| | The Week -- as Planned
Picture
of the front of the house with azaleas and lattice done
Picture of the front
porch with furnishings
Picture of Kitchen with
Ivy stenciling
Picture of the Breakfast
Room (from kitchen entrance)
Picture of the Breakfast
Room (from other entrance)
5-20-2001 |
Finished Coax installation in Family Room
Finished Spackling in several areas:
- Touched-up the entire main level
- Touched- up small areas in new bedroom levels
- Fixed the basement ceiling where the kitchen sink water leak came through.
Finished Sanding in several areas:
- Touched-up the entire main level
- Fixed the basement ceiling where the kitchen sink water leak came through.
Hannah soccer game
Ballet Recitals for Hannah and Suzy.
International Woodwind Ensemble Concert for Tim
|
5-21-2001 |
Finished planting zoysia plugs. Finished Sanding of touch up of
small areas in new bedroom levels
|
5-22-2001
|
Margaret put stenciling paint of ivy on the kitchen wall around the old
window area.
Finished putting the basement ceiling tiles back up.
|
5-23-2001 |
Added more pictures to web site
Finished caulking outdoors around new side door and along top of porch
brick/siding.
- Caulked base of new side door
- Caulked juncture between siding and brick along porch roof
Cleaned up top of new side porch door in preparation for painting.
|
5-24-2001 |
Finished most of touch-up painting of upper levels
|
5-25-2001 |
Finished touch-up painting of upper levels Planted a butterfly
garden where the big old silver maple tree was removed. Added 2
wheelbarrows of dirt and several flowers meant to attract butterflies, and
finished it off with mulch.
|
5-26-2001 |
Two Memorial Day Soccer Tournament games for
Hannah - only played one -- second one rained out and they re-scheduled
it for Sunday.
Declared
the home renovation project complete -- 5 months after the roof was
taken off, and 2 months after most of the the contractor work was done.
|
|