New Home Construction...


 
View the construction at various stages
by selecting an 'As Of' Date below:

Perspective Views:
view the construction at various stages
from various perspectives:


04/02/2000 - Foundation


Kitchen


04/08/2000 - first floor framed

Soon to follow:
Family Room
Deck
Front
Side Perspectives

04/16/2000 - Second floor framed


04/23/2000 - Garage framed


04/29/2000 - Roof completed


05/07/2000 - Electrical and Plumbing completed


05/21/2000 - Siding started


05/27/2000 - Siding completed, trim and pediments installed


06/10/2000 - Deck completed, interior primer paint


06/16/2000 - Deck completed, Cabinets installed, some lighting fixtures installed