ADVANCE
CORRECTION SLIP No. 96 dated. 22-07-2004
A new para 607(3) may be added of Indian Railway
Permanent Way Manual-1986 to read as under:-
Para 607(3) – The stability
of trains against derailment, depends upon several factors such as track geometry,
vehicle characteristics & state of their maintenance and speed of the
particular vehicle at relevant point of time etc. Rail wheel interaction is
thus, a complex phenomenon and therefore, safety tolerances for track alone
cannot be prescribed in isolation. With this in view, safety tolerances for
maintenance of track, have not been prescribed on Indian Railways. Each
derailment case, therefore, needs careful examination of all available
evidence, in respect of Track, Rolling Stock, speed and other factors
considered relevant, to arrive at the cause.
The provision and tolerances
mentioned in Para 607(2) and elsewhere in this Manual are with a view to
maintain track geometry for good riding comfort.
ADVANCE
CORRECTION SLIP No. 95 dated. 30-06-2004
The existing para 826 (i) of Indian Railways Permanent
Way Manual may be modified to read as under:-
826 (i) – The contractor shall not start any work without the presence of
railway supervisor or his representative and contractors supervisor at site.
A new para 826 (vii) may be
added to Indian Railway Permanent Way Manual as under :-
826 (vii)
– The Engineer in charge shall approve the methodology proposed to be adopted
by the contractor, with a view to ensure safety of trains, passengers and workers
and he shall also ensure that the methods and arrangements are actually
available at site before start of the work and the contractor’s supervisors and
the workers have clearly understood the safety aspects and requirements to be
adopted/followed while executing the work.
There
shall be an assurance register kept at each site, which will have to be signed
by both, i.e. Railway Supervisor or his representative as well as the
contractor’s supervisor as a token of their having understood the safety precautions
to be observed at site.
ADVANCE
CORRECTION SLIP No. 94 dated. 01-06-2004
The existing para 410 (3) and 410 (4) of Indian Railway
Permanent Way Manual may be modified to read as under:-
410(3) Speed over interlocked turnouts- Speed in excess of 15 kmph may be permitted for straights of interlocked
turnouts only under approved special instructions in terms of GR 4.10.
In the case of 1 in 8.5, 1
in 12 and flatter turnouts provided with curved switches, higher speeds as
permitted under approved special instructions may be allowed on the turnout
side, provided the turn-in curve is of a standard suitable for such higher
speeds. While permitting speed beyond 15 kmph, provisions of Para 410 (4) may
be kept in view.
The permissible speed on
turnouts taking off on the inside of the curve should be determined by taking
into consideration the resultant radius of lead curve which will be sharper
than the lead curve for turn outs taking off from the straight. 1 in 8.5
turnouts should not be laid on inside of curves.
410 (4) Upgradation of speeds on Turnouts and Loops to 30 kmph
(a)
(a)
Length of Section - Upgradation of
speeds on turnout should cover a number of contiguous stations at a time so as
to derive a perceptible advantage of the higher speed in train operation. The
works described below, should cover all the running loops on the stretch of
line taken up.
(i)
(i)
Turnouts – Speed, in excess of 15 kmph, should be permitted on
turnouts laid with ST or PRC sleepers only. All turnouts on the running loops
shall be laid with curved switches, with minimum rail section being 52 Kg. All
rail joints on these turnouts should also be welded to the extent possible.
For different type of curved switches permissible speed
are as under:-
S.No. Type
of Turnout (BG) Permissible
speed
1. 1 in 8.5 curved
switch 15 kmph
2. 1 in 8.5 symmetrical 30 kmph
split with curved
switches
3. 1 in 12 curved
switch 30 kmph
(ii)
(ii)
Track on running loop – Speed in excess of 15 kmph, should not be permitted on
running loops laid with wooden sleepers. The minimum track structure on the
running loop should be 90R rails laid as Short Welded Panels, M+4 density on
PRC, ST, CST-9 sleepers and 150 mm ballast cushion. Out of 150 mm total
cushion, clean cushion of 75 mm at least should be available. Proper drainage
of the area should also be ensured.
(iii)
(iii)
Turn-in-curves – Speed in excess of 15 kmph, should not be
permitted on Turn-in curves laid with wooden sleepers. Turn-in-curves should be
laid with the same rail section as on the turn-out with PRC, ST or CST-9
sleepers with sleeper spacing being 65 cm centre to centre (maximum).
Turn-in curve should conform to Para 410 (2) of IRPWM and
especially so in respect of curvature of the lead curve.
Extra shoulder ballast of
150 mm should be provided on outside of the turn-in curve.
The frequency of inspection
of turn-in curves should be same as that for main line turn-outs.
(b)
(b)
The following should be ensured, if
CST-9 sleepers are used in running loops or turn in curves:-
(i)
(i)
There is no cracks or fracture at
rail seat in two consecutive sleepers.
(ii)
(ii)
There is no excessive wear of lug and
rail seat.
(iii)
(iii)
All the fittings keys, cotters and
tie bars are fitted properly. Rail is held firmly with sleepers.
(iv)
(iv)
Tie bars should not be broken or
damaged by falling brake gear, wagon parts etc. and they should not have
excessive corrosion or elongated holes. The corrosion of tie-bars inside the
CST-9 plate should be especially checked as this results in their removal and
adjustment becoming difficult.
(c)
(c)
The following should be ensured, if
ST Sleepers are used in Turnouts, Turn-in curves or running loops:-
(i)
(i)
There is no crack or fracture at rail
seat in two consecutive sleepers.
(ii)
(ii)
There is no excessive wear of lug,
MLJ and rail seat.
(iii)
(iii)
All the fittings are effective and
rail is held with sleepers properly.
(iv)
(iv)
The sleepers and fittings do not have
excessive corrosion, elongated holes etc.
ADVANCE CORRECTION
SLIP No. 93 dated. 05-03-2004
The following correction may be made in advance
correction slip nos. 32, 44 & 70 issued from Board to IRPWM – 1986:
Corrigendum to advance correction slip No. 32
dated. 04-08-1999:-
The existing para 320 (3) (5)
Annexure 3/1 and para 320 (3) (8) Annexure 3/2 to be renumbered as Annexure 3/2
and 3/3 in place of Annexure 3/1 and 3/2 respectively.
Corrigendum to advance correction slip No. 44
dated. 10-02-2000:-
The
first line of advance correction slip No.44 – The existing para 919 be replaced
with following should be replaced with “the existing para 919 (1) be replaced
with the following” respectively.
Corrigendum to advance correction slip No. 70
dated. 24-05-2001:-
The
existing Note (1) Annexure –DTM/1 regarding “scattered renewals, creep adjustments
and earth work repairs should be done as necessary” is deleted.
ADVANCE CORRECTION SLIP No. 92 Dated. 04.02.2004
The existing para 302 (1)
(e) may be renumbered as para 302 (1) (f) para-302 (1) (e) be read as under :-
Para-302 (1) (e) – The service life in terms of total GMT of traffic carried for
considering through rail renewal on the bridge proper and in approaches (upto
100 m on either side) for all the important bridges and such of the major
bridges where height of bank is in excess of 4.0 m, all tunnels and their
approaches (upto 100 m on either side) shall be half of the GMT specified in
para 302 (1) (d) above.
The released P.Way material
shall be dealt with in accordance with para 320 of IRPWM.
ADVANCE CORRECTION SLIP No. 91 Dated.
20.01.2004
The
existing contents of para 252 (3) along with annexure 2/9 of Indian Railway
Permanent Way Manual, 1986 may be deleted and substituted with the following:
Para 252 (3) – “ Ultrasonic testing of rails is
specialized activity and the inspectors carrying out the ultrasonic testing of
rails shall be trained by RDSO, in the technique of USFD testing. Each zonal
railway shall create adequate number of ex-cadre posts of inspectors to ensure
that entire track length in their jurisdiction is ultrasonically tested at the
laid down periodicity.
Detailed
instruction for ultrasonic testing of rails and welds are contained in the
Manual for Ultrasonic Testing of Rails and Welds, August, 1998, which along
with its correction slips may be referred to as Annexure to this Manual. It is
very important that instructions contained therein are carefully studied by the
Permanent Way Officials connected with the laying and maintenance of track”.
ADVANCE CORRECTION SLIP No. 90 Dated.
23.12.2003
The existing para 421 of Indian Railway Permanent Way
Manual may be modified to read as under:
Para 421 – Criteria for realignment
of a curve:
(1)
(1)
When as a result of inspection by
trolley or from the foot plate of locomotive or by carriage or as a result of
Track Recording carried out, the running on a curve is found to be
unsatisfactory the curve should be realigned.
(2)
(2)
The running over a curve depends not
only on the difference between the actual versine and the designed versine but
also on the station-to station variation of the actual versine value. This is
because it is the station to station variation of versine which determines the
rate of change of lateral acceleration, on which depends the riding comfort.
Service limit for station to station versine variation
for 3 speed group viz. 120 Km/h and above, below 120 Km/h and below 80 Km/h and
upto 50 Km/h, should be considered as tabulated below:
Speed Range |
Limits of station to station Variation (mm) |
120 Kmph and above |
10 mm or 25% of the average versine on circular curve
whichever is more. |
Below 120 Kmph and upto 80 Kmph. |
15 mm or 25% of the average versine on circular curve
whichever is more. |
Below 80 Kmph and upto 50 Kmph. |
40 mm or 25% of the average versine on circular curve
whichever is more. |
In case
exceeding of the above limit is observed during an inspection, local
adjustments may be resorted to in cases where the variation of versine between
adjacent stations is only at few isolated locations, at the earliest possible.
If more than 20% of the stations are having versine variation above the limits
prescribed, complete realignment of the curve should be planned within a month.
ADVANCE CORRECTION
SLIP No. 89, dated: 19-09-2003
The existing para 211(1) (v) of Indian
Railways Permanent Way Manual may be modified to read as under:
Para 211(1) (v) – The permanent way track diagram of the railway
line showing the type of track and fittings when laid, type of ballast, type of
formation with classification of soil (to be carried out as per RDSO’s Circular
No. GE-P1 – May 2003), blanket thickness, type of formation trouble (if any)
and indication of how the railway boundary is demarcated. Change points in the
track diagram shall be indicated correct to the nearest meter (details as in
annexure 2/4 (Revised)).
ADVANCE CORRECTION SLIP No. 88 Dated.
15.09.2003
The existing para 250 (2)
(a) of Indian Railways Permanent Way Manual may be modified to read as under:
250 Rail maintenance to Reduce Rail Deterioration
(2) Prevention of corrosion (anti corrosive measures) – (a) Anti corrosive
painting
i) Anti-corrosive painting of rails should be carried out in locations
which are prone to corrosion.
ii) While carrying out renewals in these areas, anti-corrosive treatment
should be given before the rails are laid in the track. The rust is removed and scales are loosened
by wire brushing/scraping. Thereafter
rails are painted with –
One coat of red oxide zinc chromate primer to IS:2074.
Two coats of Bituminous Emulsion to IRS-P-30-1996 to a dry film thickness
of 350 microns (each coat to a minimum thickness of 175 microns).
iii) In the case of rails that are already laid in track and subject to
corrosion the rails should be given the treatment in the track itself. The rust and scales are first removed by wire
brushes and thereafter painted with –
One coat of red oxide zinc chromate primer to IS:2074.
Two coats of Bituminous Emulsion to IRS-P-30-1996 to a
dry film thickness of 350 microns (each coat to a minimum thickness of 175
microns).
ADVANCE CORRECTION SLIP No. 87 Dated.
25.07.2003
The
existing para 170 (6) of Indian Railway Permanent Way Manual may be replaced as
under:
170 (6) (a) - Where the beat
of a keyman consists of PRC sleeper- The Keyman should ensure that, in addition
to his normal duty of inspection and tightening of fitting, he should also
carry out in a systematic manner from one end, greasing of the ERC and eyes of
inserts at the rate of 20 sleepers per day. Greasing shall be done as per the
procedure laid down in para 1411 (5) (b) of IRPWM.
170 (6) (b) – Where the beat of a keyman consists of PRC as well as
other types of sleepers, SE(P.Way) should make roster of keyman on monthly
basis in the proportion of the beat, so that work mentioned in para 170(5) and
170 (6) (a) are completed in respective length. On any particular day however,
he will do duties either as per 170 (5) or 170 (6) (a) only.
ADVANCE CORRECTION SLIP No. 86 Dated.
07.07.2003
The existing para 507 (1) of Indian Railways Permanent
Way Manual may be modified to read as under:
Para 507 Condition
of laying: (1) Alignment – SWR shall
not be laid oncurves sharper that 500 metres radius in both Board Gauge and
Metre Gauge. However, on PSC Sleepers,
SWR may be laid on curves with radius not less than 440 meters.
Existing SWR laid on sharper curves may, however, be
allowed to continue if there is no difficulty experienced in maintaining these
lengths. Chief Engineer’s approval should
be taken in such cases.
ADVANCE CORRECTION SLIP No. 85 Dated.
13.05.2003
The existing para 256 (1) of Indian Railway Permanent Way Manual may be
replaced as under:
(1) (a) Permanent
closure in running lines should not be less than 5.5 metre in length. However, for locations such as 500 metre
length on both side approaches of tunnels, tunnel proper, major and important
bridges including bridge proper, deep cutting and high embankments, the
stipulations of para 1 (b) below shall apply.
(1) (b) Permanent
closure in running lines, on locations specified in para 1 (a) above, should
not be less than 11 metre in length, between two adjoining fish plates.
The
closure rails existing in track which are less than 11 metre, should be welded
at least of 11 metre between two adjoining fish plated joints. Till such time this welding is done and the
length of at least 11 metre is achieved, speed restriction of 30 kmph shall be
imposed.
ADVANCE CORRECTION SLIP No. 84 Dated.
08.05.2003
The existing para
170(6) of Indian Railways Permanent Way Manual may be replaced as under:
170 (6) (a) - Where
the beat of keyman does not consist of PRC sleepers – The Keyman should ensure
that, in addition to his normal duty of inspection and tightening of fittings,
he proceeds in at least 3 T.P.lengths are made perfect every day, with a view
to complete the beat in a month.
170 (6) (b) - Where the beat of a keyman consists of PRC sleepers – The Keyman
should ensure that, in addition to his normal duty of inspection and tightening
of fittings, he should also carry out in a sysmatic manner from one end,
greasing of the ERC and eyes of inserts at the rate of 20 sleepers per
day. Greasing shall be done as per the
procedure laid down in para 1411 (5) (b) of IRPWM.
170 (6) (c) - Where the beat of a Keyman consists of PRC as well other types of
sleepers, the work at (a) and (b) above, shall be done in respective lengths.
Existing para 1411 (5) (b) may be
replaced as under:
(b) Lubrication
of ERCs – Grease Graphite to the specification IS-408-1981 Gr. O should be used
for this purpose. This work should not
be carried out during extreme of summer and heavy rainfall. At a time ERCs should not be removed from
more than one sleeper. If for any
reasons mass lubrication of ERCs is taken up, at least 15 sleepers shall be
kept intact between any two sleepers taken up for lubrication of ERCs at the
same time. The ERCs should be cleaned by
wire brush and emery paper. The eye of
the insert shall also be cleaned by suitable brush. After cleaning, grease graphite shall be
applied to the inside surface of eye of insert and leg of ERC. Inside/Outside ERCs should be interchanged
and fixed again.
A new para 1411 (5) (c) be added to
read as under:
(c) The
lubrication of ERCs and insert at the time of intial laying should be done 100%
and thereafter should be done once in a year in corrosion prone areas &
platform lines and once in two years on other areas.
ADVANCE CORRECTION SLIP No. 83 Dated. 25.2.2003
The
existing para 606 of Indian Railways Permanent Way Manual be modified to read
as under:
606. Frequency of Track Recording - Track
geometry monitoring of Metre Gauge routes is not to be done by track recording
car. The Board Gauge routes should be
monitored by TRC as per the following frequencies (except for the routes where
track recording is to be dispensed with) :-
i) Routes with existing
speeds above 130 kmph - Once in 2
months
ii) Routes
with existing speed above 110 kmph and-
Once in 3 months
upto 130 kmph.
iii) Other Group ‘A’ and ‘B’
routes - Once in 4 months
iv) Group ‘C’, ‘D’ and ‘D
spl.’ Routes - Once in 6
months
v) Group ‘E’ and ‘E spl’
routes - Once in 12
months
ADVANCE CORRECTION SLIP NO.
82 Dated 10.02.2003
The
existing para 1122 (4) (iii) of Indian Railway Permanent Way Manual be modified
to read as under:
(iii) – The rail dolley shall be protected by a flagman
at a distance of 1200 metre on Board Gauge and 800 metre on MG/NG from the rail
dolley, on a double line in the direction on single line. The flagmen shall also carry three detonators
for use in any emergency.
ADVANCE CORRECTION SLIP No. 81 Dated.
03.12.2002
The
existing para 914(b) (v) of Indian Railway Permanent Way Manual be modified to
read as under:
(v) – Check rails of lavel crossing are required to be
removed for tamping operations, overhauling of level crossing, distressing of
LWR or track renewals etc. Check rails
should be refixed as quickly as possible and preferably before leaving site.
Should a
situation arise where check rails cannot be refixed for any reason and trains
have to be passed, a speed restriction of 30 kmph should be imposed besides
ensuring that road traffic is diverted till the check rails are put in
place. In case such diversion is not
possible, temporary arrangements should be made for passage of road traffic
till the check rails are put in place.
However, in both these cases, the check rails should necessarily be
provided latest by close of next day. In
such cases, a stationary watchman shall be posted to ensure safety.
ADVANCE CORRECTION SLIP No. 80 Dated.
02.12.2002
New para
may be inserted as 264(4) and 264(5) of the IRPWM – 1986 as mentioned below:
Para 264 (4) – In new line construction, ballast
requirements will be assessed as per the profile (to be adopted) given in para
263(I).
Para 264 (5) – The quantities assessed vide sub-para in
(2), (3) and (4) above will be the net quantities of ballast required to recoup
the deficiencies or to provide required profile/section. The above net quantities may be enhanced
suitably (say 8%) to arrive at gross quantities of ballast for the purpose of
procurement action in case measurements are proposed to be taken in stacks or
in wagons at originating station.
ADVANCE CORRECTION SLIP No. 79 Dated.
10.10.2002
The following may be replaced in suppression of Advance
Correction Slip No. 71 dated. 17.7.2002 Para 283 (2) (c) of IRPWM – 1986 to
read as under:-
(c) “No part
of the tree shall be nearer than 4 mts from the nearest live conductor. Any tree or branches likely to fall on the
live conductor should be cut or trimmed periodically to maintain the safety
clearances. The responsibility for
wholesale cutting of the trees, i.e. cutting of tree trunks, will rest with the
Engineering Department. In the
electrified territories, however, the cutting of the trees shall be done by the
Engineering Department in the presence of authorized TrD staff to ensure safety
and satisfactory completion of the work.
The day-to-day trimming of the tree branches, wherever required, to
maintain the 4 m safety clearances from OHE shall be done by the authorized TrD
staff and Supervisors.
In case of dispute,
the decision whether to cut or trim a tree, shall be taken through a joint
inspection of Engineering and Electrical officials.
The modalities to be adopted for cutting/trimming of the
trees i.e. contractually or departmentally, may be decided by the respective
departments basedon local conditions.
Accountal and disposal of treescut wholesale will be done by the Engg.
Deptt. while the disposal of the trimmed tree branches will be the
responsibility of the TrD Department.
The expenditure for cutting/trimming of trees to maintain safe clearance
for OHE, shall be debited to revenue grant of TrD Department.”
ADVANCE CORRECTION SLIP No. 78 Dated.
09.09.2002
The para 1408 (1) (c) of the Advance Correction Slip No. 67 dated
24.04.2001 of Indian Railway Permanent Way Manual – 1986, be substituted as
under:
1408
(1) (c) For spot attention/ slack
picking, multi-purpose Tampers and Off-track Tampers shall be used as a regular
measure on Concrete Sleeper Track, in the following areas of application:
(i) Picking
up slacks in isolated stretches.
(ii) Points and
Crossings area,
(iii) Approaches to
bridges and level crossings,
(iv) Buffer rail
joints/switch expansion joints in LWR section.
(v) Block
insulated joints/glued joints in track-circuited stretches.
For Off-track tampers, the
working instructions, issued by Railway Board/ RDSO as amended from time to
time, should be followed.
As an interim measure, where
Off-track tampers are not available, the packing may be done with the help of
Crow bar/Beater, duly taking care that the concrete sleepers are not damaged.
ADVANCE CORRECTION SLIP No. 77 Dated.
12.08.2002
The para 248(2) (a) be replaced
with the following :-
(a) Broad
Gauge :- The following minimum rail
sections are recommended based on the speeds obtainable and the traffic
condition :-
Routes |
||||||||
Traffic desnsity in GMT |
A |
B |
C |
D.Spl. |
D |
E.Spl. |
E |
|
More than 20 |
60 Kg. |
60 Kg. |
60 kg. |
60 kg. |
60 Kg. |
60 Kg. |
60 Kg. |
|
10-20 |
60 Kg. |
60 Kg. |
60 Kg. |
60 Kg. |
52/90 |
60 Kg. |
52/90 |
|
5-10 |
60 Kg. |
52/90 |
52/90 |
52/90 |
52/90 |
52/90 |
52/90 |
|
Under 5 |
52/90 |
52/90 |
52/90 |
52/90 or 60 kg. (SH) |
52/90 or 60 Kg. (SH) |
52/90 or 60 Kg. (SH) |
*52/90 (SH) or 60 Kg. (SH) |
|
Loop line |
52 Kg. IRS-T-12 second quality rails or 52 kg.(SH) |
|||||||
Pvt.Siding |
For sidings with operating speed more than 80 kmph and upto 100 Kmph |
Track structure specified for D route. |
||||||
For sidings with operating speed more than 50 Kmph and upto 80 Kmph. |
Track structure specified for E route. |
|||||||
Where BOX’N’ or 22:1 Tonne axle wagon ply or operating speeds on sidings
exceed 30 and are going upto 50 Kmph. |
52 kg. IRS-T-12 Second quality rails or 52 kg.(SH) |
|||||||
For other sidings with operating speed upto 30 Kmph. |
52 kg. IRS-T-12 third quality rails also called ‘Industrial use rails’ or
52 kg. (SH) |
|||||||
|
|
|
|
|
|
|
|
|
Note :- 52/90 represents 52 kg/90 UTS rail section.
(i) Existing 90 R rails may be allowed to remain for speeds not
exceeding 110 Kmph.
(ii) On routes identified for running of 22.1 Tonne axle load
wagons, 60 kg. Rails shall be used on all routes.
(iii) Head hardened rails should be used on (a) Local lines where
dedicated EMU stock is running. (b) Ghat section with gradients steeper than 1
in 150 and/or curves sharper than 2 degree, (c) Locations where due to grades,
curves, traffic density and type of stock, the rate of wear of rails is such as
to necessitate rail renewal, on wear considerations, at a frequency of 10 years
or so. (d) Routes where predominantly captive rolling stock is moving in close
circuit movement, particularly with heavy mineral traffic. (e) The HH rails
should be laid on continuous and long stretches.
(iv) *Second hand 52 kg. Rails may be used on case-to-case basis,
with the prior approval of Railway Board, depending upon quality of released
rails available.
The
existing para – 322 of Indian Railways Permanent Way Manual be replaced to read
as under :-
322.
Identification of different qualities or rails in the Field –
(1) First Quality Rails (T-12) – Indian Railways specification
IRS-T-12/96 gives the detailed specification of Flat Bottom Rails 60 kg. And 52
kg. Of grade 880 Mpa, 1000 Mpa and 1080
Mpa. 52 kg./m and 60 kg./m rails shall be classified as Class ‘A’ and Class ‘B’
rails based on tolerance in End straightness. The rails shall have rolled on
it, the rail section, the Grade of steel, identification marks of the
manufacturer, month and last two digits of the year of the manufacture, process
of steel making and direction of rolling of rail.
(2) Second Quality Rails – These are rails with relaxation in
sectional tolerance as provided in Amendment to IRS-T-12/96 but other wise
conforming to T-12/96 in all other respects. The identification of such rails
will be one hole of 6 mm dia, champhered at both ends, drilled at the center
length of the rail and at the moddle of the web. These rails shall be used only
on loop lines/sidings with speed restriction of 50 Kmph. These rails shall be
painted with orange colour on both sides of the web for a distance of 1 metre
from each end, for easy identification.
(3) Third Quality Rails – In addition to above two qualities, third
quality rails supplied by Steel Plants are arising, particularly during the
inspection of rails while producing first quality rails as per IRS-T-12
specification. There is no deviation in chemical composition or mechanical
property in ‘Industrial Use’ rails from that of IRS-T-12. The deviations exist
only in tolerance in surface defects, dimensions and straightness. These can be
used in industrial sidings where speeds are limited to 30 kmph in B.G. and 25
kmph in M.G.
The
identification of such rails will be one hole of 12 m dia., champhered at both
ends, drilled at the center length of the rail and at the middle of the web. A
marking ‘I.U’ in 18 mm, size shall be stamped on both end faces of rail. The
third quality rail shall be painted with white paint on end face of the flange
and on both sides of flange for a distance of 500 mm, from each end for
identification.
ADVANCE CORRECTION SLIP No. 76 Dated.
26.11.2001
The existing para 410 (3) of
Indian Railways Permanent Way Mannual may be modified to read as under:
(3) Speed over Interlocked turn-outs – (a) Speed in
excess of 15 kmph may be permitted for straights of interlocked turnouts only
under approved special instructions in terms of GR. 4.10/1976.
(b) In the case of 1 in 8-1/2, 1
in 12 and flatter turnouts provided with curved switches, higher speed as
permitted under approved special instructions may be allowed on the turnout
side, provided the turn-in curve is of a standard suitable for such higher
speeds. Extra shoulder width of ballast of 150 mm should be provided on the
outside of such turn-in curves. When these conditions are satisfied, the speeds
indicated below may be permitted on turnouts provided with curved switches.
While permitting speed beyond 15 kmph, provisions of para 410 (4) may also be
kept in view.
S.No. |
Type of Turnout (B.G.) |
Permissible Speed |
1 |
1:8.5 curved switch
52/60 Kg. on PSC sleepers |
15 kmph |
|
|
|
2 |
1:8.5 symmetrical split
with curved switches 52/60 Kg on PSC sleeper. |
30 kmph |
|
|
|
3 |
1:12 curved switch
52/60 Kg on PSC sleepers. |
30 kmph |
(c) the permissible speed on
turn-outs taking off on the inside of the curve should be determined by taking
into consideration the resultant radius of load curve which will be shaper than
the lead curve for turn outs taking off from the straight. 1 in 8-1/2 turn-outs
should not be laid on inside of curves.
A new para 410 (4) be added to read
as under:-
410 (4) Upgradation of speeds on turn-outs should cover a number of contiguous stations
at a time. Before upgrading the speeds on Turn-out beyond 15 km/hr, the track
structure of loop lines should be strengthened as prescribed.
ADVANCE CORRECTION SLIP No. 75 Dated.
05.03.2001
The first line of para 913 (a)
and (b) of IRPWM – 1986 together with Annexure-9/3 to para 913 (3) be replaced
with the following:
913(a) On double line, if both the lines are
obstructed during the day, he shall plant a red banner flag at a distance of 5
metres from the end of check rails on the line on which a train is expected to
arrive first, then plant another red banner flag on the other side at the site of obstruction.
913 (b)
On single line, if the line is obstructed during day, he shall plant a
red banner flag at a distance of 5 metres from the end of check rails, towards
the direction from which a train is expected to arrive first, then plant
another banner flag towards the opposite direction at the site of obstruction.
ADVANCE CORRECTION SLIP No. 74 Dated.
26.11.2001
The existing para –277 of Indian
Railways Permanent Way Manual be replaced to read as under :-
a) For all Bridges: (1) On
the bridge approaches, sleepers with arrangement for fixing guard rails should
be provided for provision of guard rails as per para 275 above.
2) Full complement of track
fittings at bridge approaches up to 100 metres should be provided to maintain
required track geometry and effort should be made to immediately recoup
deficiency noticed, if any.
3) Rail level of track in approaches of bridges should be
maintained, as per provision of IRPWM –
1986 under respective para and dips in rail level immediately after abutments
should be avoided. The alignment and super elevation in case of curved track
should also be maintained as per
provisions of IRPWM – 1986 under respective para.
4) Rail joints should
be avoided within three metres of a bridge abutment.
5) In case of LWR
track, full ballast section as specified in LWR Manual should be provided up to
100 metres from the abutment.
6) Switch expansion
joints should be provided at the bridge approaches in LWR/CWR track as per
provisions of LWR manual.
b) For important and
major bridges :- In addition to para (a) above, following should also be
provided.
1) In case of CST-9
or wooden sleeper track, concrete/steel through sleepers with elastic
fastenings should be provided up to 100m/upto full breathing length wherever
LWR is provided in approach of bridge.
2) On the bridge approaches, for a
length of abut 100 metres, width of cess should be 90 cm. Clear of full ballast
section to maintain ballast profile. For maintaining ballast section, suitable
ballast retaining arrangement should also be provided.
ADVANCE CORRECTION SLIP No. 73 Dated.
02.11.2001
The
existing para – 170 (6) of Indian Railways Permanent Way Manual may be modified
to read as under :-
(6)
Where the beat of a Keyman consists of PRC sleepers, apart from his round of
the beat, the keyman should also carry out in a systematic manner from one end
greasing of the ERC and eyes of inserts at the rate of 20 sleepers per day.
Greasing shall be done as per the procedures laid down in para 1411 (5) (b) of
IRPWM.
ADVANCE CORRECTION SLIP No. 72 Dated.
07.08.2001
The existing para -1411 (5) (b) of Indian Railways
Permanent Way Manual be replaced to read as under :-
(b) In Service
maintenance : Lubrication of
ERCs in track should normally be carried out by keyman in a systematic
manner from one end to other at the rate of 20 sleepers (80 ERC) per day. This
work should not be carried out during extreme of summer and heavy rainfall.
Grease graphite to the specification IS-408-1981 Gr. O should be used for this
purpose. At a time, keyman should not remove ERCs on more than one sleeper. If
for any reason mass lubrication of ERCs is taken up then between any two
sleepers taken up for lubrication of ERCs at the same time, at least 15
sleepers shall be kept intact. The ERCs should be cleaned by wire brush and
emery paper. The eye of the insert shall also be cleaned by suitable brush.
After cleaning, grease graphite shall be applied to the inside surface of eye
of insert and leg of ERC. Inside/Outside ERCs should be interchanged and fixed
again. The lubrication of ERCs and inserts at the time of initial laying should
preferably be done in base depot and thereafter should be done once in a year
in corrosion prone areas and platform lines and once in two years in other
areas.
ADVANCE CORRECTION SLIP No. 71 Dated.
17.07.2001
The existing para – 283(2) (C ) of Indian Railways Permanent Way Manual
be replaced with the following :-
( C ) No part of a
tree shall be nearer than 4 metres from the nearest live conductor. Any tree or
branches likely to fall on live conductors should be cut or trimmed
periodically to maintain this clearance. Cutting or trimming should be done by
authorized O.H.E staff.
ADVANCE CORRECTION SLIP No. 70 Dated. 24.05.2001
Note (1) to para 204 be modified to
read as under :-
Scattered renewals, creep adjustments and earth work repairs should be done
as necessary.
Para 245 (e) be
modified to read as under :
(e)
While doing casual/scattered renewals, priority should be given in
replacing unserviceable joint sleepers and unserviceable consecutive
sleepers. Through sleeper renewals
should be carried out in continuous stretches and released sleepers after
reconditioning should be used for scattered renewals. New sleepers should not be used in
sidings. If the percentage of unserviceable sleepers becomes high, speed
restrictions may have to be imposed.
The following be added to para 301(1):
(8) Scattered Renewal
The existing
sub-para 301(3) be renumbered as 301(4) and modified to read as under :
(4) Casual Renewal : In this case, unserviceable rails, sleepers and fastenings are replaced by
identical sections of serviceable and nearly the same vintage or new track
components. These are carried out in
isolated locations of continuous but small stretches. Such renewals are not a part of normal
maintenance operations and cannot be covered under scattered renewals.
A new para 301(3) be added to read as under :
(3) Scattered Renewal : In this case, unserviceable rails, sleepers and fastening are replaced by
identical sections of serviceable and nearly the same vintage track
components. These are carried out in
isolated locations and not more than 10 rails and/or 250 sleepers in a gang
beat in a year. Such renewals are a part
of normal maintenance operations.
Note (I) Annexure – DTM/I be modified to read as under
:
Scattered
renewals, creep adjustments and earth work repairs should be done as
necessary.
The following line
be added as end of the existing para – 252 (2) of IRPWM – 1986 :-
Such an inspection on the important girder bridges and
their approaches should be done twice a year.
ADVANCE CORRECTION SLIP No. 69 Dated. 23.05.2001
A new para
no.826 be added to Chapter-VIII of the IRPWM, 1986 to read as under :
826 Safe working
of contractors - A large number of men
and machinery are deployed by the contractors for track renewals, gauge
conversions doublings, bridge rebuilding etc.
It is therefore essential that adequate safety measures are taken for
safety of the trains as well as the work force.
The following measures should invariably be adopted :
(i) |
The contractor shall not start any
work with the presence of railway supervisor at site. |
(ii) |
Wherever the road vehicles and/or
machinery are required to work in the close vicinity of railway line, the
work shall be so carried out that there is not infringement to the railway’s
schedule of dimensions. For this
purpose the area where road vehicles and/or machinery are required to ply,
shall be demarcated and acknowledged by the contractor. Special care shall be taken for
turning/reversal of road vehicles/machinery without infringing the running
track. Barricading shall be provided
wherever justified and feasible as per site conditions. |
(iii) |
The look out and whistle caution
orders shall be issued to the trains and speed restrictions imposed where
considered necessary. Suitable
flagmen/detonators shall be provided where necessary for protection of
trains. |
(iv) |
The supervisor/workmen should be
counseled about safety measures. A
competency certificate to the contractor’s supervisor as per proforma annexed
shall be issued by AEN which will be valid only for the work for which it has
been issued. |
(v) |
The unloaded
ballast/rails/sleepers/other P.Way materials after unloading along track
should be kept clear off moving dimensions and stacked as per the specified
heights and distance from the running track. |
(vi) |
Supplementary site specific
instructions, wherever considered necessary shall be issued by the Engineer
in Charge. |
Competency Certificate
Certified that Shri __________________________________P.way
supervisor of M/s._________________________________has been examined regarding
P.Way working on __________________________work. His knowledge has been found satisfactory and
he is capable of supervising the work safety.
Assistant Engineer
ADVANCE CORRECTION SLIP No. 68 Dated. 25.04.2001
The Annexure 2/3 to para 206 of IRPWM be replaced with the Annexure 2/3
enclosed.
The new
paras as indicated below be added to the existing para 206 of IRPWM – 1986 :-
(4) Maintenance attention given to the signaled loop
lines and turnouts should be recorded on the chart.
(5) Whenever the gang equipments are checked by
PWIs, the same should be recorded in gang chart against the date on which such
inspection is done. Inspecting officials
should initial against the date on the chart and also made suitable entries in
gang diary.
(4) Six months after the end of each year, the gang
charts will be collected by the PWIs and maintained as record. Thus, for the overlapping period of six
months, the gang will have two gang charts with them. A six months record will therefore always be
available with the gang for reference.
Normally, this record should be kept for at least five years. When a particular kilometer or section is
under special observation, the record may be maintained for a longer period at
the discretion of P.Way officials.
Annex 2/3 to para 206
ADVANCE CORRECTION SLIP No. 67 Dated. 24.04.2001
The para 1408 of Chapter XIV
of IRPWM be deleted and substituted with a new para 1408 as under :-
1408 Maintenance of concrete sleeper track :
(1)
General
(a) Concrete sleeper
track should be maintained by heavy on-duty track tampers.
(b) An annual machine deployment
programme shall be drawn by zonal railway and be circulated to the divisions
before the beginning of the year.
(c) For spot attention/slack picking,
multi-purpose tampers and off-track tampers shall be used. Where off-track tampers are not available, as
an interim measure, the packing may be done with the help of crow bar/beater
duly taking care that the concrete sleepers are not damaged.
(d)
Pre-tamping, during tamping and
post-tamping attentions should be given to track as indicated in para 226. (For further details, Chapter 3 of Indian
Railways Track Machine Manual may be referred to ).
(2) Annual Systematic
Attention on PRC track
In addition
to machine tamping, the gangs will carry out annual systematic attention to
track from one end of gang beat to the
other during work season. This will
include –
(a) Examination of rails, sleepers and
fastenings including measurement of
toe load of ERCs.
(b) Inspection of and attention to insulated joints,
switch expansion joints etc.
(c) Packing of approaches of bridges, level crossings,
breathing lengths of LWRs and bad formation areas etc.
(d) Shallow
screening of track ..
(e)
Through packing of track not maintained by machine, e.g. tracks not on PSC
sleepers including all running lines of the yards and pints and crossings in
such running lines.
(f)
Minor repairs to cess of bank.
(g)
Boxing and dressing of ballast.
(h)
Replacement of damage/missing rubber pads, liners and ERCs.
(3) Annual
Programme of maintenance of PRC track
The annual
maintenance programme for machine maintained concrete sleeper track would be as
under :-
Period |
Work |
(a) Post monsoon
attention : ( For six-seven months after end of monsoon) |
Immediately after end
of monsoon, attend to run down stretches in the entire gang length. Thereafter, the following schedule of work
shall be followed : (i) Picking of slack 1-2 days in a week (ii) Remaining days
shall be allotted to : (a)
Annual systematic attention. (b)
Overhauling of level crossings. (c)
Destressing of LWRs. (d)
Spot renewals of rails, sleepers etc. (e)
De-weeding. (f)
Cold weather patrolling, etc. |
(b) Pre-monsoon
attention : (For two months prior
to onset of monsoon) |
(i) Picking of slacks
1-2 days in a week. (ii)Remaining days
shall be allotted to : (a)
Cleaning and repairs to side and catch water drains and cleaning of water
ways. (b)
Attention to yard drainage. (c)
Spot renewals of rails, sleepers etc. (d)
Shallow screening of specified lengths. (e)
Hot weather patrolling. |
(c) Attention during monsoon : (For 3-4 months) |
(a)
Picking of slacks as required. (b)
Normal track maintenance of yard lines. (c)
Cleaning, removal and loose boulders from cuttings and tunnels to ensure free
flow of water. (d)
Monsoon patrolling. (e)
Maintenance of side and catch water drains. (f)
Repairs to cess and bank. |
Note : |
(i) |
For maintenance schedule on LWR track, special instructions in the LWR
Manual should, in addition, be followed. |
|
(ii) |
Spot renewal of trails and sleepers shall be done as per requirement any
time of the year. |
|
(iii) |
Destressing of LWRs shall be done as per requirement and schedule to be
prepared by the PWI, as per provisions of LWR Manual. |
|
(iv) |
Main tamping, pre and post tamping works shall be done as per schedule of
working of the tamper. PWI and AEN
should be advised at least one month in advance of the programme of the
machine to enable them to complete pre-tamping operations. |
|
(v) |
Lubrication of ERC’s shall be done by Keyman throughout the year as per
para 1411(5)(b) of the Manual. |
|
(vi) |
Oiling and greasing and visual inspection of fish plated joints shall be
done as per para 241 of the Manual. |
ADVANCE CORRECTION SLIP No. 66 Dated. 30.03.2001
A new Para 914 (b)(v) be added to chapter IX of IRPWM to
read as under :-
Check
rails of level crossing are required to be removed for tamping operation,
overhauling of level crossings, distressing of LWR or track renewal etc. Check rails should be re-fixed as quickly as
possible and preferably before leaving site.
Should a situation arise where check rails cannot be re-fixed for any
reason and trains have to be passed, a speed restriction of 30 kmph should be
imposed besides ensuring that road traffic is diverted till the check rails are
put in place.
ADVANCE CORRECTION SLIP No. 65 Dated. 01.03.2001
A new para 309 (A)
be added to read as under :
309(A) Project
report for tract renewal works : Systematic and meticulous planning for various items of
execution of track works is essential for achieving quality, economy and timely
completion of works. For every
sanctioned track work e.g. CTR, TSR, TRR, deep screening, bridge timber
renewal, etc. a detailed project report should be prepared. The report should inter alia, cover the
following aspects :
i) Details of Work - Pink book detail, scope of work, locational
details, cost of estimate particulars etc.
ii) Existing track structure - Inventory of existing tract structure
including the rails, sleepers, fittings, ballast quantity/deficiency in track,
type width of formation and other details should be taken as prescribed in
P.Way diagram, details of level crossings, bridges, electric fittings, curves,
height of bank, cuttings, yards, sidings, etc.
iii) Classification of track materials - During inventory of the existing track
structure by foot by foot survey, identification, classification and
colour making of existing track
materials as second hand and scrap would be done as provided in para 320 of
IRPWM. The classification should be
approved by the competent authority.
Action plan for stacking storage and disposal of the released materials
should be clearly indicated. Inventory
of existing track materials would normally be prepared jointly by the PWI of
the section and the PWI(Spl) for the renewal.
iv) Proposed track structure -
The proposed P.Way diagram of the affected length should be prepared in
the same format as done for the existing track structure and incorporated in
the project report.
v) Existing/proposed gradient profile
- The levels of existing
track should be taken at every 20 metres and a gradient diagram prepared. Introduction of vertical curves should be
critically examined and the proposed profile of track shown in red line
indicating the proposed grades. Lowering
of track should be avoided. Precise lift
of track at girder bridges should be worked out and a separate scheme developed
for lifting of girders on each of the affected bridges. Similarly, the magnitude of lifting at level
crossing should be worked out and indicated in the report. Care should be exercised to keep the road
surface in one level on level crossings spanning to across multiple
tracks. This may require regarding of
adjacent lines too.
vi) Realignment of curves - All
curves should be measured afresh and slew worked out for realignment wherever
necessary, keeping in the obligatory points in view.
vii) Method of execution - The
work should be executed “bottom upwards” i.e. sequence of execution of works
will be in the following order –
Formation Ballast Sleepers Rails.
viii)
Formation :
a) Repair and widening of cess : The project report should indicate the
requirement of and plan for widening of formation in both banks and cuttings
wherever necessary. Provision of proper
drains in cuttings should also be planned.
b) Formation treatment : Areas needing formation rehabilitation should
be identified and a study for possible solutions and method of execution of the
rehabilitation scheme should form part of the project report.
ix) Ballast
- The requirement indicating
bifurcation of cess supply and depot supply and the source and means of each
should be spelt out clearly. Mode of
providing ballast cushion i.e. deep screening or raising should be identified
along with sketches of cross sections present and proposed. Sleeper renewal would normally not be started
unless adequate arrangements for supply of ballast have been made.
x) Transportation of P.Way materials - The mode of transportation for various
track components and unloading of rails and sleepers in particular, at the work
sites should be indicated in the project report.
xi) Welding
- The complete details of welding
requirements, the arrangements need to be made for its execution whether
departmentally or through contract should be clearly indicated in the report.
xii) Renewal of turnouts, bridge timbers,
etc - The project report should cover the complete
details of turnouts, bridge timbers, level crossings, etc. where renewal is to
be carried out. Whether turnouts are to
be laid manually or by mechanized means, should be clearly brought out
indicating the arrangements made. The
report should also include the mode and agency for overhauling and relaying and
making up of road surface at the level crossings.
xiii) Use of machines - The
requirement of machines for renewal (if machanised renewal is planned) deep
screening ( if mechanized deep screening is planned) and tamping/stabilizing
and the duration for which the machines are required should be indicated. The machines that would be deployed should be
identified and staff nominated. The
planning for repair of machines at the works site, supply of fuel and other
consumables should be planned. The
requirement of additional lines in the existing yards for making base depot and
arrangements made for the same should be indicated in the report.
xiv) Contracts - The
contracts that are required to be entered into for various activities of works
and the activities, which are to be done departmentally, should be spelt
out. The planning for deployment of
staff/supervisors for execution at various activities should be indicated.
xv) Material Planning - The
material requirement should indicate the materials to be arranged by the
headquarters and by the Divisions.
Against each material, the proper nomenclature and drawing number should
be indicated. Rails nons. And sizes
(including lead rails, check rails etc.), sleepers (including specials), rails
and sleeper fastenings, switches and
crossings, level crossing and bridge sleepers and fittings, etc. should be
fully covered. The consignee particulars
and the destination, the mode of transport should also be indicated.
xvi) Manpower Planning - The
requirement of manpower including the officers, supervisors, artisan and other
staff should be worked out with minute details.
The arrangements made for camping of these officials and mobilization
should be reflected in the report.
xvii)
LWR/CWR plans - For
welding of rails into LWR/CWR, the LWR plan should be got approved by the
competent authority in advance. Such
plan should form part of the project reports.
xviii)
Requirement of speed restrictions,
traffic blocks and other material train -
Planning for execution of track renewal works should be such that
the time loss on account of speed restriction is minimal and is within the
permissible limits. The report should
indicate requirement of speed restrictions and traffic blocks together with
duration. The corridor for blocks is
required to be planned in consultation with the Operating Department and
accordingly reflected in the report after obtaining the approval of DRM. Arrangements made for various type of wagons
for transportation of ballast, sleepers, etc. together with requirement of
locomotives should be indicated in the report in consultation with Sr.DOM and
with the approval of DRM.
xix) Monitoring mechanism - The
list of all activities involved and the time estimation for each activities
should be worked out. These activities
should be sequenced and co-related in logical manner and network diagram
prepared using CPM method. The critical
activities should thus be identified.
These should form part of the project report.
xx)
The detailed project report covering
the various points as mentioned above should be prepared as soon as the
approval of Board to include the works in FWP is conveyed to the Railways. These reports should be submitted to
headquarters for scrutiny and approval.
ADVANCE CORRECTION SLIP No. 64 Dated. 05.01.2001
The para
901 of chapter IX of IRPWM – 1986 modified vide correction slip No. 35 dated
19-08-99 be re-modified to read as under :
901 General Location: As far as
possible, new Level Crossings may not be located in busy station yards where
heavy detention to the road traffic and other operational problems are likely
to be encountered. If provision of Level Crossing is inescapable it
may be located outside the outermost facing points. For Level Crossings already located within
busy station yards affecting Railway operations and causing heavy detention to
the road traffic, efforts should be made to replace them by road Over/ Under
Bridges as per extant rules or shift them outside the outer most facing points,
especially during planning of gauge conversions, yard re-modeling and doublings
and iits operation
ADVANCE CORRECTION SLIP No. 63 Dated. 27.11.2000
The following para be added at end of the existing para
275(3) of IRPWM – 1986:-
The fixing of guard rail on concrete
sleepers shall be done as shown in drawing No. RDSO/T-4088 to 4097 by proper
tightening of ail screws. Provision of
MS flats/tie bars for tying PRC sleepers together at ends is not required.
ADVANCE CORRECTION SLIP No. 62 Dated.
The
following line be added at the end of the existing para-1405 of IRPWM 1986 :-
`For
laying of concrete sleepers for fan shaped turnout, the instructions given in
para 1413 be followed.'
A new para
1413 be added to read as under :
1413. Laying of fan shaped turnout sleepers
: (1) Loading of PSC turnout sleepers in
BFRs.
(a) Sleeper of
the approach and sleepers meant for lock bar crank will be loaded at right
angles to the track.
(b) The
remaining sleepers will be loaded parallel to the track on the BFRs.
(c) Suitable
nos. of wooden battens to support the sleepers in between layers of turnout
sleepers will be used as in case of main line sleepers to prevent damage.
2. Unloading :
(a) Depending
upon the process of laying of the turnout adopted, the sleepers shall be
unloaded either near the proposed location on firm & level ground or
adjacent to a nearby siding or on a goods platform by means of a crane.
(b) While
unloading due care shall be taken that the sleepers or the inserts are not
damaged.
1.
Site preparation for laying :
(a) Ensure that
a clean ballast cushion of 30 cm below the bottom of sleeper is available.
(b) These
turnout sleepers are to be laid where the approach track is also laid with PRC
sleepers. Thus there would be no need to
lower the formation to provide adequate ballast cushion.
(c) The ballast
bed has to be perfectly level. Any
variation in level may affect the gauge adversely.
(d) Enough
ballast shall be stacked along the cess to enable the filling of ballast in the
cribs on the same day.
(e) Longitudinal
and cross drains may be provided in turnout area to avoid accumulation of
water.
(f) The site
preparation to be completed well before laying turnout ensuring deep screening of
ballast in turnout length and 30m on either side along the track.
2.
Assembling :
(a) Ensure the
availability of all fittings at site strictly as per requirement of latest
drawings for switch portion, lead and crossing portion.
(b) The
complete turnout will be assembled on a level ground adjacend to the site of
laying or on the loop line corrected to turnout.
(c) Red/blue
rounded marking on the sleepers should invariably be kept on the right hand
side irrespective of left hand or right hand turnout.
(d) Spacing of
sleepers should be strictly as per layout drawing.
(e) The
sleepers shall be perpendicular to the straight track in switch portion only.
(f) In lead
portion, the sleepers will be inclined at half the angle between the normals to
straight and curved track at that point.
Proposed disposition is appended as Annexure-14/1.
(g) To ensure
correct layout, laying of sleeper falling at transition from switch to lead and
lead to crossing portion should be paid special attention. Sleepers in the switch portion, lead portion
and crossing portion are as under :-
Turnout |
Switch |
Lead |
Crossing |
1:8.5 |
1-13 |
14-41 |
42-54 |
1:12 |
1-20 |
21-64 |
65-83 |
PROPOSED DISPOSITION
(h) The spacing
of the sleepers in the lead portion should be as per layout drawing to make a
radial or fan shaped layout. The spacing
has been worked out separately for both the rails. This separate spacing on two rails make the
layout fan shaped in lead portion.
(i) The
sleepers in the crossing portion shall be perpendicular to bisecting line of
crossing.
(j) Sleeper
no. 3 & 4 may be placed for housing motor with the extended portion of
sleeper in reverse direction only in circumstances where it cannot be avoided.
(k) The
approach sleeper in advance of switch portion should be provided without fail,
they are for gradual elimination of slope of rail top (1:20).
(l) The exit
sleepers behind the crossing portion should also be provided for gradual
introduction of rail slope (1:20).
3. Insertion of pre-assembled turnout :
The complete assembled turnout shall be inserted in
position after breaking it into three panels viz. Switch, lead and crossing
portions by means of cranes or rollers.
6. Manual insertion : In case the PSC
turnout sleepers are to be manually inserted, then the same must be done
sleeper by sleeper ensuring that at no time the alignment and level is beyond
permissible limits. This work may be
done under a suitable speed restriction if necessary and adequate mechanical
means for packing the sleepers must also be available.
ADVANCE CORRECTION SLIP No. 61 Dated. 22.08.2000
(Bd's letter
No.97/CE-II/TS/2 Pt.2 dtd. 22.8.2000)
4. The para 248 (2) (a) and
(b) be replaced with the following :-
(a) Broad Gauge
:- The following minimum rail sections are recommended based on the speeds
obtainable and the traffic condition :-
Traffic density in GMT |
Routes |
||||||
A |
B |
C |
D.Spl |
D |
E.Spl |
E |
|
More than 20 |
60 Kg |
60 Kg |
60 Kg |
60 Kg |
60 Kg |
60 Kg |
60 Kg |
60 Kg |
60 Kg |
60 Kg |
60 Kg |
60 Kg |
52 Kg/ 90 UTS |
|
52 Kg/ 90 UTS |
5-10 |
60 Kg |
52/90 |
52/90 |
52/90 |
52/90 |
52/90 |
52/90 |
Under 5 |
52/90 |
52/90 |
52/90 |
52/90 or 60 Kg (SH) |
52/90 or 60 Kg (SH) |
52/90 or 60 Kg (SH) |
52/90* (SH) or 60 Kg (SH) |
Loop line |
52 Kg (SH) |
||||||
Pvt. Siding |
52 Kg of T-18 quality or T-12 quality second hand rails. |
Note :
52/90 represents 52 Kg/90 UTS rail section.
(i) Existing 90R rails may be
allowed to remain for speeds not exceeding 130 Km/h.
(ii) On routes identified for running of 22.1
t axle load wagons, 60 Kg. rails shall be used on all routes.
(iii) On private sidings where BOX'N or 22.1 t
axle load wagons ply, the rail section should be 52 Kg. In case of operating speeds exceeding 30 Km/h
and going up to 50 Km/h, as also where BOX'N or 22.1 t axle load wagons ply,
T-12 quality rails should be used.
(iv) Head
hardened rails should be used for (a) local lines where EMU stock is running
(b) Ghat section with gradients steeper than 1 in 150 and/or curves sharper
than 2 degree (c) location where rate of wear of rails necessitates rail
renewal at frequency of 10 years or so.
These rails should be laid on continuous and long stretches.
(v) *
Second hand 52Kg rails may be used on case-to-case basis, with the prior
approval of Railway Board, depending upon quality of released rails available.
(b) Metre Gauge
: The following rail sections are recommended on MG routes :-
Route. Rail
section recommended.
`Q' and
`R1' 52 Kg (SH)/90R (New)*
`R2' and
`R3' 52 Kg (SH)/90R (SH)
`S' 52 Kg (SH)/90R (SH)/75R
(SH)
* 90 R
(New) to be only used with specific approval of Railway Board, in case no
suitable 52 Kg (SH) rails are available for use on MG during renewal.
5. The table `B' of para 305 (2) be
deleted and the following sentence be added to para 305 (2) :-
(iv) All renewals on Metre gauge shall be with concrete,
steel and CST-9 sleepers (new or second hand)
ADVANCE CORRECTION SLIP No. 60 Dated.
(Bd's letter No.97/CE-II/TS/2/Pt.2)
The
following sentence be added at the end of existing para 237 (1) (l):-
In case of
PSC sleeper layout with elastic fastening, creep anchors need not be
provided. In case excessive creep is
observed at such layouts, the condition of elastic fastenings may be examined
and suitable action be taken.
A new para-242
(3) (C) be added to read as under :-
Para 242
(3) (C) : The PSC sleepers with elastic fastenings are considered as creep
resistant and therefore no other creep anchors are required. In case, excessive creep is observed on PSC
sleeper road, the condition of elastic fastenings, sleepers and adequacy of
ballast resistance should be examined.
Action for replacement/renewal of fittings, sleepers and providing
adequateballast resistance etc. should be taken as necessary.
ADVANCE CORRECTION SLIP No. 59 Dated. 1.08.2000
(Board’s letter
No.2000/CE/ dtd. 1.8.2000)
Replace para
275(3) with the following :
`(3) Fixing of
Guard rails : The ends of guard rails should be bent vertically and buried
and a block of timber fixed at the end to prevent entanglement of hanging loose
couplings. To ensure that guard rails
are effective, they should be spiked down systematically to every sleeper with
two spikes towards the centre of the track and one spike on the opposite
site. Notching of the rail foot for
spikes fixing the guard rails should be done on every alternative sleeper. Sleepers
should be tied at both ends by MS Flats/tie bars fixed through holding down
bolts.'
Replace para 724
(1) & (2) with the following :-
`(1) Arrangements should be made to stock sufficient
quantities of rails, sleepers, materials for cribs, ballast, sand/quarry dust
and boulders at suitable points near vulnerable locations, so that the
materials may be rushed to site as required.
(2) Before the onset of monsoon, specified number of
wagons loaded with sand/quarry dust, ballast and boulders should be kept at
appropriate stations for quick movement to vulnerable locations.'
Replace para
723(9) with the following :
`(9) The prescribed reserve stock of boulders, empty
cement bags, wire netting and sand/quarry dust should be kept at specified
locations for rushing to site, in case of emergency and should be made good, in
case of deficiency.'
ADVANCE CORRECTION SLIP No. 58 Dated. 1.08.2000
(Board’s letter
No.97/CE-II/TK/15 dtd. 1.8.2000)
Existing para 167, 168, 169 and 170 may be modified to
read as under :-
167. Selection and training of keyman :
The selection of Gangman to perform the duties of a
keyman is to be considered as a step in his training as Mate. Keyman trained in laying and maintenance of
LWR/CWR on concrete sleeper and possessing valid competency certificates issued
by Zonal/Divisional Training center should only be posted on LWR/CWR section.
168 (1) Keyman's daily inspection :
The keyman shall inspect by foot his entire beat once a
day, both the tracks and bridges, and return along the opposite rail to that
taken on his outward journey in case of single line. On double line, keyman will carry out one
round of inspection in morning hours by going along up line and then returning
along Down line or vice-versa. On the
days of Gang holidays and rest, he shall perform the usual duties and get one
day's rest in the week as per the roster duties in force. On rest days or during absence or leave or
sickness, a senior intelligent gangman should be deputed in place of the
regular keyman.
(2) Roster duty hours of keyman :
The roster duty hours of keyman for winter months should
be so adjusted as to ensure one round of track inspection in early morning to
enable detection of any rail or weld fractures that might have occurred during
the night or early morning. DEN/Sr.DEN
of the section shall decide and notify the exact timings and the period of each
section.
169. Equipment of keyman :
The keyman shall carry with him on his rounds two red
flags, and green flag, ten detonators, a flangeway gauge if required, for
unmanned level crossings, a keying and spiking hammer, a fish bolt spanner, and
two fish bolts, spare fittings and a rail closure of 30mm size. For the work of greasing of elastic rail
clips wherever applicable, keyman shall carry a wire brush, emery paper, a
duster and grease.
170. Duties of Keyman :
1) While
walking over his length, he should look for defects, such as loose fish bolts,
SEJ fittings in switches and crossings, fittings on girder bridges and open top
culverts, broken or burnt sleepers, broken plates or tie bars, attend to them
as necessary. If he finds that fittings
are consistently working loose even after repeated attention, he should report
the matter to the Mate, PWM and Permanent Way Inspector. If the defects are serious, he should at once
inform the Mate of the gang protecting the line in the meantime, if necessary,
according to rules.
2) He
shall keep a special watch on the rails and welds marked for observation by the
USFD team.
3) If he
should notice any condition of danger, such as broken rail, broken weld or wash
away of ballast, theft of fittings in large numbers etc., he shall at once
protect the line as per rules, take such action as is possible and report the
matter to the Mate, the nearest Station Master and Permanent Way Inspector.
4) At unmanned level crossings, he
shall maintain the flange ways between the check and the running rails clear of
obstructions.
5)
In track other than with elastic fastenings, the keyman in addition to his
normal round of the whole beat and inspection and tightening of loose fittings,
should attend one telegraph post (TP) on one line thoroughly on every day. This thorough attention should consist of
tightening of each bolt and fittings in these TPs of the beat during that
particular day. Missing keys and other
missing fittings will be recouped by him.
He shall also ensure correct driving of fittings in this stretch.
6) Where the beat of a
Keyman consists of PRC sleepers, apart from his round of the beat, the keyman
should also carry out in a systematic manner from one end greasing of the ERC
and eyes of inserts at the rate of 15 sleepers per day. Greasing shall be done as per the procedures
laid down in para 1411(5) (b) of IRPWM tackling one clip at a time.
7) Keyman with the assistance of one
gangman will also carry out rail end examination, lubrication of fish plated
joints as per direction of PWI/PWM.
8) For imposing of caution after
stopping the train or otherwise wherever required for safety, Keyman will be
provided cyclostyled slips by PWI.
Keyman after filling location and speed will hand over the same to
Driver or ASM and obtain acknowledgement.
9) The following are the special duties and
responsibilities of the keyman in LWR/CWR territories :-
(i) Periodical (fortnightly)
oiling and greasing of SEJ, checking and retightening of fastenings at SEJ and
other sleepers, if necessary (para 6.2.6 of LWR Manual).
(ii) Replacement of
missing fastenings not requiring lifting or slewing of track as per para 6.2.6
(I) of LWR Manual.
(iii) To ensure that all
creep anchors where provided butt against the sleepers and in case of large
scale displacement of anchors, he shall report the matter to Mate/PWM/PWI
(Subsection)/PWI (incharge).
(iv) To watch for sun kinks, loose
or missing fastening which may result in buckling or any damage to LWR/CWR and
SEJ. On noticing any buckling or damage
to track, he shall take necessary action to protect the track and report the
same immediately to PWI (Sub-section)/ PWI(incharge), Station Master. However, he will continue to perform his
Keyman's duties of daily inspection.
(v) To keep a sharp look out in cold
mornings, especially during winters to detect any fractures which may occure,
in case of rail/weld fracture, he shall take prompt action to protect the track
and carry out emergency repairs to permit the restoration of traffic promptly
and report to PWI (Subsection)/ PWI(Incharge)/nearest Station Master (para
7.2.2 and 7.2.3 LWR Manual).
10. The Kayman shall promptly
report to Mate/PWI any encroachment or unauthorised structures as and when they
take place in the Railway land in his beat.
11. After completing
inspection of the beat, the Keyman should assist the Mate in the day's work
being done.
12. When materials,
such as dynamo-belts, engine tools and personal articles of passengers, are
found on line, the Keyman should collect them and arrange for handing them over
to the nearest Station Master.
13. The Keyman will remain
incharge of the gang in absence of the Mate once a week. On that day, the Mate is required to carry out
the work and duties of Keyman.
14. Whenever
directed he will supervise rail dolly working.
However, he must have competency certificate for the same.
An additional para
may be added as under :-
168. Keyman's book :
(i) Printed
keyman's book should be supplied to every keyman.
ii) The
keyman shall maintain the book upto date wherein all special work done, missing
fittings and their recoupment with location and date are to be entered.
(iii) PWI should
make a date wise schedule and enclose with the Keyman's book the Kms/TPs that
the Keyman has to attend on each day of the month to complete the task required
to be done as per sub para 6, 7, 9(I) of para 170 above. PWIs and AENs during their inspections should
check to ensure that such Kms have really been thoroughly attended to and
initial against the entries.
(iv) Special
locations to be watched by the keyman should be entered in the book.
v) The special
fittings like joggled fish plates and other material provided in the section
which are vital for safety and for restoration of traffic should also be
mentioned in the book.
ADVANCE CORRECTION SLIP No. 57 Dated. 17.02.2000
(Board’s letter
No.98/CE-II/TS/1 Pt. Dtd. 25.7.2000)
The
following may be added to para 202 (1) under Group`B' route:
(XVII) - Chennai beach - Dindigul.
(XVIII) - Bangalore-Dharmavaram-Gooty.
ADVANCE CORRECTION SLIP No. 56 Dated. 13.07.2000
(Board’s letter
No.Track/21/99/0907/7 dtd. 13.7.2000)
Para 252 (3)
of Indian Railway's Permanent Way Manual, 1986 Edition may be modified as
follows :-
252 (3)
`Ultrasonic Rail Flaw Detection - Ultrasonic testing of rails is a specialised
activity and the inspectors carrying out the ultrasonic testing of rails shall
be trained by RDSO, in the techniques of USFD testing. Each zonal railway shall create adequate
number of ex-cadre posts of inspectors to ensure that entire track length in
their jurisdiction is ultrasonically tested at the laid down periodicity.'
(a)
Description of instrument - Manually operated….
ADVANCE CORRECTION SLIP No. 55 Dated. 31.05.2000
(Board’s letter
No.98/CE-II/CS/2 dtd. 31.5.2000)
The
following changes may be made in paras 910 & 1007 of IRPWM :-
Para 910 (1) (v) be modified to read as
under :- Gatemen working on double line/multiple lines, ghats, suburban and
automatic block territories shall be provided with three fusees. Gatemen working on single line sections shall
be supplied with one fusee.
The note
to para 910 be modified to read as
under :-
Note
: In the case of level crossings in multiple lines and hand signal flags/lamps,
detonators shall be increased suitably.
Para 1007 (1) (1) be amended to read as
under :- Three flare signals (fusees) on double/multiple lines, ghats, suburban
and automatic block territories and one fusee on single line sections.
ADVANCE CORRECTION SLIP No. 54 Dated. 29.05.2000
(Board’s letter
No.99/CE-II/TK/20 dtd. 29.5.2000)
The
existing para 277 be substituted with the following :-
1.
On the bridge approaches, for a length of 100m, PSC sleepers with arrangement
for fixing guard rail (Drg.No.RDSO/T-4088 to 4097) should be provided
irrespective of the type of sleepers in the track.
2.
The full compliment of track fittings at bridge approaches upto 100 metres must
be ensured at all times to maintain required track geometry. Any deficiency noticed must be recouped
immediately.
3.
The rail level of track in approaches of bridge should be maintained as per
L-section and dips in rail level immediately after abutments must be
avoided. The alignment and super
elevation in case of curved track should also be maintained as per design. Rail joints should be avoided within three
metres of a bridge abutment.
4.
Full ballast cushion as specified for LWR track should be provided upto 100
metres from the abutment.
5.
On the bridge approaches, for a length of about 100 metres, width of cess
should be 90 cm. Clear of full ballast section to maintain ballast
profile. Ballast retaining wall should
also be provided for a length of one rail from the abutments to maintain ballast
section. The condition of the ballast
wall should be checked and repairs carried out whenever necessary.
6.
Switch expansion joints should be provided at the bridge approaches in LWR/CWR
track as per provisions of LWR manual.
ADVANCE CORRECTION SLIP No. 53 Dated.
(Board's letter
No.88/Track-III/TK-18/Vol.III (Part)).
The existing para 203 (1) be replaced to
read as under :-
(1) System to be adopted – The track should
be maintained either by conventional system of track maintenance or by 3-tier
system of track mainteannce.
The
existing para 205 be renumbered as Para 205 Maintenance Planning – (1).
New para 205 (2) be included to read as
under :-
(2) For
sections nominated for mechanised maintenance, annual plan for deployment of
various track machines shall be finalised by CTE(MC)/CTE of the Zonal Railway
and he shall arrange to deploy the machines accordingly.
The existing para 225 regarding
`Maintenance by Measured shovel packing is deleted.
The existing para 228 be replaced to read
as under :-
228. 3-tier system of track maintenance: -
(1) 3-tier System of track maintenance shall be adopted on sections nominated
for mechanised maintenance. This shall
consist of the following 3 tiers of track maintenance:
(i)
On-track machines (OMU)
(ii)
Mobile Maintenance Units (MMU)
(iii)
Sectional Gangs
(2) Large track
machines for track maintenance include Tie-tamping machines for plain track and
points and crossings, shoulder ballast cleaning machines, ballast-cleaning
machines, ballast regulating machines and dynamic track stabilizers. These machines shall be used as per the
various instructions issued in Indian Railways Track Machines Manual. These machines shall be deployed to carry out
the following jobs:
(a) Systematic tamping of plain track as well as
Points & Crossings;
(b) Intermediate tamping of plain track as well as
Points & crossings;
(c) Shoulder ballast cleaning;
(d) Ballast profiling/redistribution;
(e) Track stabilization;
(f) Periodical deep screening.
(1) Mobile
Maintenance Units :
(a) The mobile maintenance units (MMU) shall consist
of two groups:
(i) MMU-I : One for each PWI’s section.
(ii) MMU-II: One for each sub-division
(b) The functions of MMU shall be as below :
MMU-I, (Rail-cum-Road Vehicle based)
one with each PWI incharge with a jurisdiction of 40 – 50 Kms. double line or
90-100 Kms. single line:
(i) Need based spot tamping;
(ii) In-SITU rail welding
(iii) Casual Renewal and repairs except planned
renewals
(iv) Overhauling of Level Xings
(v) Replacement of glued joints
(vi) Rail cutting/drilling and chamfering
(vii) Permanent repairs to fractures
(viii) Creep or gap adjustments involving use of
machines
(ix) Distressing of LWR/CWR
(x) Loading/Unloading of materials
(xi) Any other functions assigned.
MMU-II : (Road Vehicle Based ) : one with each sub
division :
(i) Reconditioning of Turnouts
(ii) Minor repairs to the equipments of MMU
(c) The MMU
shall be equipped with the following equipments. These equipments shall be used according to
the working instructions, as and when issued.
List of equipments for MMU-I :
A.
Communication Equipment
1. Walkie
Talkie | 4 sets
2. Portable field telephones |
B.
Rail Cutting/Drilling Equipment
3. Disc
Cutter 1
4. Rail Cutting Machine 1
5. Rail Drilling Machine 1
6. Chamfering kit 1
C.
Rail Welding Equipment
7. Rail
Welding Equipment 2 sets
8. Weld Trimmer 1 set
9. Rail Profile Grinder for welded joints 1 set
D.
Spot Tamping with Lifting Lining
10.
Off Track Hand Held Tamper
With Generators 1 set
11. Lifting Jack-hydraulic/mechanical 4 sets
12. Lifting-cum-Slewing Device 2 sets
E.
Destressing Equipment
13. Rail
Tensors-Hydraulic/mechanical 2 sets
14. Rollers, wooden mallets 1 complete
set
for
Distressing
3
Km. LWR
F.
Inspection Gadgets
15. Inspection
Kit 1 No.
16. Gauge cum Level 1 No.
17. Rail Thermometer 1 No.
18. Vernier Calipers 1 No.
19. Micrometer 1
No.
G.
Material Handling Equipment
20. Rail
Dolly 6
No.
21. Mono Rail Wheel Borrow 2 No.
H.
Safety and Protection Equipments
22.
Warning System
23.
Red Banner Flag
24.
Red Hand Signal Flag
25.
Green and Signals
26.
Detonators
I.
Gas Cutting Equipments with Accessories : 1 set.
List of Equipments for MMU-2 :
A.
Points and Crossing Recording Equipment :
1. Welding
Generator 1 set
2. Arc Welding Equipment 1 set
3. Hand Held Rail Grinder 2 sets
B. For Minor Repairs to Equipments :
4. Spanner of sizes 2 sets
5. Trifer 2
6. Files of Sorts 2 sets
7. Bench Drill 2
8. Vice Bench 2
9. Bench Grinder 2
(4) Sectional Gangs :
The
sectional gangs, under 3-tier system of track maintenance shall perform the
following functions :
(a) Patrolling of track :
(i) Keyman’s daily patrol
(ii) Hot/cold weather patrolling
(iii) Monsoon Patrolling
(b) Watching vulnerable locations
(c) Attention of emergencies viz. temporary repairs
of fractures.
(d) Need-based attention to bridges, turnouts, SEJs
and approaches of level crossings.
(e) Greasing of ERCs, lubrication of joints, casual
changing of rubber pads and other fittings
(f) Minor cess repairs
(g) Cleaning of drains and boxing of ballast
(h) Attention to loops
(i) Creep and gap adjustment not involving use of
machines
(j) Cleaning of crib ballast for effective
cross-drainage
(k) Pre & post tamping attention
(l) Assistance to MMU & OMU as required
(m) Any other functions assigned.
ADVANCE CORRECTION SLIP No. 52 Dated. 24.04.2000
(Board's letter
No.98/CE-II/TS/4 dtd. 24.4.2000).
The
existing legend of the annexure 2/4 of para-211 of IRPWM be modified as under
:-
Rail Section/UTS |
Colour |
Indigenous |
Imported |
|
Yellow |
|
|
|
Yellow |
|
|
|
Green |
|
|
|
Green |
|
|
|
Red |
|
|
|
Red |
|
|
|
Sky Blue |
|
|
|
Sky Blue |
|
|
|
Blank |
|
|
|
Blank |
|
|
|
To be decided by Rly. |
|
|
SLEEPERS |
|||
|
Green |
|
|
|
Green |
|
|
|
Yellow |
|
|
|
Red |
|
|
|
Black |
|
ADVANCE CORRECTION SLIP No. 51 Dated. 21.04.2000
(Board's letter
No.98/CE-II/CS/2 dtd. 21.4.2000).
A new para
251 (5) may be added to IRPWM,1986 to read as under:
Para 251(5) Chamfering of bolt holes in
rails : (a) General : (i) Chamfering of bolt holes work hardens the
periphery of holes and thereby delays the formation of star cracks. The chamfering of hole takes 5 minutes per
hole. Each drilled hole shall be chamfered.
(ii) Existing
hold holes in fracture prone zones should be chamfered if not elongated. In case of elongated holes, the chamfering
bit will not be in contact with the full edge of the bolt holes and there will
be uneven hardening of the metal resulting in stress concentration in
weaker-zones. Therefore, such portion of
rail should be removed; holes should be drilled and chamfered.
(b) Equipment for chamfering of bolt holes
: Work hardening of bolt holes should be done with chamfering kit of approved
make. The chamfering kit consists of the
following :
Equipment (as per Fig.1)
Qty.
(i) High
tensile bolt M-20 1
No.
(ii) High
tensile nut for M-20 bolt 1
No.
(iii) Sets of 2
H.S.S. chamfering bits 1
set
(iv) 19mm sq.
drive sockets size 32mm 8 Nos.
(v) Set of 2
packing pieces (sleeves) 1
set
(vi) T-400
torque-wrench with built-in rachet
Mechanism 1.25m length 1
No.
(c) (i) Chamfering of bolt holes in the welded rail
panels should be done before despatch in the Flash Butt Welding Plants, if
situation so warrants.
(ii) When rails in track
are end-cropped, new bolt holes should be chamfered at site.
(iii) Bolt holes
in new rails received directly from steel plant should be chamfered before rails
are laid in track.
(d)
Procedure for chamfering of bolt holes :
(i) The nut of
high tensile steel bolt is removed and one packing piece is inserted in the
shank followed by one side of the H.S.S. chamfering bit.
(ii) The high
tensile steel bolt is inserted with 2 pieces in the rail hole.
(iii)
On the other face of the rail hole, the second half of the HSS chamfering bit
is inserted over the shank followed by the second packing piece.
(iv)
The nut on the high tensile steel bolt is replaced.
(v)
Pre-set torque-wrench on nut at torque value of 52 Kg-m equivalent to an exile
force of 12.5 tonnes, is applied. The
nut is tightened with the torque wrench.
As soon as the present torque is attained, the torque wrench will
automatically trip indicating complete tightening to pre-set torque valve.
(vi)
The nut by reversing the torque wrench is unscrewed and HTS bolt is
removed. The process is repeated on
other rail holes.
(e) Chamfering
of each hole should be done under the supervision of Mate/Keyman.
ADVANCE CORRECTION SLIP No. 50 Dated. 14.04.2000
(Board's letter
No.99/CE-I/LX/80 dtd. 14.4.2000).
The
existing para 918 of IRPWM be replaced with the following :-
Para 918 - Provision of speed breakers on
the approaches of level crossing :- Provision of rumble strips on
approaches of level crossings as per the standard design is the responsibility
of Road authorities. Matter may be
persued with all State Governments/Road authorities to ensure that rumble
strips are provided on all level crossings as per standard design over the
total width of the road i.e. edge of the berm to edge of berm with proper road
warning signs as per the standard design.
However, it is incumbent upon Railways to provide speed breakers as per
the standard design on both manned as well as unmanned level crossing
irrespective of whether the approach road are metalled or un-metalled, as a
temporary safety measure, till such time these are replaced with rumble strips
of proper design by the Road authorities.
While providing speed breakers, following guidelines may be observed :-
(2)
One speed breaker should be provided on either approach of level crossings
located within the Railway land boundary at a distance maximum feasible but not
exceeding 20m covering full width of the road including berms as per Annexure -
9/6. For safety reasons, the paint
marking should be provided and their maintenance ensured.
(3)
Standard warning signs for speed breakers as per Annexure - 9/7 should be
invariably provided at a prescribed distance as indicated in item 19 of
Annexure 9/1 to para 904.
(4)
Speed breakers should be constructed with hot pre-mix bituminous material, well
compacted after laying on well prepared surface. Enough time is to be allowed for the
bituminous material to harden before opening it to the traffic. On berms and unmetalled roads, the speed
breakers should be supported on proper base of compacted road metal.
Annexure - 9/6
Annexure - 9/7
ADVANCE CORRECTION SLIP No. 49 Dated. 11.04.2000
(Board's letter
No.97/CE-II/Misc/5 (CS)/Pt. Dtd. 11.4.2000).
The
following changes may be made in the para - 263 of IRPWM :-
In
Annexure 2/11, 2/12, 2/13 and 2/14 to para 263 the following changes may be
made :-
Annexure 2/11 : Under
column F the figure of 6100 be replaced with 6850.
Under column F1 the figure of 5490 be replaced with 6250.
Annexure 2/12 : Under
column F the figure of 4880 be replaced with 5850.
Under column F1 the figure of 4270 be replaced with 5250.
Annexure 2/13 : In
the diagram the top width of 6100mm be replaced with 6850mm.
Annexure 2/14 : In
the diagram the top width of track shown as 4880mm be Replaced with 5850mm.
ADVANCE CORRECTION SLIP No. 48 Dated. 11.04.2000
(Board's letter
No.93/CE-II/PRA/40 dtd. 11.4.2000)
The
existing para 1208 of IRPWM be replaced with the following :-
1208 : Official-in-charge
of Material Train :- Whenever a material train is worked it shall be
accompanied by a Guard. As the Guard is
not qualified to carry out such duties as working of hoppers, distribution of
ballast/materials, supervising loading and unloading, maintaining muster rolls
and daily reports of labour and preparation of daily reports on material train
working a qualified engineering official should be deputed on the train to
ensure working of material train to the programme specified by Assistant Engineer.
ADVANCE CORRECTION SLIP No. 47 Dated. 15.03.2000
(Board's letter
No.99/CE-II/PRA/Accd./1 dtd. 15.3.2000))
The
existing para 243 (4) be replaced with the following para :-
234 (4) Action on buckling of track : If a
buckling does occur or appears imminent, the track should be protected
immediately with hand signal flags and detonators as per the protection rules
laid down. The buckled rails shall
preferably be cut adequately apart not less than 6.5 metres. The track shall then be slewed to the correct
alignment and cut rails of the required length shall be inserted to close the
gaps making due provision for welding of joints on both rails. The cut rails shall then be connected by use
of special fish plates and screw clamps and the line opened to traffic with
speed restriction. It may not be
possible to do any more until the temperature drops when the joints must be
adjusted. Particular care must be taken
to see that the factors which contributed to the buckling i.e. jammed joints,
seized fish plates or shortage of ballast receive appropriate attention without
delay.
ADVANCE CORRECTION SLIP No. 45 Dated. 17.02.2000
(Bd's letter
No.94/Track-III/TK/23-Vol.II dtd. 17.2.2000)
The para 607 of IRPWM 1986
may be read as under :-
Para 607 may be read as 607 (1).
A new Para 607(2) may be added to read as under :-
The
following limits of track tolerances are prescribed for the guidance of the
Engineering officials on the suitability* of standard of maintenance of track
for sanctioned speeds above 100 Km/hr. and upto 140 km/hr on BG track.
(i)
Alighment defects (versine measured on a chord of 7.5 metres under floating
conditions)
a)
On Straight Track : 5mm; values upto 10mm could be tolerated at few
isolated locations.**.
b)
On Curves : 65mm over the average versine, Values up to 6 7mm could be tolerated at few isolated locations**.
Total change of versine from chord to chord should not
exceed 10mm.
(ii) Cross Level
Defects :- No special tolerance limits. As regards cross levels, the track
should be maintained, to standards generally superior to that at present
available on main line track on which unrestricted speeds upto 100 Km/hr. are
permitted.
(iii) Twist (to
be measured on a base of 3.5 m)
(a)
On straight and curve track, other than on transitions - 2mm/metre except that
at isolated locations**, this may go upto 3.5mm/metre.
(b)
On transitions of cruves - Local defects should not exceed 1mm/metres, except
that at isolated locations** this may go upto 2.1 mm per metre.
(iv) Unevenness
rail joint depressions (versine measured on a chord of 3.5m) - 10mm in general
and 15mm for isolated locations**.
(v) Gauge
variations - No special specifications.
The maximum limits for tight and slack gauge should be as indicated in
Para 224(2)(e).
(*) Suitability
- Suitability refers to good riding quality for passenger comfort and not from
stability point of view.
(**) In above `few
isolated locations' has been taken is not exceeding 10 per km.
ADVANCE CORRECTION SLIP No. 42 Dated. 05.11.1999
(Bd's
lr.No.98/CE-II/CS/2 dtd. 5.11.99)
The
following may be added to para 301 of IRPWM.
(8)
Through Turnout Renewal (TTR)
(9)
Through Fitting Renewal (TFR)
(10)
Through Weld Renewal (TWR)
(11)
Through Bridge Timber Renewal (TBTR)
Para 1411 (4) may be modified to read as under :-
The existing matter be numbered as 4 (a).
Para 1141 (4) (b) be added to read as under :-
(b) Periodicity
of Measurement of Performance of Elastic
Fastening Components.
1. SAMPLES, SIZE AND TESTING FREQUENCY : (i)
SAMPLE SIZE : Toe load of elastic rail clip should be measured on 1% of
ERCs randomly on every 100 sleepers (all 4 ERCs to be measured on one sleeper).
(ii) TESTING FREQUENCY : Initial testing of
ERCs is to be done after four years of passage of 200 GMT of traffic, whichever
is earlier. In corrosion prone area, the
initial testing of ERC is to be done after two years or passage of 100 GMT,
whichever is earlier.
(iii) Subsequent
testing will be done every four years or 200 GMT in normal areas and two years
or 100 GMT in corrosion prone areas, whichever is earlier. However, if 20% or more of sample size
records toe load below 600 Kg. both frequency of inspection and sample size are
to be doubled.
2. REPLACEMENT OF ERC : (i) If 20% or more
of sample size records toe load below 400 Kg which is to be confirmed by 5%
sample size, proposal of through fastening renewal should be initiated.
(ii) The
provisions given above are only for guidance of Railways. The Railways on the basis of the overall
condition of track, pattern of traffic and the required level of maintenance should
undertake the large-scale replacement of the fastening.
(iii) Further,
as the loss of toe load is reflective of conditions of other elastic fastening
components like groove rubber sole plate, GFN/metal liners etc. as well, the
railways may also record condition of these components along with measuring toe
loads for elastic rail clips.
ADVANCE CORRECTION SLIP No. 41 Dated. 02.11.1999
The
existing para 302 (a) to be replaced with the following :-
(a) Incidence of rail fracturesfailures : A
spate of rail fractures on a particular sections having 5 withdrawals of rails
per 10 Km. in a year due to fracture and/or rail flaws detected ultrasonically
falling in the category of IMR & REM will have priority while deciding rail
renewals. In case the rail failures at
fish plated/welded joints are predominant, end cropping with or without welding
could be considered.
ADVANCE CORRECTION SLIP No. 40 Dated. 27.09.1999
The para
913, 3(a) & (b) of the IRPWM 1986 together with Annexure 9/3 to para 913 be
replaced with the following :-
(a) On double
line, if both lines are obstructed during day, he shall plant a red banner at a
distance of 5 metres on the line on which a train is expected to arrive first,
then plant another red banner flag on the other line at the site of
obstruction. He shall then pick up red
hand signal and showing it, proceed on that line towards the direction of an
approaching train to a point 600 metres on Broad Gauge and 400 metres on Metre
Gauge and Narrow Gauge from the level crossing and place one detonator on the
line, after which proceed further to not less than 1200 metres from the level
crossing on Broad Gauge and 800 metres on Metre Gauge and Narrow Gauge and
place 3 detonators on the line about 10 metres apart. Having thus protected the line on which a
train is expected to approach first, he should return to the level crossing,
picking up the intermediate detonators on his way back. He shall then proceed on the other line
showing red hand signal, place detonators similarly and return to the site of
obstruction to warn the Driver of an approaching train.
Provided that on those Metre Gauge sections where trains
run at more than 75 Km/h, the detonators shall be placed at distance to be
specified under special instructions by the Administration (Annexure 9/3).
(b) On single
line, if the line is obstructed during day, he shall plant a red banner flag
towards the direction from which a train is expected to arrive first, then
plant another banner flag towards the opposite direction at the site of
obstruction. He shall then pick up red
hand signal and as in sub-para (a) above, protect the line in the direction
from which a train is expected to approach first, return to the site of
obstruction, and proceed with all haste in the other direction to protect the
line. Having protected the line on both
sides, he should station himself at the place of obstruction to warn the Driver
of an approaching train (Annexure 9/3).
ADVANCE CORRECTION SLIP No. 39 Dated. nil
The table at para
244(4)(a) be substituted with the following :-
Traffic Density in GMT |
Routes |
||||||||||||
A |
B |
C |
D-Spl |
D |
E-Spl |
E |
|||||||
Number of sleepers per km. |
|||||||||||||
More than 20 |
1660 |
1660 |
1660 |
1660 |
1660 |
1660 |
1660 |
||||||
10-20 |
1660 |
1660 |
1660 |
1660 |
1540 |
1660 |
1540 |
||||||
Under 10 |
1660 |
1540 |
1540 |
1540 |
1540 |
1540 |
1540 |
||||||
Loop lines |
1340 |
1340 |
1340 |
1340 |
1340 |
1340 |
1340 |
||||||
Pvt. siding |
1340 |
1340 |
1340 |
1340 |
1340 |
1340 |
1340 |
||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(i) For routes
identified for running 22 t axle load wagons, Sleeper density of 1660 nos/km
should be maintained.
The Table (A) of
para 305 (2) be substituted with the following :-
(i)
All primary renewals in future shall be carried out with 60 Kg. PRC sleepers.
(ii)
PRC or ST sleepers may be used on loop lines and private sidings.
(iii)
ST sleepers used on loop lines and private sidings may be with elastic or rigid
fastenings.
The para 248(2)
(a) be replaced with the following :-
The following minimum rail sections are recommended based
on the speeds obtainable and the traffic condition :-
Traffic Density in GMT |
Routes |
||||||
A |
B |
C |
-Spl |
D |
E-Spl |
E |
|
More than 20 |
60 Kg |
60 Kg |
60 Kg |
60 Kg |
60 Kg |
60 Kg |
60 Kg |
10-20 |
60 Kg |
60 Kg |
60 Kg |
60 Kg |
52/90 |
60 Kg |
52/90 |
5-10 |
60 Kg |
52/90 |
52/90 |
52/90 |
52/90 |
52/90 |
52/90 |
Under 5 |
52/90 |
52/90 |
52/90 |
52/90 or 60 Kg (SH) |
52/90 or 60 Kg (SH) |
52/90 or 60 Kg (SH) |
52/90 or 60 Kg (SH) |
Loop Lines |
52 Kg (SH) |
||||||
Pvt. Siding |
52 Kg. or T-18 quality
or T-12 quality second hand rails. |
(i) Existing 90R rails may be allowed to
remain for speeds not exceeding 130 Km/h.
(ii) On routes identified for
running of 22 t axle load wagons, 60 Kg. rails shall be used on all routes.
(iii) On private sidings where BOX'N or 22 t
axle load wagons ply, the rail section should be 52 Kg. In case of operating speeds exceeding 30 Km/h
and going up to 50 Km/h, as also where BOX'N or 22 to axle load wagons ply,
T-12 quality rails should be used.
(iv) Head hardened rails should be
used for (a) local lines where EMU stock is running (b) Ghat section with
gradients steeper than 1 in 150 and/or curves sharper than 2 degree (c)
location where rate of wear of rails necessitates rail renewal at frequency of
10 years or so. These rails should be
laid on continuous and long stretches.
ADVANCE CORRECTION SLIP No. 38 Dated. 08.09.1999
(Bd's lr No.Track-21/99/0907/7 dtd. 8.9.99)
Para
281(c) of IRPWM 1986 may be modified as under :-
The instructions for Fabrication, installation and
Maintenance of Glued insulated rail joings as given in the `Manual for Glued Insulated Rail joints,
1998' issued by RDSO, should be strictly followed.
ADVANCE CORRECTION SLIP No. 37 Dated. 01.09.1999
(Bd's lr No.98/CE-II/CS/2 dtd. 1.9.99).
Existing Note (I) at the end of para 807 (2) (b) shall be
modified as under:-
Note (I) : Annexure 8/3 and 8/3A indicate the distance at
which these are to be fixed.
The following new sub-para 2 (a) along with Annexure 8/3
is to be added to para 808 :-
2(a) Multi Speed
Restriction (i.e. existence of two or more than two speed restrictions in
continuation) : When work of deep screening or sleeper renewal is in progress,
there is situation of having two or more than two speed restrictions in
continuation. In such situation,
placement of speed boards for following speed restriction shall be as under :-
(i) In case of
following speed restriction being more restriction, a minimum of 200m track
should be under earlier speed restriction zone.
If not, then only one SR board should be provided, considering that the
previous speed restriction is at par with the following SR, which is more
restrictive.
(ii) In case of
following speed restriction being less restrictive, corresponding speed
indicator board for following speed restriction shall be placed at a distance
equal to the length of the longest goods train operating on the section after
termination point of previous speed restriction zone.
Existing sub-para 2 or para 808 shall be renumbered as
2(b) and modified as under :-
2(b) The details
and position of fixing each indicator are detailed in Annexure-8/4, 8/3 and
8/3A.
ADVANCE CORRECTION SLIP No. 36 Dated. 24.08.1999
The para
503 of IRPWM 1986 may be replaced with the following:
Alumino thermic Welding of rails :
Alumino
Thermic Welding of rails may be carried out in accordance with the detailed
procedure laid down in the Manual for Fusion Welding of Rails by Alumino
Thermit Process, September 1996. A
thermit weld done in situ shall be joggle fish plated with four clamps and
supported on wooden blocks till tested as good by USFD.
The following may be added as para 127(3)
:
Quality of welding
and avoidable fractures :
The direct
responsibility for quality of AT welding being done in the section shall rest
on the PWI incharge of the section.
Responsibility for avoidable fractures taking place in the section shall
also rest with the PWI incharge of the section, except in cases where the USFD
testing was done and found good upto three months before the fractures.
ADVANCE CORRECTION SLIP No. 35 Dated. 19.08.1999
(Bd's Lr.No.99/CE-I/LX/80 dtd. 19.9.99)
The
existing para 901 of Chapter IX of IRPWM, 1996 be modified to read as follows
:-
901 General Location : As far as possible, new level crossing
should not be located in Marshalling yards/Station yards within Station limits
from safety and operational considerations.
Efforts should be made to shift the existing level crossings, which are
within station limits to the locations outside station limits. During planning of gauge conversions, yard
remodelling and doublings, the planning of the yard should be such that in case
any manned level crossing falls within the station limit, its operation from
the cabin should be possible and this should form part of the main work.
The
existing part 910(4)(c) of chapter IX of IRPWM -1986 be modified to read as
under :-
910(4)(c) : "Height
Gauges should be located at a minimum distance of 8 metre from gate posts. In exceptional circumstances where site
condition do not permit. Chief Engineer
can give exemption in these standards subject to a minimum of 8 metre distance
from the centre line of the track. Road
surface upto this point may be at the
same level as the road surface inside the gate posts."
The existing sub para 919(2) and 919(5) of IRPWM - 1986
should be deleted.
Sub item (iii) under Column (5) and (6) of item No.9(a)
of Annexure-9/1 of IRPWM - 1986 should be deleted.
The new para no.924 may be added to chapter IX of IRPWM -
1986 to read as under :-
924. Provision
of New Level Crossings/Manning/Demanning/Elimination:-
(a) Provision of the new level crossings : If, provision of new
level crossing is inescapable, then only manned level crossing is to be
provided. This is applicable to all existing lines, new constructions and gauge
conversions. However, these instructions are not applicable in case of private
sidings.
(b) Manning of Unmanned Level Crossing :
(i) Based on traffic density,
visibility and regular plying of buses etc., unmanned level crossings have been
categorised into I-V categorised for manning at Railway's cost in a phased
manner on a programmed basis as per following priority.
Category-I :Level Crossings
where the Train Vehicle Units
(TVUs) exceed
10000.
Category-II :Level Crossings
where TVUs exceed 6000 and
where visibility is
restricted.
Category-III : Level Crossings
where TVUs is less than 6000 and
visibility is
restricted but buses, motor vehicles
do not ply
regularly.
Category-IV : Level
Crossings where TVU is less than 6000 and
visibility is
restricted but motor vehicles
do not ply.
Category-V : Level crossings where visibility is
adequate but
traffic density
exceeds 6000 TVUs.
(ii) All
unmanned level crossings on Rajdhani and Shatabdi routes where maximum
permissible speed is 120 Kmph or more should be manned on priority.
(iii) For
manning of unmanned level crossings with traffic density more than 10000 TVUs,
Board's approval is not required.
However, in all other cases Board's sanction is required.
(c) De-Manning/Elimination of the Level
Crossing : The existing manned level crossings should not be demanned. However, the detailed review/survey of the
existing level crossings both manned and unmanned to be carried out with a view
to eliminate them by either passing the road through an existing bridge or by
constructing link roads to combine two or more level crossings etc.
A new para no.925 may be added to
chapter IX of IRPWM - 1986 to read as under :-
925. Criteria for replacement of existing level
crossings (other than those provided on `deposit terms') with Road Over/Under
Bridges on cost sharing basis :
(1) Minimum
Train Vehicle Units on a Level Crossing should be 1 lakh per day to become
eligible for replacement with Road Over/Under Bridges on `Cost Sharing'
basis. However, this could be relaxed in
the following cases :-
(a)
Suburban sections having high frequency of train services; and
(b)
Near stations where detentions to road traffic are very high on account of
either shunting operations or multi-directional recepit/despatch of trains or
stabling of trains etc.
(2) Preference
should be given to the Level Crossings located on trunk routes vis-à-vis those
located on branch lines. In any case,
minimum number of times the level crossing is required to be closed against the
road traffic should atleast be 12 times per day.
(3) Subject to
(1) and (2) above, priority should generally be accorded by the concerned State
Government giving preference to Level crossings on National Highways.
(4) In case of
Road Over/Under Bridges constructed in replacement of busy level crossings
situated in Municipal/Corporation/Metropolitan areas where Light Vehicular
traffic is considerable and where the Railways are satisfied that closure of
the level crossings would cause hardship, additional provision may be made for
construction of the sub-way or a light Over Bridge with ramps for the use of
light vehicular traffic at the time of framing the proposal for the
construction of Road Over/Under Bridges.
The proposals for providing the ramps/sub-way should be examined
critically and should be provided for only in the case of genuine hardships and
not as a matter of course. The cost of these
ramps/subway will be shared equally with the Sponsoring Authority on 50:50
basis.
(5) Closure of
the Level Crossings should be ensured before commissioning of the Road
Over/Under Bridges. All such cases where
State/Local Authorities do not agree to abide by this should be reported to the
Railway Board promptly.
ADVANCE CORRECTION SLIP No. 34 Dated. 06.08.1999
In
continuation of par 252(3) of Indian Railway Permanent Way Manual, 1986, part
252(4) may be added as follows :
252(4) USFD Testing of Service Rails :
No rail
untested by USFD shall be laid in the track whether for new lines or layouts or
renewals or for repair works or even temporarily such as service rails for PQRS
work. For repairs and casual renewals, a location-wise imprest of tested rails
of various lengths (13m, 9m, 6m) shall be prescribed for each PWI by
Sr.DEN/DEN.
In
continuation of par 502 (4), provided in the Manual, para 502(5) may be added
as follows :
502(5) Joggling of in-situ thermit welds :
A thermit
welding done in-situ shall be joggle fishplated with 4 clamps and supported on
wooden blocks till tested as good by USFD.
ADVANCE CORRECTION SLIP No. 33 Dated. 06.08.1999
(Bd's
lr.No.99/CE-I/LX/80 dtd. 6.8.99).
A new para no.922 may be added to chapter IX of IRPWM-1986 to read as under
:-
922. Manning of
the unmanned Level crossings through Member of Parliament Local Area
Development Scheme (MPLADS) : (1) The manning of unmanned Level Crossings has
been included in the list of works covered under Member of Parliament Local
Area Development Scheme (MPLADS). The
funds for capital cost of construction covering the cost of road, provision of
lifting barrier, arrangement of water and electricity, quarters for the
gatemen, duty hut etc. will be provided by Member of Parliament from MPLADS
Fund and recurring maintenance and operation cost will be borne by the
Railways.
(2) Unmanned
level crossings equal to number of level crossings manned through Member of
Parliament Local Area Development Scheme, will be converted into manned level
crossing at Railway's cost as selected in consultation with Member of
Parliament concerned.
(3) Preferably,
selected unmanned Level Crossings, should fall in the category I-V with
priority given to Level Crossings falling in Category-I followed by
Category-II, III, IV, V. For Level
crossings falling in the same category on different routes, priority shall be
given to A route followed by B, C, D-Spl., E-Spl, D and E-routes.
(4) Divisional
Railway Managers will liaison with the District Authorities and the Hon'ble
Member of Parliaments in selecting the Level Crossings for manning. On identification of the Level Crossings,
Member of Parliament will send his recommendations to the District Magistrate/
Dy.Commissioner for releasing the funds.
Railway will provide an estimate for the work and any other details to
the District Administration as required.
Departmental charges shall not be levied on these works and supervision
and establishment charges will be kept to the minimum as provided in the case
of similar Railway works. Separate
accounts shall be maintained for each work and `Utilisation Certificate' will
be submitted to the District Administration on completion of the work.
A new par No.923 may be added to Chapter IX
of IRPWM-1986 to read as under :-
923. Level Crossings on National Highways/State
Highways and Other Important roads. (1) In case of National Highway/State
Highways or their bypasses and important city roads, no new Level Crossing to
be provided and only grade separators can also be considered.
(2) In case of
other important roads, it is preferable to provide grade separators. However, depending upon the traffic density
envisaged, manned Level Crossings can also be considred.
(3) Relaxation
of the above (I) will require Board's prior approval.
ADVANCE CORRECTION SLIP No. 32 Dated. 04.08.1999
The
existing para 320(1)(a) may be replaced to read as under :
Classification and
use of released material.- (a) After a
section of track has been renewed, the released material shall be carefully
sorted out so that greatest possible use may be made of them. They should then be classified by the Sr.Section Engineer (P.Way). Tools and plant left over should also be
classified and action taken on their disposal.
A new para 320(3) may be added, as below :
(3) Accountal of released P.Way materials :
(1) The quantity of released materials from every work included for track
renewal/gauge conversion will be based on yardsticks for loss of weight to be
fixed on the basis of data collected during foot by foot survey. If there is more than one work on the same
route, near to each other and under similar ground conditions, only one set of
yardsticks would suffice.
2. List of
materials likely to be released will be prepared indicating the quantum of such
materials separately as second hand (SH) and scrap following the instructions
given in para 320(2) above.
3. While
second hand materials will be indicated only in length/nos. in case of scrap
materials, the accountal will be as follows :
(i)
Rails - in length, then converted to weight.
(ii)
Sleepers - Nos. separately as whole and in parts and then converted to weight.
(iii)
Fittings & fastenings - by weight.
4. During foot
by foot survey, actual observations will be recorded jointly by PWI and
ISA/Stock Verifier giving the percentage loss of weight over the new component
for each and every material likely to be declared as `SCRAP'. This can be done by actual weighment of few
representative samples.
5. The
yardsticks will then be approved by the Sr.DEN/DEN personally based on the
report duly test checked by AEN or DEN.
These will specify the maximum percentage loss of weight for different
components under different ground conditions as per format given in the
Annexure-3/1.
6. The
conversion to weight in case of each of the items for purpose of accountal will
then be done by the Section Engineer (P.Way) on the basis of the specified percentage
loss of weight over the new components.
In case, however, some abnormal variation of weight is observed after
the materials have been released and the percentage loss is more than that
specified for that category, specific justification will have to be recorded
for the same by the Senior Section Engineer (P.Way) and all such cases would
have to be certified by DEN/Sr.DEN after actual sample checking at site.
7. In case
however, the actual loss after release is seen to be lower than the yardstick
the accountal will be done on the basis of the actual.
8. After
actual releases of materials, the Section Engineer (P.Way) will take the
releases on books on the basis of summary sheet as per Annexure-3/2.
9. The
sectional AEN will carry out test checks to the extent of 20% of each item and
make entries to this effect in the summary sheet. The sectional DEN/Sr.DEN will also carry out
random checks to ensure that the category and weight of releases are correct to
the maximum possible extent.
10. The periodical
returns for track renewal/gauge conversions are to be submitted at the laid
down periodicity as per rules and the existing procedure for checking should be
streamlined to ensure that the returns are looked into detail in the AEN's
office in nos. as also their conversion in weight. The returns will be specifically prepared on
the basis of instructions given in para-2 above.
11. As an
internal check by the department, one of the works accountants in the division
with engineering department or with construction department should be made
responsible to carry out methodical checks of all MAS accounts of track
renewals/gauge conversion works.
12. In cases
where the track work is to be done by contractor, the list of released
materials shall be jointly prepared on the basis of field survey to be
conducted by the Sr.Sec. Engineer (P.Way) and contractors representative after
the work has been awarded but before the dismantling work is allowed to
commence. The contractor shall be bound
to hand over the materials according to the said agreed list and should be
responsible for any shortages.
Annexure-3/1
LOSS OF WEIGHT OF RELEASED SCRAP
(P.WAY COMPONENTS)
DESCRIPTION OF WORK : ______Railway
FOOT BY FOOT SURVEY CARRIED OUT BY : ______Division
DATE :
Sl. No |
Description of Material |
Weight of New item |
Max. % loss of weight
on release |
Weight of released item |
Remarks |
1 |
Rails |
|
|
|
|
2 |
SLEEPERS : (a)
(a) Steel (b)
(b) CST-9 (c)
(c) Wooden |
|
|
|
|
3 |
FISH PLATE |
|
|
|
|
4 |
TIE BAR |
|
|
|
|
5 |
OTHER FITTINGS (a)
(a) Bearing Plates (b)
(b) ACP (c)
(c) ERC (d)
(d) Two way key, other fittings |
|
|
|
|
ANNEXURE-3/2
SUMMARY OF P.WAY MATERIAL TO BE RELEASED.
NAME OF WORK_______________________________________________
DIVISION_________________SECTION_____________PWI____________
DEN/SR.DEN___________________________________________________
PERIOD OF EXECUTION OF WORK FROM (date) to (Date)____________
Km |
Category of section |
Name of material |
List of material to be released |
Remarks for abnormality if any |
Sign. of PWI |
Test check by AEN |
Remarks |
|||
Serviceable or scrap |
If scrap |
|||||||||
No/Length |
Rate (WT) |
WT |
||||||||
|
|
|
|
|
|
|
|
|
|
|
ADVANCE CORRECTION SLIP No. 31 Dated. 26.07.1999
(Bd's
lr.No.98/CE-II/TK/Misc.2 dt.26.7.99)
The
following changes may be made in the under-mentioned paras of IRPWM :-
Para 261 : The para shall read as follows :-
"Type
of ballast in use - Stone ballast shall be used on all lines including points
and crossings."
Para 262 : The following may be replaced in the para -
"With all types of sleepers 50mm gauge
of square mesh sieve.
Under points and crossings 40mm gauge
on square
mesh sieve."
With the
following :-
"As per specifications issued from
time to time."
Para 263(2)(a): The
notes under the recommended minimum depths of ballast below the bottom of the
sleeper at the rail seat shall read as follows :-
"Notes
:-
1.
In case of SWR the recommended depth is 200mm.
2.
Whenever primary renewals are carried out even on E routes, the minimum depth
of ballast of 200mm shall be provided.
3.
Minimum depth of ballast under the rail seat of the sleepers shall be 150mm
except under PRC sleepers where it shall be 250mm.
4.
Wherever 22.1 t Axle load rolling stock is nominated to run the minimum depth
of ballast shall be 350mm."
IRPWM C/S No.30 dtd. 7.7.99 (Bd's letter No.98/CE-II/TS/1/pt.
dt.7.7.99)
1.
The following may be added to para 202 (1) under Group B route:
(xvi)
Malda Town-Barsoi-New Jalpaiguri
2. The
existing line under Group C of para 202(1) be replaced to read as `Suburban
sections of Bombay, Delhi and Calcutta'.
Group D Spl. Sections
where the traffic density is very high or likely to grow substantially in
future and the sanctioned speed is 100 Km/h at present. The following routes will fall under this
category :-
(i)
Kharagpur-Midnapur-Adra
(ii)
Barkakana-Barwadih-Garwa Road
(iii)
Tundla-Yamuna Bridge
(iv)
Bolangir-Titlagarh
(v)
(v)
Gudur-Renigunta
(vi)
Anara-Chandil-Kandra-Sini
(vii)
Anuppur-Shahdol-Katni-Bina
(viii)
Ahmedabad-Viramgan
(ix)
Nagda-Ujjain-Maksi-Bhopal
(x)
Lucknow-Sultanpur-Zaffarabad-banaras
(xi) Delhi-Ghaziabad-Hapur-Moradabad
(xii)
Lucknow-Kanpur
(xiii)
Chapra-Hajipur-Barauni
(xiv)
RSD-Titlagarh-Vizianagaram
(xv)
Guntakal-Tornagallu
(xvi)
Udhna-Nandurbar-Jalgaon
Group E Spl : Sections
where traffic density is very high or likely to grow substantially in future
and present sanctioned speed is less than 100 Km/h, the following routes will
fall under this category :
(iii)
(iii)
Garwa Road-Sonnagar
(iv)
(iv)
Tornagallu-Hospet
(v)
Panskura-Haldia
(vi) Talcher-Rajatgarh-Salegaon-Nergundi
(vii)
Cuttack-Paradeep
(viii) Radhakishorepur-Rajatgarh-Barang
(ix) Kapilas
Road-Salegaon
(x) Radhakishorepur-Machapur
(xi) Kirandul-Koraput
(xii) Rajkharswan-Dongaposi-Padapahar-Barajamda-Gua
(xiii)
Bondamunda-Bimlagarh-Barsuan-Kiriburu
(xiv)
Kandra-Gamharia
(xv)
Champa-Gevra Road
(xvi)
Marauda-Dallirajhara
(xvii)
Urkura-Sarona
(xviii)
Bhojudih-Mohuda G-C
(xix)
Chandil-Muri-Bokaro-Rajbera
(xx)
Diwa-Vasai Road
(xxi)
Padapahar-Banspani
(xxii)
Jharsuguda-Bolanikhandan
(xxiii)
Muri-Barkakana
(xxiv)
Talgoria-Bokaro City
(xxv)
Kota-Ruthiyai
3. List of `Q'
routes at para 202(2)(a) be substituted with the following list :-
(i) Delhi-Sarairohilla-Rewari-Ratangarh
(ii)
Rewari-Ringus-Phulera
(iii)
Ratangarh-Degana
(iv)
Ajmer-Ratlam-Khandwa
(v)
Jaipur-Phulera-Ajmer
(vi)
Bandikui-Agra Fort
(vii) Ahmedabad-Bhavnagar
(viii) Agra-Mathura-Bhojipura-Lalkuan
(ix)
Bhojipura-Lucknow
(x) Villupuram-Thanjavur-Tiruchchirappalli.
5. The list of
R-1, R-2 & R-3 routes shown under para 202(2)(b) be replaced with the
following list :-
R-1 route :
(i)
Gandhidham-Palanpur
R-2 route :
1. (i) Secunderabad-Mudkhed
2. (ii) Guntakal-Bellary
3. (iii) Guntakal-Villupuram
4. (iv) Tiruchchirappalli-Manamadurai-Virudunagar
R-3 route :
1. (i) Madurai-Rameswaram
2. (ii) Virudunagar-Tenkasi
3. (iii) Dindigul-Pollachi
4. (iv) Ratangarh-Bikaner
Annexure 2/1 and
2/2 of P.Way Manual will
stand corrected accordingly.
ADVANCE CORRECTION SLIP No. 29 Dated. 07.07.1999
The
following may be replaced in supersession of Advance Correction Slip No.19
dated 18.11.98 Para 618 of IRPWM to read
as under:-
618
Portable Accelerometers :
(1) General :
OMS-2000
equipments are portable accelerometers used for Oscillation monitoring using a
portable accelerometer and transducers converting the oscillations to
electrical signals which can be recorded electronically and processed on PC.
(2)
Operation :
The OMS Accelerometer is kept in the cabin of locomotive
or on the coach floor, as close to the bogie pivot as possible. It is preferable that same coach and the same
vehicular position are used in successive runs.
The accelerations recorded are transferred to electronic recorder and
are readable on the LCD display on real time basis. The stored data can be downloaded on TMS
Computer for maintenance planning.
This equipment measures the Track Performance by
measurement of vehicle response in terms of vertical and lateral
accelerations. The real time output of
the equipment is in the form of value of peaks exceeding the limiting value,
their location and Ride Index. These
values are available for both vertical and lateral accelerations.
(3)
Frequency of Recording :
A. Broad Gauge :
Speed above 100 Kmph Once
every month.
Others Once in two months.
B. Metre Gauge :
Speed above 75 Kmph. Once
every month.
Others Once
in two months.
The above
schedule is only a guidance. Chief
Engineers may vary it, depending upon the availability of instrument and its
use. For the time being A, B and C
routes are to be covered once a month and other routes can be covered as per
capacity and need.
(4)
Recording of Defects :
To access the track quality, vertical and lateral
acceleration peaks exceeding the values as below are to be considered :
Broad Gauge :
High Speed Routes above 110 Kmph greater than 0.15 g
On A & B routes
Other Routes upto 110 Kmph greater than 0.2 g
Metre Gauge greater than 0.2 g
(5)
Classification of Track Quality :
To classify a continuous section's (PWI's
jurisdiction/sub-division/division) track quality, the following criteria to be
used (average total number of peaks per km.):
Very Good Good Average.
High Speed Less
than 1.0 1 - 2 Greater than 2
Others Less
than 1.5 15-3.0 Greater than 3
The above
criteria are for judging the quality of track.
However, if the average number of peaks of vertical and lateral
accelerations exceeding 0.30g is more than 0.25 per km. or more than one in any
particular kilometre, the track will need attention. All locations where peaks of lateral and
vertical accelerations exceed 0.25 g, the track will have to be attended to
urgently.
ADVANCE CORRECTION
SLIP No. 28 Dated. 07.07.1999
The existing contents of para 252(3) along with Annexure
2/9 of IRPWM 1986, may be deleted and substituted with the following :-
(3) Reference to
Manual for Ultrasonic Testing of Rails and welds, August-1998.
Detailed instructions for Ultrasonic Testing of Rails and
welds are contained in the Manual for Ultrasonic Testing of Rails and Welds,
Auigust, 1998 which may be referred to as an Annexure to this Manual. It is very important that instructions
contained thereon are carefully studied by the Permanent Way Officials
connected with the laying and maintenance of track.
The frequency for USFD testing of rails in service on A,
B & D routes of BG (keeping in view the traffic density and speed) is given
in the table below :
Route |
Frequency |
|
(a) (I) A,B & D routes of BG |
After passage of 8 GMT subject to a Maximum interval of six months as per
table below : |
|
|
GMT |
Testing frequency |
|
|
|
|
Upto 15 GMT |
6 months |
|
15-30 |
4 months |
|
30-45 |
3 months |
|
above 45 |
2 months |
|
|
|
(ii) If in a kilometre total REM & IMR defects detected and actual
fractures exceed 1 per km between two successive testing. |
The frequency which caused defect generation rate more than 1 per km.
should be doubled. |
(b) For other
section (C & E of BG and MG sections) Chief Engineers may apply this
frequency at their discretion or continue with conventional frequency of
testing.