The Shed


Phase I: Floor/Foundation: Complete 8/15

Phase II: Wall Framing: Complete 8/19

Phase III: Wall sheathing: Complete 8/23

Phase IV: Roof rafters: Complete 8/29

Phase V: Roofing: Complete 9/4

Phase VI: Door/Window: Complete 9/5

Phase VII: Siding: Complete 10/17

Phase VIII: Finish: Complete 10/31