Project Start Date: Tue 12/29/98
Project Finish Date: Wed 5/12/99
| 1 | Start Project | |||||
| 2 | Initiating tasks | 1 | ||||
| 3 | Initial meeting with project sponsor | 1 | Kathy[50%],John[50%],Mary[50%] | |||
| 4 | Research similar projects | 3 | John | |||
| 5 | Draft project requirements | 4 | Kathy[50%],John | |||
| 6 | Review with sponsor and other stakeholders | 5 | Kathy[50%],John[50%],Mary[50%] | |||
| 7 | Develop project charter | 6 | Kathy | |||
| 8 | Charter signed | 7 | ||||
| 9 | Planning tasks | 8 | ||||
| 10 | Develop WBS | 8 | Kathy[25%],John[25%],Mary[25%],Chris[25%] | |||
| 11 | Estimate durations | 10 | Kathy[25%],John[25%],Mary[25%] | |||
| 12 | Assign resources | 10 | Kathy[10%] | |||
| 13 | Determine task relationships | 10 | Kathy[10%] | |||
| 14 | Enter cost information | 10 | Chris[50%] | |||
| 15 | Review Gantt and PERT chart information | 13 | Kathy[25%] | |||
| 16 | Review plan with stakeholders | 11,12,13,15 | Kathy[25%],John[25%],Mary[25%],Chris[25%] | |||
| 17 | Executing tasks | 16 | ||||
| 18 | Analysis tasks | 16 | John[75%] | |||
| 19 | Design tasks | 18FS-10 % | Mary[75%] | |||
| 20 | Implementation tasks | 19FS-3 days | Mary[75%],Chris[75%] | |||
| 21 | Controlling tasks | 8 | ||||
| 22 | Status reports | 8 | Kathy[10%] | |||
| 23 | Status reports 1 | |||||
| 24 | Status reports 2 | |||||
| 25 | Status reports 3 | |||||
| 26 | Status reports 4 | |||||
| 27 | Status reports 5 | |||||
| 28 | Status reports 6 | |||||
| 29 | Status reports 7 | |||||
| 30 | Status reports 8 | |||||
| 31 | Status reports 9 | |||||
| 32 | Status reports 10 | |||||
| 33 | Status reports 11 | |||||
| 34 | Status reports 12 | |||||
| 35 | Status reports 13 | |||||
| 36 | Status reports 14 | |||||
| 37 | Status reports 15 | |||||
| 38 | Status reports 16 | |||||
| 39 | Status reports 17 | |||||
| 40 | Enter actuals | 8 | Chris[5%] | |||
| 41 | Review reports | 8 | Kathy[5%] | |||
| 42 | Adjust plan, if needed | 8 | Kathy[25%] | |||
| 43 | Closing tasks | 20 | ||||
| 44 | Prepare final project report | 20 | Kathy,John,Mary,Chris | |||
| 45 | Present final project to stakeholders | 44 | Kathy,John,Mary,Chris | |||
| 46 | Prepare lessons learned | 45 | Kathy[25%],John[25%],Mary[25%],Chris[25%] | |||
| 47 | End Project | 46 |