Parish Center Construction Updates

As you all should be aware of by now construction is slated to begin on the new Parish Center sometime in the early fall.

Once the present Parish Center has been taken down and until the construction is completed, there will be several changes needed in regards to parking and access to the Church and/or school building.
We will post any details regarding Religious Education here as soon as we are made aware of them.

One of the major issues affecting us will be the entering and the dismissal of the children from Religious Education classes. We are working on a plan to ensure the safety of all the children. When it has been finalized we will let you know.
We are sorry for any inconvenience that may occur but please bear with us. As for now, we ask for your cooperation and prayers for the parish as we start this wonderful project.
Any questions please give the office a call 781-483-1139.
******
Please also continue to check the Parsih bulletin for progress reports from Father Toomey.
August 15, 2009
(Feast of the Assumption)

It has started-- the first phase for the replacement of our new Parish Center. Last week the shrubs/trees that needed to be removed was completed. A safety fence has been put up to secure the constuction site. Demolishtion of our old Parish Center is slated to be completed before Labor Day and the resumption of activities at the Parish.
August 24, 2009

The equipment arrived over the weekend. Today is the first day in the demolition of the old Parish Center.  By the end of the day the center was a mass of rubble and fond memories.
August 31, 2009

The debris has been taken away and in place of our old Parish Center now sits a big hole. This will remain for a couple of weeks until construction starts. You may ask why the center was taken down before construction was due to begin--the answer is, that it was felt best to have the demolishtion done before the traffic of people returning from vacation and school starting, thus lessening any inconvenience.
October 1, 2009

The plans are progressing. The contractor has been hired. The next phase will be testing and preparing the site. The Capital Campaign (fund raising) is underway and off to a great start. Please consult the bulletin for dates of receptions being held this month.