Project2


Project Start Date: Tue 04/06/02
Project Finish Date: Tue 03/09/02

Tasks

IDTask NameDurationStartFinishResource Names% Complete
1Embodiment design50 daysTue 04/06/02Mon 12/08/02 0%
2Detail Design52 daysTue 18/06/02Wed 28/08/02 0%
3FMEA24 daysFri 26/07/02Wed 28/08/02 0%
4Design for Manufacture24 daysTue 30/07/02Fri 30/08/02 0%
5Costing7 daysWed 21/08/02Thu 29/08/02 0%
6Final Report55 daysWed 19/06/02Tue 03/09/02 0%
7Poster3 daysWed 28/08/02Fri 30/08/02 0%
8Prepare mannual1 dayFri 30/08/02Fri 30/08/02 0%
9Web Page 65 daysTue 04/06/02Mon 02/09/02 0%
10Powerpoint3 daysWed 04/09/02Fri 06/09/02 0%
11Presentation2 daysMon 09/09/02Tue 10/09/02 0%

Resources

IDNameGroupMax UnitsPeak Units
 Unassigned 100%0%
1Embodiment design  100%
4Design for Manufacture  100%
5Costing  100%
6Final Report  100%
7Poster  100%
9Web Page   100%
10Powerpoint  100%
11Presentation  100%
2Detail Design  100%
3FMEA  100%
8Prepare mannual  100%

Assignments

Task IDTask NameResource NameWorkStartFinish% Work Complete