Sound all the tanks. |
![]() |
Determine compartment flooded. |
![]() |
Determine cause of flooding. |
![]() |
Start bilge pump, portable welden pumps to pump out water from the flooded compartment. |
![]() |
Asses rate of flooding. |
![]() |
Check ship’s damage stability condition and loss of buoyancy. Refer to damage stability booklet. |
![]() |
Determine reserve buoyancy, change in GM, trim, list. |
![]() |
As per damage control plan, follow counter measures to control flooding. |
![]() |
Keep monitoring soundings at regular intervals. |
![]() |
Contain any oil spill, activate SOPEP in case of any oil spill. |
![]() |
Transmit distress/urgency message as necessary if situation is uncontrollable. |
![]() |
Proceed to a port of refuge if necessary and unsafe to continue voyage. |
![]() |
Inform owner, charterer, P&I club, MPA. |
![]() |
Inform port control/VTIS if necessary. |
![]() |
Log down all timings, corrective actions taken.