Proposed Audit Trail and related areas.
No. |
Area / Department |
Related Element(s) |
1 |
Management |
4.1, 4.2.5, 4.14, 4.17 |
2 |
APQP + Design |
4.3, 4.4, 4.2.3, 4.2.4, 4.9.5 |
3 |
Sales |
4.3, 4.15.6 (delivery) |
4 |
Plant / Production (I, II, III, …) |
4.8, 4.9, 4.10.3, 4.10.4, 4.11 (Daily Mastering), 4.12, 4.13, 4.15, 4.20 |
5 |
QC (Inspection and Test) |
4.10.2, 4.10.3, 4.10.4 |
6 |
QC (Corrective Action) |
4.13, 4.14 |
7 |
Store & Warehouse |
4.15 |
8 |
Procurement / Purchasing |
4.6, 4.10.2, 4.15, 4.7 |
9 |
Document Control |
4.5, 4.16 |
10 |
Calibration & MSA |
4.11 |
11 |
Training |
4.18 |
12 |
PM & Tooling |
4.9 g, 4.2.6, 4.7 |
13 |
Internal Audit + Safety + 5S |
4.17, 4.6.1.2, 4.9.b.1, 4.9.b.2 |
14 |
Servicing |
4.19 |