Vaudeville Interactive CD-ROM Gant Chart ED 724 Unit 7 Discussion 1
  Tasks               Wk 1 Wk 2 Wk 3 Wk 4
Wk 5
Wk 6 Wk 7 Wk 8 Wk 9 Wk 10 Wk 11 Wk 12 Wk 13 Wk 14 Wk 15 Wk 16 Wk 17 Wk 18 Wk 19 Wk 20 Wk 21 Wk 22 Wk 23 Wk 24 Wk 25 Wk 26 Wk 27 Wk 28 Wk 29 Wk 30 Wk 31 Wk 32 Wk 33 Wk 34 Wk 35
 
 
Develop storyboards      
Prepare baseline graphics         <-Finished one week early  
Prepare unit specific graphics                         <-finish one week early  
Prepare narration scripts                
Prepare video scripts                 <-finished early  
 
Program instructional units                         <-delay in finishing the programing will not affect final outcome
Record narration          
Edit narration      
 
Shoot video            
 
Develop unit specific animations                           <-anticpated early completion  
Review narration      
Revise narration        
Edit video            
Integrate narration          
Review video      
Revise video            
Integrate video        
 
Test instructional units          
Revise instruction units        
Retest instructional units      
Package for delivery                                                                      
                                 
Status as of the end of Week 8:   Legend  
Preparation of unit specific graphics is on one week behind schedule         Task as scheduled  
Preparation of video scripts and baseline graphics are one week ahead of schedule         Task completion  
Programming of instructional units is one week behind schedule         Task late  
All other tasks are on target.    
 
  Change in estimated task completion  
  Task dependencies  
  Milestone  
                                 
Making this chart is easy. I used Excel to "draw" the chart. In more sophisticated programs, the chart is data driven. The selection of methods
is mostly one based on need and the conventions of your organization. 
To facilitate detail at the weekly stage I simply made the columns narrower and assigned week numbers to them. You could use dates if that
worked better for your needs.
To use for reporting, each week I move the dark vertical bar over by one grid. Now it is at the end of Week 9, next week I will move the bar to 
the end of Week 10. Then I will go back and change the colors of the bars for Week 9 to show their status. You will see that for Preparing unit
specific graphics I was a week late at the end of Week 9. I put a gray box under Week 13 to show that the action would end up taking a week
longer than scheduled.
The most important thing to remember about Gantt Charts is that they are designed to provide information. In very long and complex projects,
the Gantt Charts produced by programs such as Microsoft Project become very detailed and if printed would fill several pages or need to be
run on a plotter so the entire thing can be pinned to a wall. Most multimedia development projects are a lot less complex and the form of
chart shown here is often all that is needed.