Project1


Project Start Date: Tue 28/05/02
Project Finish Date: Thu 30/05/02

Tasks

IDTask NameDurationStartFinishResource Names% Complete
1Background information64 daysThu 28/02/02Tue 28/05/02 0%
2Proposal Report16 daysFri 22/02/02Fri 15/03/02 0%
3Analsis of existing products65 daysMon 25/02/02Fri 24/05/02 0%
4Looking at the componets38 daysThu 21/02/02Mon 15/04/02 0%
5Conceptual design52 daysTue 19/03/02Wed 29/05/02 0%
6Spring system52 daysThu 14/03/02Fri 24/05/02 0%
7Speed adjustment43 daysTue 19/03/02Thu 16/05/02 0%
8Height adjustment38 daysWed 20/03/02Fri 10/05/02 0%
9British Standard50 daysTue 19/03/02Mon 27/05/02 0%
10Manufacturing Process40 daysTue 26/03/02Mon 20/05/02 0%
11Web Page30 daysFri 19/04/02Thu 30/05/02 0%
12Interim Report53 daysTue 19/03/02Thu 30/05/02 0%

Resources

IDNameGroupMax UnitsPeak Units

Assignments

Task IDTask NameResource NameWorkStartFinish% Work Complete