Week 1 (11/04/05)
Day 1 Registration Day Briefing of Initial Study of Waja Day 2 Prelimenary Work on Waja's Body & Engine Specification (Standard) (Digitizing, Model and etc.) (Action: JKMP, FK, ITMA & AATL) Day 3 to 6 Brifing on Purchase of Item Documentation (FK forms) |
Week 2 (18/04/05)
Day 1 Initial Analysis for Conversion to Racing Vehicle Roller Cage Analysis (Action: Trainee) Day 2 One Day Road Tour to Sepang International Circuit (SIC) (Action:FK Transportation) |
Week 3 (25/04/05)
Day 1 Vehicle Assembly (Action: Trainee) Day 2 Vehicle Maintenance Practice Invited Mechanic (Action: En. Eris) |
Week 4 (02/05/05)
(If Car arrived) Perform Car Performance Testing (Standard) (Action:Akademi Sukan & Keselamatan) |
Week 5 (09/05/05)
Still Carry On Car Performance Testing Modification Analysis is splitted into 3 divisions: i) engine ii) structure iii) driver Finalise Quotation |
Week 6 (16/05/05)
Purchasement of Order (PO) will be issued |
Week 7 (23/05/05)
Doing of the Process of Modification |
Week 8 (30/05/05)
Full Complete Process of Modification |
Week 9 (06/06/05)
Further Modification |
Week 10 (13/06/05)
Run Test and Ready to Race |