Project Start:
Project Finish:

Sun 9/23/01
Thu 11/29/01



Tasks


Task NameDurationStartFinish% Complete
1 Initial Investigation
2 daysSun 9/16/01Mon 9/17/01100%
1.1 Problem Identification
1 daySun 9/16/01Sun 9/16/01100%
1.2 User's Analysis
1 dayMon 9/17/01Mon 9/17/01100%
1.3 Scope Negotiation
1 dayMon 9/17/01Mon 9/17/01100%
Initial Investigation Completed
0 daysMon 9/17/01Mon 9/17/01100%
     
2 User Requirement Analysis
5 daysTue 9/18/01Sat 9/22/01100%
2.1 Business Need Identification
2 daysTue 9/18/01Wed 9/19/01100%
2.2 System Requirement Analysis
1 dayThu 9/20/01Thu 9/20/01100%
2.3 System Layout Objectives
1 dayFri 9/21/01Fri 9/21/01100%
2.4 Prioritize Requirements
1 daySat 9/22/01Sat 9/22/01100%
User Requirement Analysis Completed
0 daysSat 9/22/01Sat 9/22/01100%
     
3 Business process Analysis
6 daysTue 9/18/01Sun 9/23/01100%
3.1 Business Process recognition
1 dayTue 9/18/01Tue 9/18/01100%
3.2 Process Efficiencies & Analysis
2 daysWed 9/19/01Thu 9/20/01100%
3.3 Process Integration Alternatives
1 dayFri 9/21/01Fri 9/21/01100%
3.4 Evaluate Best Solution
2 daysSat 9/22/01Sun 9/23/01100%
Business Process analysis completed
0 daysSun 9/23/01Sun 9/23/01100%
     
4 Data Requirement Analysis
10 daysMon 9/24/01Wed 10/3/01100%
4.1 Identify Sources Of Data
2 daysMon 9/24/01Tue 9/25/01100%
4.2 Analyze Dataflow
3 daysWed 9/26/01Fri 9/28/01100%
4.3 Data Organization Analysis
5 daysSat 9/29/01Wed 10/3/01100%
Data Requirement Analysis Completed
0 daysWed 10/3/01Wed 10/3/01100%
     
5 Data Procurement
5 daysThu 10/4/01Mon 10/8/01100%
5.1 Analyze Data Capture Technique
2 daysThu 10/4/01Fri 10/5/01100%
5.2 Data Gathering
3 daysSat 10/6/01Mon 10/8/01100%
Data Procurement completed
0 daysMon 10/8/01Mon 10/8/01100%
     
6 Database Design
10 daysTue 10/9/01Thu 10/18/01100%
6.1 Data Organization Design
4 daysTue 10/9/01Fri 10/12/01100%
6.2 System Interface Design
3 daysSat 10/13/01Mon 10/15/01100%
6.3 Data Application Design
3 daysTue 10/16/01Thu 10/18/01100%
Database Design Completed
0 daysThu 10/18/01Thu 10/18/01100%
     
7 Business Process Interface Design
9 daysFri 10/19/01Sat 10/27/01 100%
7.1 Data Integration Analysis
5 daysFri 10/19/01Tue 10/23/01 100%
7.2 User Interface Design
4 daysWed 10/24/01Sat 10/27/01 100%
Business Process Interface Design completed
0 daysSat 10/27/01Sat 10/27/01 100%
     
8 Programming
15 daysSun 10/28/01Sun 11/11/01 100%
8.1 Program Modularization
3 daysSun 10/28/01Tue 10/30/01 100%
8.2 Modules Assignment
5 daysWed 10/31/01Sun 11/4/01 100%
8.3 Coding Session
7 daysMon 11/5/01Sun 11/11/01 100%
Codding Completed
0 daysSun 11/11/01Sun 11/11/01 100%
     
9 Unit Testing
6 daysMon 11/12/01Sat 11/17/01 100%
9.1 Unit Testing
6 daysMon 11/12/01Sat 11/17/01 100%
Unit Testing Completed
0 daysSat 11/17/01Sat 11/17/01 100%
     
10 System Testing
6 daysSun 11/18/01Fri 11/23/01 100%
System Testing Completed
0 daysFri 11/23/01Fri 11/23/01 100%
     
11 Documentaion & Presentation
6 daysSat 11/24/01Thu 11/29/01 100%
11.1 Documentaion
5 daysSat 11/24/01Wed 11/28/01 100%
11.2 Presentation
1 dayThu 11/29/01Thu 11/29/01 100%
Documentation & Presentaion Completed
0 daysThu 11/29/01Thu 11/29/01 100%