Working title : "An investigation of the accident
prevention strategies for public works in Hong Kong"
Acknowledgements
Abstract
Summary of figures
Summary of tables
1.
Introduction
1.1 |
Background |
1.2 |
Scope
of the dissertation |
1.3 |
Objective |
1.4 |
Methodologies |
1.5 |
Dissertation
contents |
2.
Literature
review
2.1 |
Introduction |
2.2 |
Possible hazards related to public
works |
|
2.2.1 - Crisis made by
mechanical moving plant |
|
2.2.2 - Settlement of
existing footway / carriageway |
|
2.2.3 - Traffic accident
due to temporarily closed carriageway |
|
2.2.4 - Damage
of existing underground utilities |
2.3 |
The Accident Prevention Strategies |
|
2.3.1 – By the
Government |
|
2.3.1a - Crisis made by mechanical moving plant 2.3.1b - Settlement of existing footway /
carriageway 2.3.1c
- Traffic accident due to temporarily closed carriageway 2.3.1d
- Damage of existing underground utilities |
|
2.3.2 – By the Architect /
Engineer |
|
2.3.2a - Crisis made by mechanical moving plant 2.3.2b - Settlement of existing footway /
carriageway 2.3.2c - Traffic accident due to temporarily
closed carriageway 2.3.2d
- Damage of existing underground utilities |
|
2.3.3 – By the Contractor |
|
2.3.3a - Crisis made by mechanical moving plant 2.3.3b - Settlement of existing footway / carriageway 2.3.3c
- Traffic accident due to temporarily closed carriageway 2.3.3d
- Damage of existing underground utilities |
2.4 |
Critical appraisal 2.4.1 - Crisis made by mechanical moving plant 2.4.2 - Settlement of existing footway /
carriageway 2.4.3 -
Traffic accident due to temporarily closed carriageway 2.4.4 -
Damage of existing underground utilities |
3. Methodology
3.1 |
The
questionnaire
|
|
3.1.1 -
Research design |
|
3.1.2 -
Sample characteristic |
|
|
|
3.1.4 -
Variables |
|
3.1.5 -
Date analysis |
|
|
|
|
3.2 |
The interviews |
|
3.2.1 -
Type of Design Used |
|
3.2.2 -
Role of the
Researcher |
|
3.2.3 -
Data Collection
Procedures |
|
3.2.4 -
Data Analysis
Procedures |
|
3.2.5 -
Findings of the
Interviews |
|
3.2.6 -
Limitations |
3.3 |
The case studies |
|
|
4. Findings and
improvement
5. Discussion
6.
Conclusion and recommendation
7. Reference / bibliography
Those who help answer my interview
http://www.my3q.com – providing free online questionnaire
industry accident statistic – census & statistics department
trades - factory inspectorate labour department
Construction industry used to be one industry that with high accident rate. Indicated in statistic data every year, public was awaked to pay attention in this issue. Not only inside the site boundary, public projects would also cause crisis to public areas. The public safety problem related to construction works is especially concerned in Hong Kong as lots of such kind of projects are very closed to the pedestrians. The reason is that the land has been insufficient for people in this small region, people would need to walk exactly the edge of fencing off the area of public works. When accidents occur in public projects, it is highly possible to affect the safety of pedestrians. Generally, pedestrians are innocent to be affected, therefore the number of accident in public project should be reduced as much as possible.
Four kinds of accidents are chosen for this topic. 1) Crisis made by mechanical moving plant, 2) Settlement of existing footway / carriageway, 3) Traffic accident due to temporarily closed carriageway 4) Damage of existing underground utilities. Notwithstanding these four kinds of accidents cannot be classified as serious accident, through the occurrence of accident in a site condition seems to be safe or ought to be safe, there should be something wrong in the operation of site works. This report is trying to reflect what goes wrong and recommend how to improve the situation.
In the last ten
years, construction accidents claimed the lives of 470 workers, accounting for
over 80% of all fatal industrial accidents. The number of fatal construction
accidents has been on the decline in the past few years. (Presented by Mr.
Matthew CHEUNG Kin-chung, JP, Permanent Secretary for Economic Development
& Labour (Labour) at the Hong Kong Construction Association Annual Safety
Conference "Partnering
in Construction Safety" on 30 October 2003
(Thursday). http://www.labour.gov.hk/eng/major/301003.htm)
Fortunately, evidence showed that the statistic data was keeping a downward trend in these years. This is such a good sense and good sign to improve the image of construction industry.
The scope of
this dissertation is to investigate the accident prevention strategies by three
parties (the Government, the Architect / Engineer, and the Contractor) involved
in public projects in Hong Kong. The possible hazards of public projects and
the causes of it shall be introduced first and then the duty and performance of
the four parties in accident prevention shall also be examined. Thus, the
degree of effectiveness of existing accident prevention strategies could be
evaluated.
The objective of this dissertation is to find out the deficiency and provide possible improvement measure of existing accident prevention strategies for public projects in Hong Kong.
The methods of gathering information for analysis are chosen to be by interviews and case studies. Through interviews to management level, it is able to find out the ideas of management level towards safety of public project such as what is insufficient and what is needed to improve, etc. Through case studies in some public projects in Hong Kong, it is able to realise what is the difficulties when carrying out the precautious measures, etc.
There are seven
major chapters in this dissertation. Chapter 1 Introduction would show the
background and scope of this dissertation. Chapter 2 Literature review would
derive the selected matter and have it supported by references. Chapter 3
Methodology would show the readers how the information for research is
gathered. In chapter 4 “Findings and improvement”, analysis the gathered
information and report the results. In chapter 5 “Discussion” would discuss the
reported results of the research. Chapter 6 “Conclusion and recommendation”
would summarize the findings and make some recommendation when necessary. The
last chapter “Reference / bibliography” listed out all the sources adapted as
supporting or supplementary information for this dissertation by Harvard
Referencing.
The objective of this literature review is to study the accident strategies taken by the Government, the Architect / Engineer and the Contractor. However, the accident prevention strategy is very board, the research should be narrowed so that 4 possible hazards related to public projects are chosen in searching information which are 1) Crisis made by mechanical moving plant, 2) Settlement of existing footway / carriageway, 3) Traffic accident due to temporarily closed carriageway and 4) Damage of existing underground utilities. The structure of this literature review will be to introduce the causes of the 4 types of possible hazards and then study the accident prevention strategy by captioned parties.
|
1997 |
1998 |
1999 |
2000 |
2001 |
AFR |
227.4 |
247.9 |
198.4 |
149.8 |
114.6 |
FAFR |
0.50 |
0.71 |
0.66 |
0.36 |
0.35 |
RAFR |
42.8 |
45.5 |
39.1 |
35.4 |
32.3 |
RFAFR |
70.7 |
82.4 |
90.4 |
67.4 |
82.4 |
APW |
357 |
377 |
271 |
229 |
177 |
APD |
51 |
54 |
39 |
33 |
25 |
FAPW |
0.8 |
1.1 |
0.9 |
0.6 |
0.5 |
APF |
0.94 |
1.00 |
0.70 |
0.59 |
0.47 |
AFR : Accident Frequency Rate = Number of Construction Accidents / 1000 Workers
FAFR : Fatal Accident Frequency Rate = Number of Fatal Construction Accidents / 1000 Workers
RAFR : Relative Accident Frequency Rate
= Number of Construction Accidents / Number of Total Accidents x 100%
RFAFR : Relative Fatal Accident Frequency Rate
= Number of Construction Fatal Accidents / Number of Total Fatal Accidents x 100%
APW : Number of Construction Accidents Per Week
APD : Number of Construction Accidents Per Day
FAPW : Number of Fatal Construction Accidents Per Week
APF : Number of Construction Accidents Per Firm
Accident : Death of a person or injured a person exceeding 3 days of incapacity.
http://www.hkca.com.hk/indnews/12_1203ifawpca_report.doc
33RD IFAWPCA CONVENTION
SINGAPORE OCTOBER 5-9, 2003
PREPARED BY SINGAPORE CONSTRUCTION SAFETY
& CONSULTANCY PTE LTD, SC2 (A SUBSIDIARY OF SINGAPORE CONTRACTORS
ASSOCIATION LTD, SCAL)
Possible hazards related to public projects here means when accidents occur, it is also possibly to affect the safety of pedestrians. There is no boundary for classification of accidents as accidents must be occur ahead of everyone’s expectation. Therefore, we should focus in four possible hazards that would happen frequently. They are: 1. Crisis made by mechanical moving plant, 2. Settlement of existing footway / carriageway, 3. Traffic accident due to temporarily closed carriageway and 4. Damage of existing underground utilities.
Spacing is not enough for public projects in Hong Kong, it is easy to find that the site boundary of public projects so close, or even abutting, to existing buildings, facilities or assess roads. Although the whole of the site area would be fenced off by some hoardings or barricades, it is really a question that whether these kinds of precautionary works be functioned as a barrier to the heavy motion of moving plants inside the site. People may wonder whether the hoarding would collapse or be damaged once it is hit by moving plant and fail to prohibit the motion goes on.
During construction stage, vehicles such as
concrete loaders and dump trucks would inevitably get in and out of the site
entrance. For public projects, the area of these entrance may also be the
pavement,
A common mechanical moving plant used in public works is mobile crane due to its high degree of applicability. Mobile crane is helpful in public projects in Hong Kong for locating materials, such as batches of reinforcement bar or plywood. It also helps lifting fittings to upper working spots, e.g. lifting windows, doors or casting concrete by concrete skid. In Hong Kong, the limited site space at public area mostly cause difficulty to place the large mobile crane. It is not uncommon to see in Hong Kong that the mobile crane operate outside the site boundary – the busy street. More commonly to see is that lorry crane transported goods to site but it does not get in site because of insufficient space, thus the lorry crane unload the goods outside site boundary. Actually, Statistic figure shown that over 60% of accidents involved different type of mobile crane (Lee H. K., 1996). Another common situation is that the materials are lifted from outside the site boundary and the lorry crane to retreat.
The tilting of mobile crane in public projects may cause serious accident. broken hoisting rope – overloading and poor maintenance of the wire rope may result in falling of lifting objects in pavement.
Causes of accident may be incompetence of operator and lack of technical
knowledge. It is found that the average age of mobile crane operator is quite
low so that the experience is not enough.
In modern construction, plants become an essential part.
In case the failure of mobile crane, the jib
is enough to damage and affect the safety outside the boundary of public site.
+ Backhoe
The Safe Use of Cranes
PRACTICE NOTE FOR REGISTERED CONTRACTORS 18 –
Buildings Department
All excavations must be adequately supported to avoid displacement of earth or soil seepage. Then, the road surface loses support. Once the road surface loses support, the self weight of the road surface has been enough to cause settlement. You can image serious traffic accident may occur if sadden settlement happen in heavy carriageway. Timber, Sheet piles or Trench box are common to be applied as soil retaining system in excavation work in Hong Kong. In large scale project, open cut slope at a safe angle is an alternative method but if seems impossible in public projects, especially in this overcrowded Hong Kong.
In Hong Kong, there is a great deal of
utilities aligned underground including both the heavy carriageway, footway and
also back lane. New laying or repairing of these underground utilities must
involve trench excavation. Now assume the risk of hazard is much higher in
carriageway, the concern falls in there. Trench excavation in carriageway not
only may cause settlement of abutting carriageway but also increase the
possibility of traffic accident, especially for main carriageway, because of temporarily closed carriageway. It is common to see in Hong Kong one of the
three lanes is temporarily fenced off, traffic warning cones and signs are
placed to notify drivers of the execution of works in part of the carriageway.
Such traffic diversion works is dangerous at
night. If the warning signs are not enough, vehicles in highway may not easily
notify the existence of the trench with insufficient lighting. Possibly, the
driver may get not enough time to response as the speed in highway is very
high.
As mentioned before, there are many kinds of underground utilities such
as water pipelines, rainwater pipes, sewage system, underground electric
cables, telephone wires and gas pipelines. When open the footway or carriageway
in Hong Kong urban area, there must be full of these types of utilities. These
underground utilities not only cause hindrance to construction works in public
areas but also cause danger to public if any damage to them. As it is, special
care must be put to these utilities.
If water main pressure pipes are damaged, large amount of water would
flood out to pavement and carriageway. If electric cables is broken up, the
electrical supply in a large area of residential area will be cut. If town gas
pipelines are damaged, it is really a serious crisis to public as town gas may
lead to large explosion and no one can imagine what the
Inspections
(Practice Note for Registered
Contractors 31 - Monitoring for Site Safety) http://www.bd.gov.hk/english/documents/pnrc/Pnrc31.pdf
4. SMS
inspecting officers will inspect sites more frequently where the works, the
construction
stages or the operations pose higher risks to life and limb. Examples are
demolition, deep
excavations,
percussion piling, formation of steep slopes, construction of high retaining
walls, works
projecting
over public thoroughfares and operation of heavy powered mechanical plant.
5. All SMS
inspecting officers will carry a warrant card with authorisation by the
Building
Authority to
:
(a) inspect any premises and enter upon any land;
(b)
ascertain whether the provisions of the Buildings Ordinance are being complied
with; and
(c) carry
out tests, make openings and take reasonable samples for the purposes of the
Ordinance.
Concerted efforts
have been made to further improve health and safety on construction sites.
Through the implementation of the Pay for Safety Scheme and the Independent
Safety Audit Scheme, public works contractors have been encouraged to establish
more efficient safety management systems for maintaining a safe and healthy
working environment on construction sites. In 2001, the Considerate Contractors
Site Award Scheme attracted 100 nominations from public and private sector
sites, providing another incentive for participating contractors to be more
considerate towards the public and the neighbourhood during construction.
Contractors have also been encouraged to implement a Site Safety Cycle to
increase the safety awareness of workers and to maintain good housekeeping and
tidiness on construction sites. Regulating actions are taken against
contractors with poor site safety records. As a result, the overall accident
rate for public works contracts has continued to decline, and in 2001 it was
about 40 accidents per 1 000 workers per year, which was about one-third of the
construction industry average.
2.3.1.1 – crisis made by mechancial moving plants
Construction Sites (Safety) Regulation Chapter 45(1):
The Contractor responsible for any mechanical equipment shall ensure that, when it is used on a construction site, it is not operated except by a workman who is trained and competent to operate it: Provided that the equipment may be operated by a workman not so qualified if hs is operating it under the supervision of another worker who is so qualified.
Construction Sites (Safety) Regulation Chapter 45(1):
The contractor responsible for any mechanical equipment shall ensure that no person under 18 years of age is employed.
(a) to operate the equipment; or
(b) to give signals to the operate of the equipment.
Factories and Industrial Undertaking Ordinance, CAP.59
- Contractor must employ a registered safety officer on a full-time basis if site staff over 100; every 20 worker must employ 1 safety supervisor, no need full time.
- SO duties is to ensure the execuation of safety precaution work. Investigate accident, provide education of importance of safety on site; SS duties is to assist SO in carrying out his duties, ensure working to comply with safety standard.
Under Construction Sites (Safety) Regulations, crane should be inspected and tested once a week by a competent person. Operator need not under 18 years old and formally trained and obtain licence.
2.3.1.3 - Settlement of existing footway /
carriageway
Section VI:
Excavation on Construction Sites
2.3.1.4 - Traffic accident due to temporarily closed carriageway
-
to post
warning sign
-
to limit
access to construction to construction area
-
to obtain
permit for work considered to present a significant risk of injury (http://www.plantown.com/Willits/3.12Hazards.pdf)
To cope with this hazard, Highways Department – one of the Hong Kong Government Body, have issued Code of Practice for the Lighting, Signing and Guarding of Road Work newly updated 2005 Version – Draft. This Code of Practice provides a standard of good practice for the marking of road obstructions as well as for the temporary traffic control necessitated by such obstructions. It enables the legal requirements to be met in a wide variety of circumstances, although it has no statutory force. Compliance with the requirements of this Code should be made a condition of contract for any road works carried out under contract. In the Code of Practice, it is recommended that all person worked for the temporary traffic control works needs to wear retroflective stripes to let drivers to notice. The Code of Practice recommended the contractors to comply with Road Traffic Ordinance – Road Traffic (Traffic Control) Regulation, in which regulation 20 place on the person responsible for road works, a cleat obligation to erect and maintain prescribed lanterns, traffic signs and road markings as the Director may require, and to locate them, in association with barriers, in the manner set down in the Code of Practice. Section 3 of this Code of Practice guided the contractors the recommended size and pattern of traffic signs applied in traffic controls. Section 4 required the contractors to apply for excavation permit before execution of traffic controls, so that the contractors is required to have a detail and mature planning and give the Road Management Office (RMO) of Hong Kong Police and Traffic Department reasonable time to arrange the monitoring works for any emergency accident. Section 5 to 8 give notes to contractors the recommended layout of the precautionary works for different situations, both carriageway and pavement is concerned. The spacing of traffic cones, the length of taper and what traffic warning signs should be placed in different situations are both listed in this Code of Practice.
2.3.2.1 - crisis made by mechancial moving
plants
2.3.2.2 - Falling objects
2.3.2.3 - Settlement of existing footway / carriageway
2.3.2.4 - Traffic accident due to temporarily closed carriageway
Set up Preliminary Project Feasibility Studies (PPFS)
To set up a monthly reporting system to strengthen the
monitoring of the planning progress of high impact public works projects
Co-operative Efforts
(Practice Note for Registered
Contractors 31 - Monitoring for Site Safety) http://www.bd.gov.hk/english/documents/pnrc/Pnrc31.pdf
6.
Registered contractors are expected to co-operate in the interest of public
safety by
ensuring
that :
(a) ready
access to sites is provided to SMS staff;
(b) copies
of all approved plans, agreed work sequence and procedures and all conditions
imposed by
the Building Authority issued to you by the authorized person and registered
structural
engineer are kept on site;
(c) all
approved or agreed work sequence and procedures and all conditions imposed or
orders
issued by the Building Authority, made known and explained to you by the
authorized
person or registered structural engineer, are adhered to;
(d)
requirements on supervision of building and demolition works are met;
(e) adequate
precautionary measures are provided, particularly with regard to falling
objects
at sites;
(f) any
contravention resulting from the carrying out of works is notified to the
Building
Authority as
soon as possible; and
(g)
unsatisfactory aspects of work sites and building works are rectified without
delay.
2.3.3.1 - Crisis made
by mechancial moving plants
Poon and Lee (1992) recommended that contractors should provide training
scheme for safety knowledge to staff, providing money support to staff to take
training course in Construction Industry Training Authority (CITA) is also a
good practice to this point. Before lifting goods it is recommended to design
for a Lifting Plan to seek for approved by the Engineer, and then the Engineer
may able to assess the risk for the lifting process and arrow the contractor to
carry out lifting process strictly referring to the plan. Automatic safe load
indicator is also recommended to be installed inside the crane, so that once
the loads meet the safety level of lifting the safe load indicator would give
out warning signal to notify the operator to stop the lifting process at once.
The project manager or safety officer need to conduct site assessment – to assess
the site conditions, before the lifting process especially for the spot where
the crane will be located, it is because if the crane is located in soft soil layer,
the land will provide insufficient stability. The crane is possibly to tilt
before the safe loading is achieved. Poon and Lee (1992) also recommended the
Hong Kong Government to introduce regulation for the restriction of usage of cranes
which are operated for over continuous 10 years working lift.
Lee (1996) recommended the contractors to have detail inspection on the
crane duty chart and manufacturer’s instruction to understand the plant’s
structure and the checking responsibility. The contractors shall understand very
well the and erection and dismantling procedures. For this, needless to say,
experience is to great important. Inspect of test certificates and other
statutory reports become compulsory action in construction industry. Always inspect
the general condition of the crane to have an early notice of the failure of
crane and have an early rectification of the failure but not aftermath of
accident. Lee (1996) also suggest the contractors to inspect safety devices
regularly to ensure it could help when it is needed. A common sense of safety
that the contractor should never ask for the crane to overload. Same as Poon
and Lee (1992), this book emphasise the importance of inspection ground
conditions when lifting materials by crane.
By Contractor’s Safety Handbook issued by Hong Kong Baptist University, it is highlighted at the table below the all lifting appliances including chains, ropes & lifting gear must be tested, examined and inspected in different time range.
Item |
Testing
& Examination |
Testing |
Examination |
Inspection |
Report Form |
Action |
Lifting Appliance (other than a crane, crab or winch) |
Before use |
|
|
|
Form 4 |
Competent Examiner |
Crane, Crab or Winch |
During the preceding 4 years before use |
|
|
|
Form 3 |
Competent Examiner |
All Lifting Appliances |
Before use after undergone substantial repair, re-erection, failure,
overturning or collapse |
|
|
|
Form 3 Form 4 |
Competent Examiner |
|
|
At least once in the preceding 12 months |
|
Form 5 |
Competent Examiner |
|
|
|
|
Within the preceding 7 days |
Form 1 |
Competent Person |
|
Crane |
|
After erection, removal to a new location, adjustment of any component member |
Before erection (for all of the devices used for the anchoring or ballasting) |
|
Form 2 |
Competent Examiner |
Chains, ropes & lifting gear |
Before use |
|
In the preceding 6 months before use |
|
Form 6 Form 7 |
Competent Examiner |
2.3.3.3 - Settlement of existing footway / carriageway
2.3.3.4 - Traffic accident due to temporarily closed carriageway
What the Contractors can do is to minimise the possibility of accident
with guided by the Code of Practice
Practice notes for construction managers
(http://www.hkicm.org.hk/FILES/HKICM-PNCM4-PM01.pdf)
(www.hkbu.edu.hk/~ehsu/access/handbook.pdf)
6.7 Control of Subcontractors
- All subcontractors shall be made aware of the stringent safety requriements to be imposed on the project site.
- Subcontractors shall be required to provide all suitable and necessary safety precaution and equipment to their employees and enforce application of these measures and equipment. Disciplinary action shall be taken against subcontractors and their employees for non-compliance of the required safety standards.
- A copy of safety rules and requirements shall be issued to each subcontractors.
- In order to exercise close monitoring and control over the safety performance, site safety instructions/memo shall be issued to subcontractors for actions.
- Every subcontreactor shall be required to appoint a Safety Supervisor/Representives for monitoring the safety performance of its work, and for communicating with UNION personnel regarding health and safety matter.
- Procedures for a Permit to Work system shall be implemented to ensure the safety of working in confined space.
- All subcontractors are also required to
attend monthly safety meeting so that adequate briefing and appraisal can be
given with feed back heard from them.
3.1 |
The
questionnaire
|
|
3.1.1 -
Research design |
|
3.1.2 -
Sample characteristic |
|
3.1.3 -
Research Instrument |
|
3.1.4 -
Variables |
|
3.1.5 -
Date analysis |
|
3.1.6 -
Findings and
Results of the Questionnaires |
|
3.1.7 -
Limitations of the
Questionnaire |
3.2 |
The interviews |
|
3.2.1 -
Type of Design Used |
|
3.2.2 -
Role of the
Researcher |
|
3.2.3 -
Data Collection
Procedures |
|
3.2.4 -
Data Analysis
Procedures |
|
3.2.5 -
Findings of the
Interviews |
|
3.2.6 -
Limitations |
3.3 |
The case studies |
|
KCR HUNG HOM
STATION MODIFICATIONS PLANNING,
DESIGN AND CONSTRUCTION (West
Rail Phase 1, Tsim Sha Tsui Extension, Ma On Shan Rail and Lok Ma Chau Spur
Line) (http://www.hkiecvd.org/paper/HKIE%20Paper_Final%20-27-3-03_.pdf) |
The challenge is to carry out construction work in a busy
operating train terminus with over 200,000 passengers a day. How works can be
carried out depend on detailed phasing which are developed together with
Operations in design stage, with one track occupied for works and keeping 3 out
of 4 existing tracks in operations. Train services, E&M services,
evacuation routes must remain un-interrupted at all times. Safety to the
public, train operation and construction are the top priority.
The
Hung Hom Station will change from a terminus station to an intermediate station
with the TST extension.
The early
curving railway alignment inside HUH encroaches onto 16 nos. major columns (2
in pair over an expansion joint). Those columns support the podium of the
Coliseum, a major recreational complex managed by Leisure & Culture Services Department. To ensure the
structural gauge requirement of the new alignment, the
affected columns are required to be demolished and underpinned. The
underpinning of the podium is by the construction of a reinforced concrete
portal with a versatile jacking system selected for load transfer from the
column to be demolished to the new reinforced concrete portal. Control of
cutting and jacking sequences is required to safeguard public using the station
in the vicinity, with detailed monitoring and instrumentation scheme, site
safety control and risk assessment. For health and safety of public, full
height hoarding with dust curtain is also placed during the operation. Figure 1 provides schematic
arrangement of the construction of the underpinning portals track by track in
phases.
Figure 1
Thorough
understanding of station operation and train planning, coordination with KCR
Operation and statutory authorities (BD, EMSD, FSD, HK Railway Inspectorate) is
required. Detailed arrangement of work activities within constraints of
operating station and selection of appropriate form of construction are
essential which should be quick in construction. Structural steelwork with
reinforced concrete flooring is used for the mid level concourse to minimize
the wet trade inside operating station which is both environmentally desirable
and retains the flexibility of construction to suit restricted hours of works
inside station.
The new mid
level concourse straddles across all the four domestic tracks and therefore
closure of tracks is inevitable, with typical phased construction shown in Figure
4. KCR train Operation has carried out rescheduling of train time table
during the construction period in order to maximise the use of the remaining 3
tracks in HUH during closure of a particular track. After a year of planning
and consultation with Operation, a set of phasing plans has been finalised with
a total of 9 phases of works. The track closure would start from Track 2
onwards, then Track 1, Track 4 and Track 3. Typical works during the 9-month
closure of Track 2 includes (i) erection of full height fire rated hoarding to fence
off part of the Track 2 and platform 2 from the public area, (ii)
decommissioning of the overhead line above Track 2, (iii) demolishing train
signal system in the vicinity and temporary decommissioning of the public
addressing system and next train indicator along the whole platform 2, (iv)
erection of the structural steelwork for the portion of reprovided mid level
concourse immediately above Track 2, (v) concreting of new concourse floor,
(vi) modification of electrical and mechanical system within closed area, (vii)
mini-piling work, (viii) concreting of the new column and beam, (ix) platform
edge modification work to suit the curved alignment, (x) track formation work
to the planned vertical alignment for relaying of tracks by permanent way
contractor.
The
requirement of acquiring works area in tracks is known as Possession of Track
(P). Six weeks advance booking is required to be given to East Rail Operation
known as Traffic Engineering Notice. An inherent constraint imposed by ER at
Hung Hom Station is 3 out of 4 domestic tracks should remain in service such
that heavy passengers flow can be catered. Under certain circumstances a
further track may be closed in non-peak traffic hours between 10:00am to
4:00pm, subject to the ER approval. Otherwise, night work during non-operating
hours executed between 1:30am and 5:30am is the only option. This implies less
efficient working hours and discontinuity of the works.
East
Rail establishes requirements preventing electric shock when working in train
operation area. Any person or object at any time cannot approach within 2m
radius of the live high voltage overhead line. If any planned construction
works involved any workers, plants or materials to be approached within such 2m
radius of the live high voltage overhead line, then the Possession of Track
must also include the Isolation of high voltage overhead line (I) to turn off
the voltage of the overhead line. The procedures of P and I frequently
prohibited the continuity of the works.
Staff
and workers are required to attend trainings before supervision or working
within ER boundaries, for example, for KCRC Resident Site Staff,
Person-in-Charge of Possession (PICOP), Staff-in-Charge of Non-Operating Area
(SICNOA), KCRC Qualified Supervision (KQS), Authorized Person (AP) for
isolation of HV lines, General Line Safety (GLS); and for contractor staff,
Contractor Qualified Supervision (CQS), AP and GLS.
Even simple
hoarding can become one of the important issue. Minimum platform width, queuing
zone must be maintained as well as the normal operation of the station. Some
hoarding in close proximity to operating tracks had to be erected during night
work [Figure 15]. Full height (8m) fire rated hoardings were provided in
some areas to fence off the
construction
work area so as to eliminate nuisance to the operating station.
Special
Safety Considerations
Majority of
the construction materials and plants are scheduled to be delivered to the
track area at night time after the closure of train operation. In order to prevent
sparks emitted by welding of the structural steelwork escaping out of hoarded
area, full height fire rated curtain had to be erected from the top of the
hoarding to the ceiling of the Station. The intumescent painting of the
structural steel member was carried out at mid-night as the operation
considered that the odour of the paint would harm the passengers. Difficulties
were also encountered when concreting to the new mid-level concourse, with
concrete pumped at high level over the platforms where thousands of passengers
passed through below.
For E&M
services and utilities diversion at high level, suspended bamboo scaffoldings
were erected at the ceiling of the Station as the working platform. The
contractor proposed to re-phase the sequence of work by providing the fire
rated working platform above the high voltage cable cross over to four
platforms. The advantage of this arrangement is to provide
the
continuity of E&M works at high level independent of rack possession,
minimizing the interrupt to the building services to the station and train
operation. [Figure 16]. Fire precaution and safety must be addressed.
Sufficient fire rated boards were used to spread over the platforms and safety
net were stretched under the platforms. For those scaffolding platforms above
the overhead high voltage cable, a minimum clear distance of
600mm between
the cable and the platform must be maintained as stipulated by the rules of
East Rail. No workers can be allowed on the bamboo scaffoldings above live
tracks during the
railway
operating hours.
Contractor
Safety Performance and Awards
As public and
construction safety are the top priority over all other concerns, a safety
management system is implemented by the contractor which includes (i) All
workers need to attend safety induction course before their commencement of
work. (ii) Tool-box talk to workers about 2 tails per worker per month. (iii)
Site safety committee to be held monthly. (iv) Joint site safety inspection to
be held weekly. (v) Conduct internal safety audit and external DNV safety audit
every six months. (vi) Conduct risk assessment and relevant safety training
before commencement of work. (vii) Conduct daily morning briefing to workers.
(viii) Permit to work system including permit to operate of crane, hotwork
permit and entry permit for confined spaces. (ix) Safety cash award to workers.
(x) Safety promotion on site such as fire drill. With the implementation of the
above safety measures and partnering approach, the project has the following
safety achievements: - (1) Hong Kong Occupational Safety Awards – Gold award
2002. (2) No safety compliant from public, with over 200 million passengers
passing through the Hung Hom Station during the last 2 years. (3) The accident
frequency rate is 0.42, which is significantly lower than the Government Works
Bureau target of 1.4 and KCRC ERE target of 1.25. (4) The lowest accident rate
within KCRC ERE, with only 3 reportable accidents in the whole contract.
The challenge
of construction work in a busy operating railway terminus with over 200,000
passengers a
day is an immense task. Train services and evacuation routes must remain
un-interrupted at all times. This demands detailed phasing, careful planning of
every step, close co-operation with station operations, and stringent safety
practices. Limited working space with restricted headroom for plant, limited
access to track area, material handling restriction, inefficiency at restricted
hours during track possession and night works. Underpinning of the podium and
load transfer are technical challenge. Safety to public, train operation and
construction is the top priority over all other concerns. The project is
successfully delivered through partnering approach to overcome various
constraints and
unforeseen
conditions. No safety complaint received from the public with over 150 million
passengers passing through the station during the construction period, and even
achievements in the safety awards under such conditions deserve a recognition
on its own.
- outbreak of any hazard may contribute public hazard
General - Public Works1, www.yubacity.net/documents/Chapter 14 - Public Works.pdf
- Hazards and public safety, http://www.plantown.com/Willits/3.12Hazards.pdf
Section 2 - Contractor Safety Handbook, www.hkbu.edu.hk/~ehsu/access/handbook.pdf
HOLT, G. (1998) A guide to successful dissertation study for students of the built environment. 2nd ed., School of Engineering and the Built Environment, University of Wolverhampton: The Built Environment Research Unit.
SIME, J. D. (1988) Safety in the built environment. School of Architecture, Portsmouth Polytechnic: E. & F. N. Spon.
GEORGE, H. & CHRIS, G. (1983) Practical Site Management – An Illustrated Guide, 2nd ed.,. Longman Group Limited: George Godwin.
LEE, H. K. (1996) Construction Safety in Hong Kong. 1st ed., Form Advertising Co., Ltd.: Lorrainelo.
No Data (2005) Code of Practice for the Lighting, Signing and Guarding of Road Work. 2005 Draft ed., Highways Department, Hong Kong Government: Publications Sales Unit. <http://www.hyd.gov.hk/eng/public/publications/Code/index.htm>
No Data (2002)
Contractor Safety Handbook. 1st ed., Hong Kong Baptist
University: Environmental Health & Safety Unit, Estates Office.