Frequently-Asked Questions for Control Chart Implementation
Within subgroup variation V.S. Between
Subgroup Variation
|
|
X-bar chart |
R chart |
|
|
Tracking Between subgroups variation |
Tracking Within subgroups variation |
|
|
Detect Special Cause Variation |
Represent Common Cause Variation |
|
|
|
|
|
|
|
|
|
|
|
|
Two Definition of Cpk
|
Product Capability = Total Process Variation, Cpk = [min (abs(USL-X_doublebar), abs(X_doublebar-LSL)] /
3 Sigmax Sigmax = Standard Deviation obtained from all 125 samples(from all 25 subgroups) |
|
Process Capability = Inherent Process Variation, Cpk = [min
(abs(USL-X_doublebar), abs(X_doublebar-LSL)] / 3 Sx Sx = Standard Deviation obtained from R_bar / d2 |
Selection of X_bar, R chart in stead of X_bar, S chart
SPC Implementation Plan and Q&A
Selection of Characteristic or Parameter for Plotting Control Chart
1. Must be Variable Data, if you want to use X_Bar, R Chart
2. Special Characteristics (defined by Customer or APQP team)
3. Tightest Tolerance Characteristics
How to formulate all population -> Histogram or Dot plot
-> sample -> Histogram or Dot plot
è Subgroup average -> X_bar, R chart
Variable V.S. Attribute data
Example of Terms used to describe and frequency in “Control Plan”
Comparison table for selection of proper sample size and sampling frequency
|
Sampling Patterns |
Units produced between interval of each sample in same subgroup (if not contiguous) |
Units produced within interval of each complete subgroup |
Units produced between interval of each complete subgroup |
Total time for all 25 subgroups |
Total units covering 25 subgroups |
|
2 pcs / 24 min |
|
|
|
|
|
|
5 pcs / hour |
|
|
|
|
|
|
10 pcs / 2 hours |
|
|
|
|
|
And other consideration such as :
Number of streams, cycles,
The term unit may be replaced by passing time in second or minute for bulk material.