Jane's International Defense Review
August 2002
Pg. 52

U.S. Army Approach Decision Point On Future Of Comanche And Apache

By Bill Sweetman

A crucial decision is imminent for the future of the U.S. Army's attack helicopter force. The U.S. Army, Sikorsky and Boeing are completing plans for a total overhaul of the development program for the RAH-66 Comanche attack and reconnaissance helicopter. It calls for doubling the engineering and manufacturing development (EMD) budget envisaged two years ago when the current EMD contract was issued. Today, even program officials concede that the current EMD program - which was, itself, the fifth restructuring of a project that started in 1983 - would probably have been a technical failure.

The restructuring has been approved by the army but, in late June, awaited the verdict of both the Joint Requirements Oversight Committee, which will assess how well the Comanche meets cross-service needs, and the Defense Acquisition Board, which will measure the importance and cost of the Comanche against other major projects. Underlying the decision process is the recognized need for 'transformational' change in the way the US Army deploys and fights. There is no real doubt that the Comanche will be canceled if the senior Pentagon leadership rejects the restructured program.

This will have an enormous impact because the army's entire armed helicopter plan is based on the Comanche. The army plans to buy more than 1,200 of the new helicopters, and has cut back planned purchases of its current attack helicopter - the Boeing AH-64D Apache Longbow - to fund the new aircraft.

Comanche program history

The RAH-66 Comanche started as the LHX (Light Helicopter Experimental) project in 1983, with the goal of developing scout-attack and utility variants to replace the AH-1 Cobra, UH-1 Huey, OH-58 Kiowa and other aircraft. The program was narrowed down to a scout-attack helicopter in 1987, and the Sikorsky-Boeing team was selected to perform a demonstration/validation program in April 1991. The first of two YRAH-66 Comanche demonstrators made its first flight in January 1996, but the start of EMD was repeatedly delayed, for both technical and budgetary reasons; primarily, the U.S. Army regarded the AH-64D as a higher priority and could not fund both programs in parallel.

By the time the EMD contract was finally awarded, in June 2000, the army was facing problems with an aging fleet of helicopters. For this and other reasons, the army and its contractors signed an EMD contract with a short, demanding schedule, which skipped over some test stages that are normally considered crucial. The Pentagon's Directorate of Operational Test & Evaluation (DOT&E) and Congress' General Accounting Office (GAO) were highly critical of the EMD plans in separate reports issued in early 2001. "It is highly unlikely that the service can deliver the expected system performance within the current budget and schedule," the DOT&E commented. The GAO pointed to excessive risk with the Comanche's offensive avionics and its mission equipment package (MEP), and to unresolved issues with weight, and observed that the army planned to launch low-rate initial production (LRIP) just six months before the design would be frozen.

While the GAO earned a reputation for cautious and critical reports (some would call them nitpicking), it would appear that Congressional investigators were accurate in their assessment of the Comanche project. Deputy Program Director Mike Blake, who joined the program in early 2001, remarks that he and other incoming program managers recognized that there were a number of risk areas in the project. In particular, the original program did not include a full-scale systems integration laboratory (SIL), a test facility which includes sensors, processors and displays. "Software went straight to flight test," remarks Blake. "It was a huge risk." The plan also called for "10 major software drops" in a seven-year period - allowing little or no time to test, analyze and fix problems before the next revision of the software was issued to the flight-test aircraft.

In June 2001, Blake notes, the Comanche program managers "looked at the program and decided that we had a real executability issue." The industrial team members assembled a 'graybeard panel' of independent experts: one assessment was that the MEP development plan was "an all-red condition" - that is, every element embodied a high risk of failure - and that the overall chance of MEP success under the June 2000 contract was 23%. The Comanche team has now reorganized. In 1999, it formed a joint program office at the army's aviation headquarters in Huntsville, Alabama, supervising individual contractor offices in Stratford, Connecticut (Sikorsky) and Philadelphia (Boeing). Late last year, the Huntsville and Philadelphia offices were closed and a single program office was opened at Stratford. On the government side, the Comanche program is being closely monitored by the new Assistant Secretary of the Army for Acquisition, Logistics and Technology, Claude Bolton - a 30-year US Air Force (USAF) veteran who played important management roles in the F-22, B-2, Advanced Cruise Missile and other stealth projects. "We have a window of opportunity - that's this year," Bolton said in a recent interview with Bloomberg News. "Either we are on track at the end of the year or we are looking for something else to do: I could terminate the program."

EMD proposal

The revamped management team was due to submit a new EMD proposal on 15 July. The fundamental change is that the start of LRIP slips from 2005 to 2007. The money saved by delaying LRIP is moved into EMD - an additional US$3.4 billion, on top of the original US$3.2 billion budget. The new program acknowledges the fact that the initial operational capability (IOC) criteria in the original EMD contract were unusual, to say the least: the army planned to declare IOC in late 2006, but the first-unit-equipped date was two years later, at the end of 2008. The IOC unit "was not meant to go to combat," says Blake. Under the revised plan, the Comanche is due to reach initial training capability (ITC) in 2006, and the first combat unit will be equipped in September 2009. The army and the contractors plan to recoup much of the additional time and money spent on EMD by increasing the full production rate, reached after 2012, from 60 to 96 aircraft per month. This is expected to save most of the added EMD funding. If the army stays within the current total planned cost for the Comanche program, it will be 126 aircraft short of its 1,207-aircraft goal, but it will have the option of adding more funds at the end of the program to buy the rest of the aircraft. The additional EMD money and time will be used for work that was deferred to the LRIP stage under the previous program. Roughly half the funds, according to Blake, will be used to support development of the MEP. A complete SIL or 'hot-bench' will be constructed, and the software release schedule will become more realistic. MEP software will also include 'Level 4' control for unmanned aerial vehicles (UAVs), allowing the Comanche crew to take direct control of the navigation and sensors of a UAV. The EMD increase will also pay for engineering and test efforts that address the Comanche's vertical rate of climb (VROC) problems, including weight reductions and propulsion and aerodynamic improvements.

The new EMD program will use fewer aircraft (nine versus 13) because the longer schedule allows each aircraft to fly more test hours before IOC. The first EMD aircraft will be completed in late 2004 and should make its first flight in March 2005. The EMD aircraft conform to the ITC configuration. The airframe and propulsion system should meet the definitive Comanche standard, with the uprated Rolls-Royce/Honeywell T800-LHT-802 engine and complete low-observable (LO) treatments. However, the ITC aircraft will carry no weapons except the General Dynamics/Giat turreted gun system. Operational requirements

The EMD aircraft will be followed by 198 LRIP aircraft in the Block 1 configuration, which will be delivered over five years from July 2008. The Block 1 "meets 90% of the operational requirements document," says Blake. It will carry Hellfire missiles, a fire-control radar and satellite communications (satcom) equipment.

Full-rate production deliveries are due to start in August 2013 with the Block 2 configuration. This will include the External Fuel and Armament Management System, carrying extra weapons and fuel-weight improvements; and further software enhancements. It should also carry an air-to-air missile (AAM), provided the current army-versus-Congress dispute over the Thales SMS Starstreak has been resolved by 2013. However, Blake notes, the new 'spiral' development program means that Block 2 is not yet completely defined, and need not be defined until much later in the decade, so that the details of Block 2 can reflect emerging technology, changing user requirements, and lessons from building and testing the ITC and Block 1 configurations. Comanche supporters continue to argue that the helicopter is unique, mainly because of its combination of stealth and integrated avionics. More than any other helicopter, Comanche has been designed for LO from the outset. The difference between a fixed-wing stealth aircraft and an LO helicopter stems from differences in the environment and the threat, and consequently in the importance of different signatures. While radar is dominant for a fixed-wing aircraft, noise will often be the first indicator of an approaching helicopter, and low-altitude threats use infrared (IR) tracking and homing more than radar. A helicopter uses terrain to mask itself from ground-based radar, and airborne radars have to contend with strong ground clutter.

Acoustic stealth has two elements: the reduction of total noise level and the elimination of distinctive sound patterns. The Comanche has a five-blade rotor, increasing the frequency of blade-to-blade noises. Drooped, swept blade tips have been evaluated to reduce noise. The directional control fan in the tail has eight blades with shrouded tips, eliminating interaction between the wakes of the main and the tail rotor.

The Boeing 360 demonstrator of the late 1980s - which was used to evaluate some LO technologies in support of the Boeing-Sikorsky LHX proposal - exploited its high-speed rotor design to reduce noise. A high-speed rotor needs to have a low stalling speed at the root (so that the retreating blade can produce lift), and this means that it is theoretically possible to fly with reduced rotor rpm at moderate speeds (in the region of 170km/h), further reducing noise. It is not known whether this 'sneak mode' is used on the RAH-66: Blake says he is "not well versed" on any such technique. Comanche incorporates an elaborate IR suppression system. Exhaust gases are piped to linear nozzle arrays, pointed downwards, located in vertical ejector ducts on each side of the tailboom. The high-speed exhaust creates a pressure drop in the duct, drawing ambient-temperature downwash from the rotors through the duct inlets in the upper surface of the tailboom. The result is a very small difference between the exhaust and the ambient air temperature.

Radar cross-section (RCS) is reduced by tilting all the airframe surfaces away from the vertical - including the tail, which has an asymmetric cant angle - and by incorporating a retractable landing gear and internal weapons. The Comanche carries missiles on weapon-carrying doors in the side of the fuselage, and the turreted gun rotates through 180º to stow in a fairing beneath the nose. Flush air inlets, a convoluted inlet particle separator and the exhaust system conceal the engines from radar. "One of the biggest challenges" in the program, according to Blake, has been the development of shrouds for the rotor head, which conceal the complex machinery of the head from radar without hampering access for maintenance. The first Comanche prototype flew with a number of rotorhead designs, comprising root cuffs and pyramidical fairings around the mast, but a definitive design was selected late last year and has not been flight-tested.

'Stealthy' blades

The main rotor and FanTail blades of the production aircraft will also be shaped and treated to reduce RCS. At one point in the long development program, there was a possibility that Comanches would use untreated blades in peacetime and be fitted with low-RCS blades for combat operations, but it is now the intention to fit all aircraft with 'stealthy' blades. The Hexcel company provides 'special-process honeycomb' materials for the Comanche program, possibly for use in the rotor blades.

The design of a stealthy helicopter is described as "at least a thousand times more time-consuming" than a fixed-wing aircraft, "because the rotating blades, both the main rotor and the tail rotor, must be modeled in thousands of positions,"according to one Sikorsky statement. Sikorsky has developed in-house codes to perform RCS predictions for the Comanche, and installed an SGI Origin 2000 computer server in February 2000 to support this work. The computer has 128 processors and two terabytes of storage. Sikorsky now claims that "our level of efficiency and productivity in stealth calculations is unequalled in the airframe industry."

A full-scale RCS model built by MicroCraft has been tested at Boeing's outdoor RCS range at Boardman, Oregon. (Located in the northern part of the state, 270km east of Portland, the Boardman range has been a well-kept secret for some years. It uses a rail-mounted mobile shelter over the main model pylon, similar to the well-regarded McDonnell Douglas range at Grey Butte, California.) Both partial and full-scale tests have been carried out.

Airframe advances

The EMD Comanche airframe will be "80%" different from the prototypes, according to Blake. One reason is that the helicopter's weight increased during development, partly because of the incorporation of extra equipment such as the radar, to the point where its ability to meet the army's 500ft/min VROC requirement wasin doubt. The EMD aircraft has a larger-diameter rotor than the prototypes, together with greater power. The first Comanche prototype flew with the 843kW T800-LHT-801 engine in June 2001, with 17% more power than the original T800-LHT-800, and the baseline engine for the production engine is the 895kW T800-LHT-802. The new engine is expected to deliver the extra power without prejudice to its 6,000h design life. The other visible change to the design during prototype flying, the adoption of an H-shaped tail to reduce vibration, will be reflected in the EMD design.

Because of the changes between the prototype and EMD designs, the prototypes are of limited use to the EMD program. The first aircraft, which was used for envelope expansion and concluded its testing with the H-tail and aerodynamically representative rotor-mounted radome, made its last flight in January 2002 after 318 flights and 387h. The second Comanche returned to the flight-test program in late May, with prototype mission computer cluster and new cockpit displays. By September, it is expected to be performing an initial flight demonstration of the Night-Vision Pilotage System, and it will fly some 15 hours per month through October. The other element of the electro-optical sensor system(EOSS), the Electro-Optical Target Acquisition and Designation Sensor, has undergone preliminary tests on a Black Hawk helicopter. The EOSS, developed by Lockheed Martin, uses similar technology to the improved optronics being developed for the Apache. Other aspects of the Comanche MEP, however, are new. Harris is providing many key components of the MEP, and is replacing the military-unique components originally planned for the Comanche with commercial-type technology. The MEP is linked together by two optical networks. The High-Speed Data Bus, running at 80Mb/sec, links the main avionics subsystems. Point-to-point Image Data Distribution Networks, running at 1Gb/sec, link the sensors to the processors and feed image data to the cockpit displays. Harris is also providing memory storage devices, based on commercial PCMCIA memory cards and using MPEG compression codes to store video imagery. Also from Harris are the flat-panel displays, based on ruggedized commercial glass, and the digital map system. Northrop Grumman provides the mission computer cluster for the Comanche, along with the target acquisition system software (TASS). Hosted on the mission computer, TASS includes an automated target tracker and will eventually include aided target detection and classification as well as a target threat manager. Northrop Grumman also produces the fire-control radar, in a joint venture with Lockheed Martin. The radar is based on the Apache Longbow's APG-78, but features an active electronically scanned array (AESA): a brassboard AESA was demonstrated at Baltimore and Yuma in early 2000. All Comanches will be able to carry radar, but it is expected that only one third of the aircraft in the field will use the system in service, using datalinks to transfer targeting data to other Comanches in the formation.

Rockwell Collins' Kaiser Electronics division is developing the Helmet Integrated Display Sighting System (HIDSS), which has been in EMD since passing its preliminary design review in late 2000. The HIDSS is a two-piece system that attaches to a standard aviator helmet; the optical and tracking systems make up an Aircraft Retained Unit which remains with the aircraft at all times. The binocular display covers a 35x52º field of view, and the imagery is generated by small commercial-type 1,280x1,024-pixel AMLCDs produced by Kopin, with a Kaiser backlight.

ITT Avionics is the integrating subcontractor for the Comanche's self-defense suite. It will be based on the ITT/BAE Systems ALQ-211(V)3 radar warning receiver, a variant of the AN/ALQ-211 Suite of Integrated RF Countermeasures (SIRFC) under development for the Apache. Additionally, Goodrich is providing a laser warning system and BAE Systems is providing a point chemical detector. The first suite is due to be delivered in the second quarter of 2003.

The Comanche's communications, navigation and identification suite is one area where design work is being augmented with new funding. The army intends to equip the Comanche with a satcom datalink to provide a real-time non-line-of-sight to other aircraft and commanders. The Comanche program is working with the Joint Strike Fighter office to produce a low-cost, LO-compatible satcom antenna, which will be located above the tail, but is ready to develop a Comanche-specific satcom antenna if it is needed.

Revolutionary vehicle

The Comanche's combination of speed, stealth and advanced avionics makes it a potentially revolutionary vehicle. However, it is also early in its development. Two prototypes have flown less than 500h between them. No weapons have been fired and only a small part of the MEP has been flown on the Comanche. This is one reason why Boeing is lobbying Congress and the army to take actions that will maintain its ability to produce and support the army's in-service attack helicopter, the veteran AH-64 Apache.

Apache deliveries

In April, Boeing delivered to the U.S. Army the last of 232 AH-64D Apache Longbows supplied under a five-year contract. The first of 269 aircraft covered by a second five-year contract, signed in October 2000, was handed over in May. All these aircraft were originally delivered as AH-64As and have been (or will be) rebuilt as AH-64Ds. All the aircraft delivered to date - Lots 1-5 under the first contract and Lot 6 aircraft under the second contract - share a common configuration known as Block 1.

Next year, with Lot 7, Boeing will deliver the first Block 2 AH-64Ds. The principal changes in these aircraft center on better processing and communications. New computers and a fiber optic databus will improve the crew's ability to handle multiple targets, and the Improved Data Modem will be upgraded to handle a two-times-larger set of messages. Later lots will include improved radio equipment.

More changes are due with the Lot 8 Apache, to be delivered in 2004. As well as a new Harris digital map, the Lot 8 aircraft should include the Target Acquisition Designation Sight (TADS) and Pilot's Night-Vision Sensor (PNVS), under development by Lockheed Martin and Boeing under the Arrowhead XR (extended range) program.

The first test example of the new TADS/PNVS was delivered to Boeing for bench testing recently and could make its first flight on the Apache by the end of this year. TADS/PNVS is one of the three most costly maintenance items on the Apache, and the new unit should cost less than half as much to support as its predecessor. The army plans to retrofit all its Apaches, including the remaining AH-64As, with the new system.

The PNVS in the new system incorporates a higher-resolution thermal imager with 10 times as many elements, improving the pilot's ability to detect wires and other small obstacles. It also includes an image-intensification (I2) tube, allowing the pilot to select the best system for any conditions. This will also reduce the need for the pilot to use night-vision goggles (NVGs); the difficulty of training with both the head-steered PNVS and NVGs emerged as a problem after Kosovo operations, but now the pilot will be able to use an I2 image with the helmet display. The new system will have an improved multitarget auto-tracker and an automated boresighting system, eliminating a complex maintenance task, and a better built-in test system. The TADS turret now incorporates a modern thermal imager, with similar components to the PNVS, and a daytime CCD camera which replaces the direct-view optics in the current system.

EFW Inc, the U.S. division of Elbit, acquired Honeywell's helmet-mounted display (HMD) line in early 2001, including the Apache's Integrated Helmet Display and Sighting System. EFW is now under contract to provide an improved HMD for the Apache, probably based on the USAF's Joint Helmet-Mounted Cueing System. It will probably provide a wider field of view, which TADS/PNVS is intended to support.

Block 2, remarks a Boeing program official, provides the army with a much improved helicopter that can fly and fight in a wide range of weather conditions, and which has direct connectivity with Joint STARS (Surveillance Target Attack Radar System) and its associated ground stations. However, deliveries end in July 2006 and Boeing and the US Army are looking at the next step in the Apache program, known as Block 3.

Currently, the U.S. Army has no intention of upgrading its 200 AH-64As, let alone building new Apaches. The service's most basic goal is to bring the Block 1 and 2 AH-64Ds to a common configuration. However, Boeing and the army have also identified a number of desired improvements that could - depending on budgets - be part of a Block 3 program, and Boeing is working on technology to ensure that these upgrades are ready if needed.

One improvement involves extending the range of the Apache's sensors and weapons, with the goal of improving its performance in littoral operations. Changes would include new processing for the APG-78 radar, and a passive ranging capability for the APR-48 radio-frequency interferometer sensor. Boeing is studying a version of the Alenia Marconi Systems Brimstone missile (itself derived from Hellfire), with a longer range, dual-mode guidance combining laser designation with either a millimeter-wave or IR seeker, and a blast-fragmentation warhead. Its first use could be as a close-support weapon for U.S. Navy F/A-18s and MH-60s, but it would also be applicable to Apache.

Missile dispute

Integration of an AAM on the Apache is the subject of a dispute between the U.S. Army and Congress. The choice lies between the Raytheon Stinger Block 2, an IR homing fire-and-forget missile, and the Thales SMS Starstreak, a laser beam-riding missile guided by the TADS. The US Army's doctrine is not clear on the use of AAMs on attack helicopters (as opposed to scouts). The most important roadblock is that Congress has mandated a shoot-off between the Stinger and Starstreak, but the army maintains that Starstreak cannot be fired safely from the Apache because of debris and blast problems. Thales is working to resolve these issues, but neither Stinger nor Starstreak can be tested, as things stand, until the army's objections are addressed. Another as-yet-unfunded army requirement is an updated suite of aircraft survivability equipment. Since the early 1990s, the army's plan has been to fit the Apache with the ITT ALQ-211 SIRFC and the complementary ALQ-212 Suite of Integrated IR Countermeasures (SIIRCM); produced by BAE Systems, ITT and Raytheon, it comprises a missile warning sensor, a steerable laser-based jammer and new expendable countermeasures. Having developed these systems, the army has postponed any decision on fitting them to the Apache fleet, on the grounds of cost and weight.

One candidate is BAE Systems' Helicopter Integrated Defensive Avionics Suite (HIDAS), developed for the UK's WAH-64 Apache variant. Deliveries of the initial HIDAS started late last year. It is simpler than the planned SIRFC/SIIRCM fit, comprising the Sky Guardian 2000 radar warning receiver; the BAE Systems AAR-57 Common Missile Warning System; a laser warner; and an automated countermeasures dispenser - but it can be expanded to accommodate a directional laser jammer.

One Apache export customer has already selected HIDAS, while Egypt has chosen the Northrop Grumman ALQ-162(V)6 active jamming system for its upgraded AH-64Ds.

Not surprisingly, out-of-production parts are an issue for the Apache. Some problems have been forestalled by buying large lots of parts which are approaching obsolescence, but this defers the replacement issue. In the current system, too, replacing one component in a line-replaceable unit (LRU) can mean requalifying the entire LRU.

Boeing is looking at converting the Apache to an open-systems architecture approach, based on the Bold Stroke architecture developed by the company's Phantom Works. LRUs would be replaced by a permanently installed backplane, providing power, cooling and data connections for multifunctional cards based on commercial components.

The U.S. Army is also studying the incorporation of UAV control capabilities in the Apache. The service is interested in teaming manned attack helicopters with UAVs such as the TRW/IAI RQ-5 Hunter and its planned follow-on system. The most important technical challenges are communications - including the ability to transmit streaming video from the UAV to the helicopter - and managing workload for the crew. To address the latter issue, Boeing is looking at the Rotorcraft Pilot's Associate (RPA) technology that the company developed under a long-running army-sponsored program, originally with the goal of reducing workload for the crew flying the helicopter. Now, RPA-derived tools such as adaptive automation, real-time, automated mission replanning and automated sensor control are being applied to the task of operating a UAV from the helicopter cockpit. Teaming a UAV with the helicopter "dramatically increases the range, and the area that the helicopter can cover", says a Boeing engineer. "It's also safer for the flight crew."

Other potential Block 3 changes will affect the helicopter's airframe and powerplant. The rotor and transmission are the largest maintenance items after the TADS/PNVS, and have not been changed since the Apache was first fielded. Boeing is developing a composite rotor blade for Apache: it will cost less to build than the current blade, provide potentially higher performance (it can absorb more power) and will last at least twice as long in service. Also in the works is an upgraded drive system, similar in design to the current transmission but using new materials, coatings and processes. It will be able to handle more power (2,540kW versus 2,100kW) and will cost half as much to support.

Currently, U.S. Army AH-64Ds are fitted with both the General Electric T700-GE-701C engine and the less powerful -701 variant. Although all AH-64Ds can be fitted with the Longbow radar, only one third of the aircraft in any unit carry the radar, and these are usually the aircraft with the more powerful engines. The army would at least like to standardize its fleet around the T700-GE-701C, or even the more powerful -701D engine now being developed for the UH-60M Black Hawk.

Common Engine Program

Definitely deferred beyond Block 3 are more substantial airframe improvements such as a five-blade rotor (although the new blade is designed to be adapted to a five-blade system) and a new engine. Army plans for a Common Engine Program (CEP), an all-new, high-performance engine to replace the T700 in all its applications, are on hold while the army reassesses its plans for its utility helicopter fleet.

The CEP was aimed at developing a 2,240kW engine tailored to fit T700-powered aircraft. The program goals included 25% better fuel economy, a 60% power-to-weight improvement, and a 20% reduction in operation and support costs. The main application for CEP was the projected Sikorsky UH-60X, but the army has now shelved this program and is writing requirements for a new Future Utility Rotorcraft which may be larger and more powerful.

The Apache is still active in the foreign military sales market. Boeing has sold more than 160 AH-64Ds for export, half of which have been delivered. AH-64Ds have been delivered to the Netherlands, the UK, Israel, Kuwait and Singapore (the latest customer to take delivery, in May); both Egypt and Israel have signed contracts under which AH-64As will be upgraded to AH-64Ds.

Currently, Boeing is involved in eight Apache sales campaigns worldwide, half of them involving new customers and half for existing users, including both new aircraft and D-model upgrades. The company is predicting three contract announcements for a total of around 30 aircraft by the end of this year, and sees potential sales for another 100-120 aircraft in the next two years.

Potential new buyers include Taiwan, which plans to acquire 30 new AH-64Ds. Kuwait has applied for permission to buy an additional 16 AH-64Ds, and Korea has indicated its intention to buy 36 new aircraft.

The U.S. Army now has six operational AH-64D battalions. The sixth unit, qualified in June 2002, will be the first Longbow battalion stationed in Europe when it returns to Germany later this year. Longbows have also deployed to Korea and to the Middle East, where they are supporting Operation 'Desert Spring', defending Patriot missile units in association with Operation 'Southern Watch'. So far, only the older AH-64As have been used operationally in Afghanistan.

The army is short of attack helicopters, having retired its Cobras in 2001. Out of 740 Apaches built for the U.S. Army, just over 700 remain, leaving around 200 older AH-64As which are not yet earmarked for conversion into Ds. So far, the army plans to retain 79 of these aircraft for the National Guard and Army Reserve, replacing Cobras. However, as the active army force transitions to the AH-64D, these small groups of AH-64As - some units will have single figures of aircraft - will be almost completely irrelevant. Boeing is making the case that some of the remaining AH-64As should be rebuilt as Ds and that the rest should be retired, eliminating training and support which is specific to the older version of the aircraft. It is also argued - not without some backing in common sense - that this would keep the Apache line moving until the army has a clearer idea whether the Comanche will live up to its lofty promises.


IS THIS SMART MAKING "D" MODEL APACHES IF THEY CANNOT OPERATE IN THE MOUNTAINS?

High-Altitude Operations by George J. Mordica II, Senior Analyst, CALL states:

OBSERVATION: The traditional assault aircraft has been the Black Hawk Helicopter (UH-60). In actual operations today in Afghanistan, it is the Chinook Helicopter (CH-47).

DISCUSSION: Due to the limitations of the UH-60 at high-altitudes, the CH-47 is the primary lift aircraft for air assault operations. CH-47s can quickly outpace escorting AH-64s. AH-64s primarily train to fly at night to take advantage of their capabilities. They are being forced, however, to fight during the day due to the limitations of the CH-47 night capability.

TTP:

Units must integrate the CH-47 into training as a lift asset during air assault.

AH-64s must be mentally prepared to operate in daylight conditions in Afghanistan.

CH-47s should operate at a slower speed to ensure they maintain attack aviation protection.

At home station training, AH-64 attack and CH-47 lift helicopters (air assault) need to get into the habit of working together.

CH-47 crews should train on NVD more often.

OBSERVATION: Army forward observers (FO) used Air Force (AF) close air support (CAS) as the primary means of fire support, using indirect positive control of emergency close air support (ECAS) during Operation Anaconda.

DISCUSSION: No artillery fire support was available during the first few months in Afghanistan. Units relied on company and battalion mortars. The only other fire support available was AF CAS. Normally, FOs do not use CAS, but the techniques used by the FO and ETAC was indirect positive control. FO communicates with ETAC; the ETAC communicates to the aircraft. ECAS is when the fire support officer (FSO) or FO speaks directly to the aircraft and identifies himself as an untrained observer.

TTP:

It is extremely important that fire support officers (FSO) and forward observers (FO) are trained as an untrained observer to provide redundancy to the ETACs.

Indirect positive control is necessary for the FOs to accurately identify the target with a 10-digit grid. Since CAS cannot bracket, FO accuracy is a must for a first round hit.

OBSERVATION: Operations at high altitudes greatly affect attack aviation since aircraft do not have the lift capabilities they normally have at lower altitudes.

DISCUSSION: Air assault from 8,000-10,000 feet must be conducted by the CH-47. However, the CH-47 and the AH-64 previously have not trained together. The high altitude prevents the AH-64 from maintaining a hover above escorted helicopters. The AH-64D Longbow cannot fly at the operation altitude due to the additional weight of the Longbow system dependent on aircraft weight or weather and temperature. The AH-64D radar is not relevant due to the threat.

TTP:

Pilots must attend high-altitude training (HAT).

Aerial gunnery preparation for Afghanistan should focus predominately on running fire. This requires ground observers to report position, then the ranges and bearing, to the aircraft.

Due to the altitude, all engagements are considered running fire.

Army aviation units need to modify the traditional close combat attack (CCA) to orient attack aviation on the target during a running fire. AH-64 pilots should use the combat mission simulator set to replicate high altitudes.

OBSERVATION: Ground and aviation unit commanders must understand and accept the significance that high altitude and dust have on aviation assets and aviation availability.

DISCUSSION: Lift helicopter assets in this unit are CH-47s, UH-60Ls, and UH-60As. Aviation unit operations are primarily taking place at 10,500 feet above sea level (ASL). The environment drives all other operational considerations. The long distances require the unit to use "fat cow" refueling operations and forward area arming refueling point (FARP) operations that require extensive planning and preparation. Units found that maintenance was all pushed up due to the flying conditions and high operational tempo. Scheduled and phased maintenance was moved to 30 hours of operation instead of the normal 45 hours conducted at home station. The dusty conditions required full cleaning after every mission, to include lube and purge. Larger air movements are a necessity in this environment; some were executed 165 nautical miles.

TTP:

Leaders need to focus on the maintenance and plan phase to ensure maximum availability for operations.

Pilots need to have high-altitude training (HAT) in Colorado, Utah, or Idaho. [Move 10th Mountain Division to the mountains ie; Fort Carson, Colorado]

These sites are trained in power management and flying in high mountain winds. All lift aircraft need to be prepared for non-standard casualty evacuation (CASEVAC).

[BE CLEAR YOU MEAN SKEDCO HOVERING LITTER HOISTING, RIGHT? SAY IT DAMN IT!]

Units must train for extensive aerial resupply in the mountains.

Question #1: Why not send Army Arty FOs to the USAFs aircraft CAS FAC (ETAC) school?

Question #2: If AH-64Ds are too heavy for Afghan mountain combat ("A" models trouble in Kosovo/Albania TF Hawk, too) why not?

a. Lighten them up for more power--with just GUN pods and rockets?

How much weight must we shed to get effective mountain flying? Or is it the tail rotor is too weak?

b. Give them Piasecki VTDP for more tail rotor authority?

c. If rotor gunships can't work why not.....(drum roll please)

GET FIXED-WING ATTACK AIRCRAFT WITH BETTER AERODYNAMIC LIFT FOR MOUNTAIN COMBATS INTO THE ARMY TO DO MAS SINCE THE USAF DOESN'T WANT TO DO CAS THAT AGGRESSIVELY?

Ready NOW Options to do Chuck Myers' Maneuver Air Support (MAS) compliment to USAF CAS

MAS
A-10 Cactus Air Force
Killer Bees

1. OV-1 Mohawks
2. Rutan's ARES
3. OV-10 Broncos
4. Sadler Piranha
5. SAAB Supporter

FEEDBACK!

> itsg@hotmail.com