Timeline for Milestones
|
|
October |
05 -
First
team meeting to decide about the subject for the project
(done) |
06 -
Defining
research question
(done) |
12 -
Deadline
for first draft of project plan
(done) |
24 -
Feedback
from BSc Jeroen Bergmann on the first draft
(done) |
27
- Deadline for Project Plan
(done) |
28 -
Deadline
for first daft of web page
(done) |
31 -
Deadline for questionnaire
(done) |
|
|
|
November |
06 - Deadline for Web Page
(done) |
07 - Beginning of pilot project
(done) |
11 -
Send letters to the clinic to inform about the survey
(done) |
13 - End of Pilot project
(done) |
14 -
Beginning of data collecting
(done) |
18 -
Send e-mail reminding the clinics about the survey
(done) |
30 -
End of data collection
(done) |
|
|
|
December |
04 - Deadline for data analysis |
06 - Team meeting: analyzed data to paper group |
11 -
Deadline for first draft of the paper |
16 -
Deadline for first draft power point
presentation |
17 -
Deadline for final version draft of the paper |
18 -
Deadline for feedback on paper |
19 -
Hand in the paper to Jeoren Bergmann & group presentation |
|
|