempt to restore the original topography as far as possible, the final suggestion should however follow from LUMP.


5.3 Deep quarry with solid waste
If it follows from LUPg that a big quarry is to be reclaimed by backfilling, it is better to decide it at the premining stage itself; and the workplan should be chalked out to decide whether the quarry is to be backfilled by OB generated at the neighbourhood or by any other solid waste (SP). In such backfilling care should be taken on two points:

* Filling should be made as compact as possible, using dumper or heavy earth moving machinery (HEMM) after each 2.5 to 3.5 meter, and finer compaction should be made by rollers, otherwise the openspace below the land generated by backfilling may disturb its usability. Even some layers of finer solid waste (if locally available) may be put in intermediate positions.
* The newly developed land should match with surrounding topography, keeping in mind that such filling materials generally do not have soil or soil nutrient. These are to be covered by 25cm to 40cm of fertile soil or soil substitutes e.g. green mulch, organic compost etc. and then can be used for plantation of local hardy species. After long period of plantation the land will get compacted and come back to original condition.
* Such backfilling will help using-up huge volume of OB and SP material also.

If it happens that the excavation takes out the total thickness of aquifer together with its base, simple backfilling cannot regenerate the impermeable base of the lost aquifer and the aquifer is lost for ever (Fig. 3.3). While the land generated by such backfilling is attempted for biological reclamation, i.e. to generate a sustainable greenery, common activity is to blanket the total land by topsoil (transported from somewhere else) or make pits of optimum size on the land and fill these with similar good soil, then greeneries are put on it.

Such activity grows greenery on the land with low survival rate because the abandoned quarry filled with OB material retains very high porosity and permeability (even if mechanically compacted), so that the topsoil put on it whenever receives any amount of water, the total soil together with water goes down rapidly upto the base of the backfilled quarry, far beyond the reach of the saplings planted on the land. This results virtually to loss of topsoil. The saplings cannot get natural water from underground as the aquifer has already been excavated out.

Further, whatever greenery grows on such land, it grows at the cost of greenery growing potentiality of some other piece of land from which the topsoil was taken. The problem can be alleviated by regenerating some aquifer at optimum depth and searching out some substitute of topsoil. The procedure for these and hence the system to be followed for backfilling of such abandoned quarries has been detailed in Fig. 5.1 and in the flow chart Fig. 5.2 (Ghosh 2000c).

Information on rainfall becomes specially required if the quarry is not in sedimentary terrain or if the information on pre-mining water table/ aquifer can not be made available. With reference to the flow of activities required for the purpose (Fig. 5.2) to decide the position of the impermeable barrier to be formed, one has to know the depth (dm) and thickness Tm of the aquifer to be re-generated (or generated freshly).

The best means to decide this is by knowing the geology of the area. To plan any mining project it needs drilling in the region as a pre-requisite to confirm the deposit. Such bore-hole logs (or drill-cores if available) may be analysed thoroughly to know the depth and thickness of the aquifer lost or to be lost by excavation. The impermeable layer should be made at a calculated depth such that the lower boundary of the porous and permeable layer (made by the filling material) be in continuity of the base of the previous aquifer.

If due to some cause (stated above) or other, such information is not available, an alternative procedure of calculating the depth and thickness of aquifer to be constructed may be as detailed next:


Previous
Home
Next