Under the 20-year concession agreement , GSL Water had to undertake the following:-
GSL water invested RM 46 Million for the plant expansion, new Balancing Reservoirs , Elevated Tanks and pipelines which were all completed by 1993.Since then , we have continued our investment program for renewal of obsolete equipment and plant modernization. The total investment since inception stands at more than RM 52 million as of 1998 |
Expansion works in 1992 |
As part of our efforts to upgrade and modernize our operations, we implemented the following:-
Presently GSL Water produces approximately 110 MLD of drinking water for Lembaga Air Perak which is turn distributes to about 300,000 consumers in the districts of Kerian , Larut and Matang covering the principal towns of Taiping , Kamunting, Bagan Serai and its surrounding areas |
GSL Water has a total production capacity of 126 MLD; Treatment Plant capacity year commissioned Taiping Headworks 30 MLD early 1900's Gunung Semanggol - Plant # 1 12 MLD 1957 - Plant # 2 14 MLD 1962 - Plant # 3 20 MLD 1984 |
Taiping Headworks began producing water for Taiping town since the early 1900's and is believed to be the oldest water treatment plant in Perak. It continues to supply water to Taiping and sources it raw water from 5 mountain streams located 0.5 - 5.0 km away. Gunung Semanggol water treatment facilities were build in various stages and is now able to meet the growing demand well beyond year 2000. Its source of raw water is the 7,000 acres Bukit Merah Lake which mainly serves the irrigation needs to rice fields in the district of Kerian |