FAIRMOUNT LINE SERVICE UPGRADE STUDY
REQUEST FOR PLANNING PROPOSALS
Background:
The 9.1-mile Fairmount Branch Line, also known as the Midland or Dorchester Branch of the MBTA commuter rail network provides passenger service to some of the most densely populated neighborhoods of Boston. Earlier this century, the line included station stops at 11 locations between Hyde Park and downtown Boston. In 1944, service was discontinued and remained inactive until November 1979 when the MBTA restored passenger service. At that time, the Fairmount Branch track was upgraded as construction along the Southwest Corridor required rerouting of rail service. Responding to neighborhood demand, the MBTA maintained the Fairmount service with stations at Readville, Fairmount, Morton St. and Upham’s Corner after completion of the Southwest Corridor project in 1987.
Today, the MBTA operates commuter rail service with 22 inbound trains and 20 outbound trains daily Monday to Friday making local stops. The earliest train departs Readville for South Station at 6 A.M. and the last outbound train leaves South Station at 9:40 P.M. During rush hours, service operates at approximately 30 minute headways and off-peak at 60-minute headways. No service is provided on weekends. According to the MBTA train audit conducted in June 2000, the four Fairmount Line stations have combined daily boardings of 1,650 riders. These four stations are served by six MBTA bus routes. Commuter parking is available at the Readville and Morton Street stations.
The Red Line and Mattapan High Speed Line serve the area east of the Fairmount Line. MBTA bus routes 8, 10, 15, 16, 17, 19, 21, 22, 23, 24, 26, 28, 30, 31, 32 and 33 serve the neighborhoods through which the Fairmount Line runs. The Fairmount Line passes through several densely populated neighborhoods, some of which do not have direct transit access to downtown Boston.
The MBTA is committed to continuous improvements in its services and to that end is looking to investigate the feasibility of expanded use and more efficient operation of its Fairmount Line. Various proposals for expanded service have been raised by neighborhood groups and the MBTA Advisory Board. These include more frequent trains , opening of additional stations at Four Corners, Mattapan, Codman Square and South Bay, use of diesel multiple unit vehicles and establishment of a hybrid commuter rail/rapid transit line.
Proposals currently under consideration in development of the Boston area Regional Transportation Plan envision a phased approach to upgrading Fairmount Line transit service. Under the first phase, additional stations would be opened and level of commuter rail service increased with operation of more frequent trains over extended hours. The second phase envisioned is conversion of the commuter rail line to a rapid transit line using alternative vehicle technology.
The planning project detailed in this RFP will focus on analyzing the feasibility of implementing the first phase of the proposed Fairmount Line upgrade. Additional planning work for the second phase would be required to assess feasibility and costs/benefits for full implementation of Fairmount Line alternatives to commuter rail operation. Depending upon the results of the first phase, a separate RFP for second phase planning work may be issued.
Purpose:
The MBTA seeks consultant services to undertake feasibility analysis of expanded commuter rail service along the Fairmount Line. Factors to consider in the analysis of an increased level of service include but may not be limited to: ridership demand; compatibility with existing freight service, intercity service and commuter rail service; lack of space for additional trains at South Station and at Readville; condition of the Line’s bridges and track; inadequate state of signal systems; Federal Railroad Administration regulations and policy; mid-day and overnight layover requirements; and equipment maintenance capacity. Factors to consider in the analysis of potential additional station stops include, but may not be limited to: right-of-way availability, safety, accessibility requirements, cost, ridership demand and ridership impact. The analysis should identify both obstacles to be overcome, as well as benefits and opportunities. Potential benefits of project implementation envisioned are: expanded and improved service for residents of some of the region’s most transit dependent neighborhoods; travel-time savings; more efficient use of rail infrastructure; and relief of bus service overcrowding along the corridor.
Through this planning project, the consultant will work with the MBTA to analyze existing conditions and operations of the Fairmount Line, identify options for commuter rail service improvement, assess feasibility of those options and analyze impacts on ridership, service delivery, neighborhoods and MBTA operating and capital budgets.
Required Schedule of Work: A project start date of February 2001 is anticipated. The consultant’s scope of work as outlined in the Request for Proposals is to be completed no later than summer 2001.
Required Scope of Work: The required scope of work includes the following major work products in accordance with the work schedule outlined above:
Final Report: A final written report summarizing and synthesizing the findings, conclusions and recommendations presented in each of the three project tasks outlined above will be completed by the consultant and due 180 days after project start.
Input and Feedback Requirements: In addition to regular consultation and communication
with the MBTA, the consultant team will be required to work closely with a Project Steering Committee which will meet regularly during the course of the project to provide guidance to the consultant and MBTA project managers.
RFP Response Requirements: Respondents to this RFP should submit their written response within thirty days of its issuance. That response shall not exceed twenty double-sided pages of narrative, with up to an additional twenty pages of attachments or appendices, if and as required. The narrative response shall address itself to the following matters:
Additional Administrative Requirements:
Consultant proposals, in response to this request must be submitted to Dennis A. DiZoglio, Director of Planning, MBTA, 10 Park Plaza, Room 5750, Boston, MA 02116 no later than 4:00pm on Wednesday, January 10, 2001. The proposals will be limited to a maximum of 20 double sided pages narrative with up to 20 pages of attachments/appendices, 8 2@ x 11@ in size, which will include title sheet, index, all graphics, etc. Please be advised that the DBE, Child Care, Debarment and Lobbying Forms are not considered to be part of the twenty page technical proposal, and can be included as an attachment. Ten (10) copies must be submitted.
ACCEPTANCE OF TERMS AND CONDITIONS
Attached to this Request for Proposals are: Articles II, General Provisions, and Article III, Compensation and Payment, which will be incorporated into the proposed contract. Acceptance of these terms and conditions is a prerequisite to commencing negotiations with the firm selected. Final acceptance must be so indicated within your proposal.
EVALUATION
The written proposal, presentation, and response to questions raised during the interview will be evaluated by the Selection Committee membership based on the following criteria:
CRITERIA |
WEIGHT |
1. Quality and Responsiveness of Proposal |
25% |
2. Technical Approach |
25% |
3. Managerial Approach |
20% |
4. EEO Compliance |
Pass/Fail |
5. General Capabilities |
10% |
6. General Evaluation |
20% |
TOTAL |
100% |