![]() After leveling the ground and putting up the forms and running the gas and electric lines, they called in the cement mixer. |
The crew getting the cement nice
and level.
|
![]() They combined the 'RV' hard stand and the BBQ patio in one pour. |
Laying the first row of bricks
for the wall.
|
The wall is going up. |
Here is the completed wall. The next thing we had to do is texture the patio to look just like the surface that goes around the pool. |
We had the area around the pool power washed and then they put douw a 'stain and sealer' and the surface |
of the patio was textured and
stained and sealed the same color. The next thing that has to be done is to have a nice BBQ work station installed. Something like the one I built in Pacifica but nicer. One task that I actually did was to re-run the down spout from the roof. I had to run it over the wall so the water would drain to the street. Can't wait to get the BBQ in.
|