Major Causes of
Software Project Failures
Lorin J. May Crosstalk Associate Editor
Most software projects can be considered at least
partial failures because few projects meet all their cost, schedule,
quality, or requirements objectives. Failures are rarely caused by
mysterious causes, but these causes are usually discovered
post-mortem, or only after it is too late to change direction. This
article is based on interviews with software consultants and
practitioners who were asked to provide "autopsies" of failed projects
with which they have been acquainted. Although not a comprehensive
compilation of failure causes, this article outlines several areas
that should demand your attention.
few years ago marked the rollout of what could have
been called a Titanic of military projects, except the original Titanic
was ahead of schedule when it sank. Hundreds of millions of dollars over
budget and years behind schedule, the first phase of this huge military
system was finally "tossed over the wall" and over the top of a network of
separate programs used by thousands of practitioners. Although long
hampered by quality problems, big hopes were again riding on the system
once it passed acceptance testing. The
intended users refused to use the system. It lacked features they said
were essential to their jobs while requiring steps they considered
unnecessary or burdensome. The project eventually died a visible, painful
death amid litigation and congressional inquiries.
This failed project was not atypical of
chronic problems in the software industry. According to the Standish Group
[1], in 1995, U.S. government and businesses spent approximately $81
billion on canceled software projects, and another $59 billion for budget
overruns. Their survey claimed that in the United States, only about
one-sixth of all projects were completed on time and within budget, nearly
one third of all projects were canceled outright, and well over half were
considered "challenged." Of the challenged or canceled projects, the
average project was 189 percent over budget, 222 percent behind schedule,
and contained only 61 percent of the originally specified features.
Other studies have likewise concluded that
failure is rampant, although not necessarily to the same degree. One
reason for the varied conclusions is that most failed projects are never
studied—even by the organization that experienced the failure. Having
wasted so much on a fruitless venture, few organizations will invest more
time or money to collect and analyze additional data, whereas any data
that had been collected may be massaged or hidden to protect careers or
reputations. Thus, information about project failures often relies heavily
on subjective assessments. This article is no exception.
For this article, a failure is defined as any
software project with severe cost or schedule overruns, quality problems,
or that suffers outright cancellation. It is based on interviews with
practitioners and consultants who were asked to describe the causes of
software project failures with which they have been acquainted. If there
is anything notable about the interviewees' diagnoses, perhaps it is that
many of these problems have been documented for years, but somehow they
keep cropping up. Also worth noting is that most of the failure causes
mentioned originate before the first line of code has been written. The
failure causes are listed in no particular order.
Poor User Input
Although the Titanic project mentioned earlier was riddled with
problems, it ultimately failed because the system did not meet user needs.
According to Paul Hewitt, a consultant with the Software Technology
Support Center (STSC), the acquirers and the developers of this system had
received most of their requirements from higher-level supervisors and
so-called "users" who were not regularly using the existing system.
Although "not invented here" syndrome contributed to the system's eventual
lack of acceptance, the bottom line is that the system was inadequate for
its environment. By contrast, Hewitt has
observed successful programs in which "end users and developers [were]
working together in the same cubicle." Although this is not always
possible, Hewitt said projects are likely headed for trouble unless
informed end users are giving meaningful input during every phase of
requirements elicitation, product design, and building. The input needed
by these users has less to do with issues like screen layouts than with
how the system would be used in the field, according to Michael Allen
Latta, chief executive officer of Ohana Technologies Corp. in Lafayette,
Colo. He said the user should be asking, "How do I use it over time? Does
it provide the right tools? What do I put into it, and what do I get out?"
However, there can also be problems if the
users are too close to the requirements. Shari Lawrence Pfleeger,
president of Systems/Software in Washington, D.C., had just started
consulting on a large federal system acquisition when she started to study
its requirements, which were supposedly "clean" due to the input of highly
knowledgeable users. Even without any prior understanding of the system or
its field environment, Pfleeger needed only a few hours to see that the
requirements were full of hidden assumptions and conflicts.
"[The users] didn't think of the consequences
of what they were requiring," she said. "They assumed that how things were
done in the past was how they would always be done in the future." The
users assumed the elicitors understood more than they did about the users'
jobs, but this was not entirely the users' fault. All involved
parties, including the developers, must understand the business of the
other parties. This need continues throughout development process. Without
this understanding, the parties "don't even know what questions to ask,"
Pfleeger said, and important issues fall between the cracks.
Stakeholder
Conflicts A few years ago, a major airline, rental car
company, and some hotel chains created an incentive plan to give customers
frequent flier-type points to "cash in" for any of the participating
companies' services. They commissioned a complex software system to track
points and compensation. Sometime later, the software developers needed
some clarifications, i.e., with input A, does the system choose X, Y, or
Z? The stakeholders could not agree on the answers. Forced to acknowledge
deep incompatibilities among their business interests, the system was
canceled in an expensive, litigious failure of the entire enterprise.
The stakeholders had worked under "the
illusion that everyone was going to get everything that they wanted,"
explained Tom DeMarco, principle of the Atlantic Systems Guild. They
"papered over their differences" rather than going through conflict
resolution in the early stages. Their differences were exposed by the
developers because "coders cannot make an ambiguous system."
Stakeholder conflicts can play many different
roles project failures. For example, "some projects are ultimately
canceled because people don't like each other," said Capers Jones,
chairman of Software Productivity Research, Inc.
Other projects fail because the developers do
not know who the "real" stakeholders are, according to Ed Yourdon,
chairman of the Cutter Consortium. Yourdon worked with a large mutual fund
company that had been working on a $300 million software system. The
developers had been working closely with the information technology vice
president, who was perceived to be the primary stakeholder for the system.
When the system ran into some problems, it drew the attention of the chief
executive officer, who turned out to be the real stakeholder in the system
even though he had not previously been involved with it. After seeing the
involved risks, he immediately withdrew his support for the system.
"No one bothered to ensure that he was going
to support it," Yourdon explained. "No one made him aware of problems
while it was being developed." Yourdon says many projects fail because the
project leaders do not have a sense of who will ultimately declare whether
a project is a success or failure, and then they are "blindsided." He said
the true stakeholders need to hear good and bad news in "small pieces"
rather than in "one chunk." Other projects,
especially smaller projects within larger projects, never go anywhere
because the internal stakeholders never agree on priorities. Watts
Humphrey, a fellow at the Software Engineering Institute, calls these
"pretend projects," meaning a few developers work on them half time or
quarter time, and nothing is ever delivered.
"They are kidding themselves that they are working on [these projects],"
Humphrey said. "No one can work quarter time on a project. … They haven't
faced the need as a management team to decide what they are really going
to do with it. They need to put real resources on it" rather than merely
pretend the project is under way.
Vague
Requirements Mariea Datiz, president of Peripheral Visions
in Houston, Texas, learned a hard lesson about what happens when a project
is started while the requirements are nebulous. The U.S. division of an
oil company hired Datiz's company to create the "first draft" of a program
so that they could impress their European counterparts and justify further
funding. But the oil company officials only had a general idea of what the
program was to do and tried to revise and refine their ideas while Datiz's
company was working on the program. "For
every step we would take, we'd go three backward," Datiz said. "We would
start down one path and then have to stop and go down another." Project
cost and quality quickly went out of control, her company was blamed, and
she lost the contract to finish the job. Like many failed projects, the
scope had not been narrowed enough at the outset to have led to any
reasonable chance for success. One obvious
solution is to establish a reasonably stable requirements baseline before
any other work goes forward. But even when this is done, requirements will
still continue to creep. "You can't design a process that assumes
[requirements] are stable," advises Humphrey. In virtually all projects,
there will be some degree of "learning what the requirements really are
while building the product," he said. Projects could be headed for trouble
if architectures and processes are not change-friendly, or if there are
poorly established guidelines that determine how and when requirements can
be added, removed, and implemented—and who will shoulder the cost of the
changes.
Poor Cost and
Schedule Estimation It is unfair to call a project a
failure if it fails to meet budget and schedule goals that were inherently
unattainable. Like all engineering endeavors, every software project has a
minimum achievable schedule and cost. Fredrick Brooks summarized this law
in The Mythical Man Month [2] when he stated, "The bearing of a
child takes nine months, no matter how many women are assigned." Attempts
to circumvent a project's natural minimum limits will backfire.
This problem occurs any time someone "makes
up a number and won't listen to anyone about how long other projects
took," said Jones. According to DeMarco, projects are often intentionally
underbid because of the "attitude that putting a development team under
sufficient pressure can get them to deliver almost anything."
The opposite is what usually happens. For
example, if a program should realistically take five programmers one year
to complete, but instead you are given four programmers and eight months,
you will have to skimp on design time and on quality checks to reach
project milestones. "Cutting a corner that
undermines the entire foundation of the project is not cutting the
corner," states Robert Gezelter, a software consultant in Flushing, New
York. "There will be heavily disproportionate costs downstream." Skimping
leads to weak designs, dramatically higher defect densities, much more
rework, and virtually endless testing. In the end, the project will cost
more, take longer, and have worse quality than would have been possible if
a realistic schedule and budget had been followed.
According to Jones, this problem can be
easily remedied. Several estimation tools on the market can combine
numerous variables to provide realistic estimates within a few hours [3],
even at the early critical decision-making junctures—before requirements
are firm.
Skills that Do Not
Match the Job Decades ago, Morris Dovey, information
director for Check Control, Inc. in West Des Moines, Iowa, worked on major
government software contracts before becoming so frustrated he decided to
never work with government contracting again.
"It was being made artificially difficult," Dovey said. The technologists
had to endure what he considered avoidable delays and mistakes because
"decisions were being made by people with no technical expertise in the
area" but had all the authority. Latta warns
that managers can perform poorly if they lead projects that do not match
their strengths. "Projects dealing with high technology need managers with
solid technical skills," Latta advises. In such projects, authority must
reside with people who understand the implications of specific technical
risks. However, the best technologists are
not necessarily always poised to be the best managers. "The skill set for
management and programming are disjoint," Jones observed. The larger the
project, the more need there is for people with excellent planning,
oversight, organization, and communications skills; excellent
technologists do not necessarily have these abilities.
Skill-driven challenges are not limited to
management. Poor developers can sap productivity and make critical,
expensive errors. Generalists can also poorly perform duties better left
to specialists, such as metrics experts or testers.
The solution to skill-driven challenges is
easy to define but difficult and expensive to accomplish: Attract and
retain the most highly skilled and productive people. "Knowledge is
money," noted Tom Pennington, senior network manager for The MIL
Corporation in Arlington, Va. However, there is an eventual payback.
Pennington believes a team made up of higher-paid people with the right
specialized skills is worth far more per dollar to an organization than a
group of lower-cost people who need weeks or months of fumbling through a
new process or technology before they can start being productive.
"You get what you pay for," Datiz echos.
"You'll also pay for what you get." Jones
advises that "if you can't get the best `techies,' get the best managers."
He said good managers can often get above-average results from average
employees, whereas great employees can have much of their potential
squandered by mediocre management.
Hidden Costs of Going
"Lean and Mean" DeMarco believes project managers and
technologists are often unfairly blamed for problems caused by people "two
levels higher." He believes managers and technologists are generally
competent and getting better every year, but they are "goaded" into
overtime work because of "the 1990s stupid flirtation with lean and
mean"—cutting jobs and expecting the same work with fewer people and less
money, whether such a feat is possible or not. DeMarco says the the
often-intentional "dishonest pricing" of projects is often off by a factor
of two or four or more, requiring never-before-seen levels of performance.
"Any failure will be viewed as a direct
result of underperformance," he charges, even though underperformance is
"not even a significant factor" in the failure of most projects. Instead,
he says, the failed projects simply had goals that were inherently
unattainable. Humphrey has observed a
different "lean and mean" problem. In many "downsized" organizations, he
says, developers are doing their own expense accounts, clerical work,
software updates, and other duties—and at a higher labor rate and with
less skill than could be performed by support specialists.
He estimates that many software developers
are spending half their work hours slowly plodding through tasks that have
nothing to do with developing software. "Software people are very
unskilled clerks," he said. "It's an enormous productivity issue."
Failure to Plan
Humphrey took charge of commercial software development for IBM
at a point when the company was taking too long to finish projects and was
missing all its announced deadlines. "People were working hard, but no one
had plans ... because no one required them to make plans," Humphrey
recalls. In response, he required that a detailed plan be developed before
any release date was announced. For the next two and one half years, the
division never missed an announced date. "If
software developers built bridges, we'd show up at the site with some
scrap iron and say, `let's start building!'" quipped Reuel Alder, a
manager at the STSC. Alder agrees that inadequate planning is a major
reason software projects spin out of control.
Humphrey said project managers often do not plan because "any plan they
put together won't meet the [desired release] date, so they can't plan."
Even though detailed planning saves an enormous amount of time in the long
run, Humphrey says many other managers and developers believe it to be
unnecessary. "They think time spent on things like planning, design,
requirements, and inspection gets in the way of real work, which is coding
and testing," he said. "This comes from the view of programming that the
issue is to get the software out the door. But there's a difference
between speed and progress." "We need a lot
fewer heroes," adds Gezelter. He believes organization "heroics" would
frequently be unnecessary if projects had been properly planned. "We keep
rewarding people for charging off on suicide missions," he said.
Communication
Breakdowns When Pfleeger was asked to consult on a large
project that was in trouble, she asked the managers to develop a process
model for the project. She did not necessarily want the model for her own
use, but wanted the managers to talk to the developers. Once they did,
they realized the project had gotten so large that the same code was being
tested by two teams that did not know the other existed.
Such problems are common on large projects,
especially if people are working at different sites. In many troubled
projects, "there isn't one person who has an overview of the whole
project," she said. Especially on large projects, Pfleeger advises that
additional time be taken periodically to have everyone in every position
learn the big picture. "The people working on the pieces need to know how
their one piece fits into the entire architecture."
Poor Architecture
Pfleeger says an example of flexible architecture is the
Patriot missile used during the Gulf War. It was not designed to intercept
scud missiles, but the software was able to be reconfigured to support the
new function. On the other end of the flexibility spectrum was a security
program created to protect sensitive word-processing documents. Everything
worked well for a few months until the operating system was updated. The
word-processing programs still worked, but the security program became
useless and unfixable because much of its code was tied to operating
system features that were dropped in the new system.
"People didn't think ahead about what was
likely to change," Pfleeger said. Architecture must allow for organization
and mission changes. Gezelter said software
developers often build with no more forethought than the man who built a
beautiful boat in his workshop and then could not get it out the door. "If
you do [architecture] right, no one will ever realize it," he said. "But
if you do it wrong, you will suffer death by a thousand cuts. Bad choices
show up as long-term limitations, aggravation, and costs."
Gezelter suggests viewing software
architecture like house-building: "Plumb" and "wire" for features and
additions you have not thought of yet. Then, when unanticipated needs or
business changes arise, you can add or modify without performing the
software equivalent of "ripping apart the walls and rebuilding them
again."
Late Failure Warning
Signals Does the following scenario by Yourdon seem
familiar? A schedule and budget are determined "by edict by people you
were afraid to say no to," and it is politically unwise either to say or
show the estimate is far from achieveable. All your early milestones
involve diagrams, designs, and other documents that do not involve working
code. These and other project milestones then go by more or less on
schedule—at least as far as upper management can tell—and testing starts
more or less on time. Not until the project is a few weeks from deadline
does anyone dare inform the "edict makers" that at the current defect
detection rate, the project will not be completed even close to its
deadline. "Nobody seems to acknowledge that
disaster is approaching," Yourdon said, even among people who sense there
is a problem. "There is no early warning signal." Until more organizations
abandon waterfall-style development in favor of processes that demand
early working code or prototypes, he says this scenario will continue to
be familiar. Yourdon says the above problem
is also extremely common with year 2000 work. He believes many year 2000
conversion teams, if they were allowed, would say of their current
situation: "Within this limited time and pitiful budget and understaffed
team, sure, we can deliver it on time—with a million bugs in it."
In a perfect world, lower-level people could
convince upper-level managers that their edicts are unworkable before the
project got under way. But until this happens, Yourdon says development
cycles need to be adopted that allow you, at the earliest possible moment,
to "provide evidence that [the project] is or is not working."
Conclusion
Other causes of failure could be added ad nauseam, but the
existence of additional factors is not the point. As Jones noted, "There
are myriad ways to fail. … There are only a very few ways to succeed." [3]
The factors of successful project management have been documented for
years—they merely need greater attention. But if this article has helped
serve as a reality check for your project, it will have served its
purpose. If you violate any of the principles noted by the consultants and
practitioners in this article, you should not expect to succeed in spite
of yourself.
About the Author
Lorin J. May is an editor and columnist for
Crosstalk: The Journal of Defense Software Engineering. He is
employed by NCI Information Systems, Inc., under contract to Crosstalk
at the Software Technology Support Center. He was previously an
editor for two book publishers and was a part-time freelance writer. He
has a bachelor's degree in journalism from Weber State University in
Ogden, Utah.
OO-ALC/TISE 7278 Fourth Street Hill AFB, UT
84056-5205 Voice: 801-777-9239 DSN 777-9239 Fax: 801-777-8069
DSN 777-8069 E-mail: MayL@software.hill.af.mil
References
- The Standish Group, "Chaos," 1995, http://www.standishgroup.com/chaos.html.
- Brooks Jr., Frederick P., The Mythical Man-Month (20th
Anniversary Edition), Addison-Wesley, Reading, Mass., 1995.
- Jones, Capers, Patterns of Software Systems Failure and
Success, International Thompson Computer Press, Boston, Mass., 1996.
|