NEXT MEETING REGULAR MEETING IS Thursday October 7,1999:


Meeting opened at 7:35 PM;
Minutes read and accepted;
Treasurers repot read and accepted;
2 guest were present;
Rock and Gem show at Washington Fairgrounds Oct 1 to the 3rd;
NW mining Expo in Spokane on Nov. 28th, contact Hayden Piper for info;
Bob Schmaltz won the fishing pole raffle;
John Satoris won the 16.8 grain gold nugget drawing;
The 40 grains gold drawing was #937 (Jay Lord) Jay was present to win so it will be 50 grains in October;
Meeting Closed at 9:20 PM;
Clarence Mohr will give a talk on Power Sluice design a theory at the October meeting.

SCUBA UNLIMITED

is a diving shop at 8450 SE 82nd in Portland. They carry all underwater equipment for dredgers. If you show them your membership card they will give you a 10% discount.
Ron Williams is the owner of Scuba Unlimited, and he gave me some advice to pass along to you.
—If you get a hole in your wet suit do not patch it with aqua seal use a neopreme cement. A wet suit can not be repaired after aqua seal is used. His shop will repair suits and diving equipment, including hooka gear. He also said you should have you hooka gear seviced every year.

HYDRAULIC MINES OPERATING IN OREGON DURING 1932


(Mines without elevators)


Norton & Nelson
     Norton and Nelson operated a placer on Galice Creek near Galice during the 1932 season. The gravel averaged about 12 feet in depth and contained nearly 20 percent of boulders over 1 foot in diameter and very little clay. Bedrock consisted of slate of medium hardness; it was rough and had a grade of one half inch to the foot.
     Water was brought through a 1 1/2-mile ditch, 500 feet of flume, and 300 feet of 15-inch pipe. The effective head was 90 feet. The maximum supply was 1,000 miner's inches and the average 600; a minimum of 500 inches was required to operate the mine. During the 1932 season the gravel was cut with a no. 2 giant with a 3-inch nozzle and driven by a no. 2 giant with a 4-inch nozzle. Only one giant was used at a time. Most of the water supply was used as a bywash. The sluice boxes were 20 inches wide, 20 inches deep, and 10 feet long. Ten boxes were used; the grade was 3/4 inch to the foot. Hungarian and pole riffles were employed. Boulders were handled with a 2-drum gasoline hoist.
     The washing season in 1932 was 150 days; 12,000 cubic yards was washed. Two men operated the mine, and an average of 80 cubic yards was washed per day. The labor cost at $4 per shift would be 10 cents per cubic yard; supplies would amount to about 2 cents per yard, making a total operating cost of approximately 12 cents.
Salmon Creek
     An innovation in placer mining was being tried in July 1932 at the Salmon Creek mine near Baker by John M. Start. The boulders were removed from the pit by a gasoline-driven shovel with a 1/2-cubic-yard dipper. The gravel contained a large proportion of boulders and clay which made it hard to cut and wash. Insufficient water was available to wash enough gravel per shift to make the mine pay unless other means of handling the boulders were provided.
     A no. 2 giant with a 2 1/4-inch nozzle under a 150-foot head was used for cutting the gravel. Wash water coming over the bank assisted the water from the giant to transport the gravel to and through the sluice. As boulders were uncovered with the giant they were picked up in the dipper and cast to one side by the power shovel. When not otherwise occupied, the shovel was used in loosening the gravel. The power shovel had the ordinary type of dipper but was to be converted to a dragline with a clamshell or orange-peel bucket which would work to better advantage. One foot of gravel, which contained most of the gold, was left on the bedrock and at the end of a month's run was taken up and washed separately. The boxes were 26 inches wide and had a grade of 1 1/4 inches to the foot for 80 feet, then a grade of 1 inch to the foot for 100 feet. Riffles in the first 20 feet of boxes were iron rails placed lengthwise in the boxes, The next 60 feet were 4-inch pole riffles also set lengthwise. The function of the first 80 feet of riffles was to help break up the clay in the gravel. The lower 100 feet were Hungarian riffles made of 1 1/4- by 1-inch wooden cross strips iron-clad on top; the spacing was 1 1/2 inches between riffles.
     The operating crew consisted of 1 piper, 1 shovel operator, 2 sluice tenders on each of two shifts, and a superintendent on day shift. During each shift one of the sluice tenders was detailed to keep small boulders moving down and out of the boxes. About 130 cubic yards was washed each shift. The gasoline consumption on the shovel was 12 1/2 gallons per shift. With labor at $4 per shift the labor cost per cubic yard would be 12 cents; at 20 cents per gallon the gasoline cost would be 2 cents per cubic yard; other supplies and repairs would cost an additional 3 cents and supervision 3 cents, making a total operating cost of 20 cents per cubic yard. This does not include rental on the shovel, interest, or amortization of the plant.
Blue Channel
     The Blue Channel mine on Coyote Creek, near Wolf Creek was operated in 1932 by M. C. Davis. The deposit consisted of recent river grovels overlying an old blue channel. The channel, which contained most of the gold, was in a depression in the bedrock of the present stream bed; it consisted of cemented gravel, had a maximum depth of 10 feet, and was about 30 feet wide.
     Water was brought to the mine under a 560-foot head through a 4-mile ditch and 1,100 feet of 52- to 18-inch pipe. A 4 1/2-inch nozzle was used for cutting, and 5-inch nozzles were used on the giants for sweeping the gravel to the sluice. A giant with a 5-inch nozzle was used also for stacking the tailings. Two giants were used at one time, Figure 11,B, shows the set-up of giants for working the mine.
     The top gravel was first piped off, then the channel was worked by first blasting a trench lengthwise in the middle of a section of the channel. After one line of holes was blasted and the broken gravel piped cut, a second row in the bottom of the trench was drilled and shot. The remaining gravel of the section was then plowed up with the giant, breaking to the trench made by blasting. The cemented gravel was disintegrated while being swept to the sluices. The sluice boxes were 56 inches wide and had a total length cf 80 feet. A plank fence 12 feet high guided the gravel to the sluice at the end of the pit. Cross riffles made of 2- by 4-inch timber, clad on top by 7/16-inch strap iron and spaced 2 1/2 inches apart, were used. The operating crew consisted of 3 men, 2 in the pit and 1 at the reservoir. The reservoir held enough water for piping with two giants for 5 hours. The average piping time for two giants was 5 hours per day during the season, while at the end of the season only one giant could be used for 2 1/2 hours of piping. The crew worked on boulders while the reservoir was being refilled. The yardage handled and the days worked were not available.

(Mines with Ruble Elevators)


Browning
     The Macintosh brothers operated the Browning mine near Leland under a lease during the 1932 season. The gravel deposit was along a small creek and averaged about 12 feet deep. Preparatory to mining, a 5,000-foot pipeline from the Columbia ditch was laid. The pipe diameter ranged from 32 to 16 inches. This work took 90 days with an average crew of l0 men. Further construction consisted of the erection of a Ruble elevator. Actual washing operations were carried on for 35 days. Ten days were required when water was available to make a new set-up of the elevator. Water was brought to the mine under a head of 300 feet. Four hundred feet cf head was available, but the pressure was reduced 100 feet from the top. The mine was equipped with one no. 4, two no. 3, and three no. 2 giants; 4 1/2-inch nozzles were used on the cutting giant and the one at the Ruble elevator. A 5-inch nozzle was used for sweeping. The Ruble giant and one other were used at the same time. The Ruble elevator was 6 feet wide and 36 feet long and elevated the oversize 14 feet. The grizzly bars, which were set crosswise, consisted of 2- by 4-inch lumber clad on top with 1/2- by 2 1/2-inch strap iron. The spacing was three fourths inch. The gravel could be driven over the Ruble as fast as one of the other giants could get it to the elevator. A timber dam was built part way across the pit on either side of the Ruble to guide the gravel to the elevator. The sluice boxes were 4 feet wide and 22 feet long and had a grade of 7 inches to 12 feet. Standard dredge-type Hungarian riffles 1 1/4 inches wide by 1 inch deep were used.
     A total of 30,000 cubic yards was washed during the season. The average daily yardage was 667. The operating crew consisted of 6 men on two 12-hour shifts; 4 men worked on day shift and 2 on night. At $5 per 12-hour shift the operating cost per cubic yard would be 4 1/2 cents. The supplies amounted to another 1 1/2 cents, making a total operating cost of about 6 cents. The labor cost of putting in the pipeline amounted to 12 cents per cubic yard of gravel moved during the season.

(Mines with Hydraulic Elevators)


Liana de Oro
     The Liana de Oro mine was in a flat river valley near Waldo. The deposit consisted of small-size gravel and clay overlain with soil. Apparently it contained too much clay for successful dredging. The mine was worked during the 1932 season by five men under a royalty agreement. The mine was well equipped and contained a good stock of supplies at the beginning, of the season. Timber for sluice boxes was cut and sawed, on the premises at a cost of $8 per M.
     Water was brought to the mine in three ditches. The upper had a capacity of 520 miners inches and was used for bringing water to a hydraulic elevator. The effective head at the elevator was 360 feet. The middle ditch had a capacity of 1,800 inches and delivered water to the mine under an effective head of 125 Feet. This water was used for cutting and sweeping in the pit and for stacking the coarse tailings. The combined average flow of the two upper ditches was 700 inches. The lower ditch delivered 10,000 inches which was used in a long tailrace for carrying away the clay and sand.
     No. 3 giants with 3-, 3 3/4-, or 4 1/2-inch nozzles, depending upon the quantity of water available, were used for cutting and sweeping. A no. 2 giant with a 3-inch nozzle was used for stacking the tailings. The gravel as cut in the pat was run through 180 feet of 30-inch boxes, set on a grade cf 5/16 inch to the foot, to the hydraulic elevator. The lift of the elevator was 44 feet; the diameter cf the standpipe was 20 inches and that of the nozzle of the high-pressure jet 3 3/4 inches. A second elevator was used as a water lift. From the elevator the gravel ran through 700 feet of 30-inch boxes, the bottoms of which were lined with sheet steel. Riffles consisting of steel rails were used in the first 300 feet of the sluice; no riffles were used in the last 400 feet. The grade of the main sluice where the elevator discharged into it was 2 inches to the 16-foot box. As the velocity from the elevator was lost the grade was increased to 3 1/2, 4, and 5 inches to the box. An undercurrent was taken out at the end of the riffle section. The undercurrent grizzly was 36 by 36 inches in plan. The grizzly bars had a spacing of 1/4 inch at the top and 3/8 inch at the bottom. They were set crosswise to the sluice; if set lengthwise, however, they would not have clogged as easily with trash or grass that came down the sluice. Black sand had a. tendency to pack in the riffles of the sluice in the pit and thus reduced their ability to catch the fine gold. To overcome this difficulty the first two or three boxes were cleaned up daily. Two thirds of the gold saved was recovered in these boxes. Because of the fine size of the gold and the relatively large percentage of clay and black sand in the gravel it was estimated that only 60 percent of the total gold was saved.
     Preparatory work for the 1932 season began November 6, 1931 and consisted of repairing flume lines and cleaning out the ditches. Washing started January 1, 1932 and continued to June 20, when the high-pressure water for the elevator failed. During the washing season piping was done on an average of 22 days per month. An average of 400 cubic yards per day was handled after washing began; the daily average for the season was 300 cubic yards, and as much as 500 cubic yards was handled in a day. With labor at $3.75 per shift the labor cost for the season would be 7 cents; supplies cost 1 cent per cubic yard, making a total cf 8 cents. The costs do not include interest, depreciation, amortization, or general overhead expenses. The labor cost includes 3 1/2 percent for workmen's compensation.
Plataurica
     The Plataurica mine near O'Brien was operated during the 1932 season by Nelson and Harrison, lessees. The mine was fully equipped when they took it over. Water was brought through 11 miles of ditch and 4,000 feet of pipeline 22 to 15 inches in diameter. The branch lines at the mine were 11 inches in diameter. The head was 450 feet.
     The gravel was about 35 feet thick. It was fairly easy to wash and contained few boulders. As no fall was available the washed gravel was removed from the pit through a hydraulic elevator with a lift cf 54 feet. The throat diameter of the elevator was 18 inches; a 3 1/2-inch nozzle was used for the high-pressure water. One giant with a 3-inch nozzle was used for cutting the gravel and driving it to the foot of the hydraulic elevator. Usually two or three 16-foot boxes with block riffles were used in the Pit in front of the elevator. The tailings at the end of the main sluice were stacked by another giant with a 3-inch nozzle which was operated about 4 hours each day. When the tailings giant was in use the cutting giant was turned off.
     The hydraulic elevator discharged into 256 feet of 30-inch boxes set on a grade of 6 inches to 16 feet. When the grads were less it was found that black sand packed tightly in the riffles. The riffles in the upper part of the sluice consisted of 7-inch wooden blocks and those in the lower end of 4-inch angle irons set across the boxes. An undercurrent was used but did not recover enough gold to pay for cleaning it. The main sluice was cleaned up four times during the season. Two flasks of quicksilver were used during the season.
     Work for the 1932 season began November 10, 1931 and continued until June 25. The operating crew consisted of 1 piper and 1 sluice tender on each of three shifts and 1 pitman, 1 ditch tender, and 1 foreman on day shift. The daily labor charge was $40. As much as 600 cubic yards was washed in a day, the average being about 500.
     The repairs on the elevator were excessive. The casting at the bottom, which cost $157, had to be replaced every 90 days. The lessees considered the ground too rocky for a hydraulic elevator. The cost for supplies, mainly in connection with the elevator, was about $1,000 for the season. The labor cost per cubic yard was about 7 cents, the cost of supplies 1 cent, and the total operating cost 8 cents. If each yard of gravel was charged with its proportionate share of the cost of ditch and and pipe lines and of equipping the mine. The total cost per cubic yard probably would be several times that shown.

(Mines with both Ruble and Hydraulic Elevators)


Lewis
     Harry Lewis had been operating a placer mine, working alone, for about 10 years on Rogue River, near Galice. The mine was situated at the edge of the river, and the fall was not sufficient for a tailrace. The water was brought to the mine through a pipeline 22 and 15 inches in diameter. The Y's in the pit were of 13- and 10-inch pipe. The gravel was cut and swept to the end of the pit by s no. 3 giant with a 3-inch nozzle. There it was driven over a steel plate with 5-inch holes. The undersize went to a hydraulic elevator with a 3 1/4-inch nozzle and a 9-foot lift and thence through a 30-inch sluice box 95 feet long set on a grade of three fourths inch to the foot. The oversize was swept by a giant with a 4-inch nozzle up a Ruble elevator made of round poles which raised it 11 feet onto a rock dump. The poles were set lengthwise and close together. A third giant was used about 1 hour per day in piping the washed gravel from the end of the sluice boxes. The hydraulic elevator and one giant were operated continuously during the shift. The riffles in the sluice were made of sections of 40-pound rails 3 feet long, placed lengthwise in the boxes. At the end of each section of rails 2- by 4-inch lumber was placed crosswise in the box. The rails had been used for 15 seasons and were about worn out.
     Three months were, required to set up the equipment and do the necessary repair work on the pipe lines preparatory to washing. Water was available for washing for 66 days. An extra man was hired for 6 days while washing. About 7,000 cubic yards was washed. With wages at $4, the labor cost would be 8 1/3 cents per cubic yard; supplies amounted to about 1 1/2 cents per cubic yard, making a total operating cost of 10 cents, exclusive of interest, amortization, or new equipment.

(Mines where water was pumped)


Conners
     During the 1931 and 1932 seasons J. C. Conners pumped water for washing a high gravel bar on Burnt River below Bridgeport. Some of the gravel which was cemented required drilling and blasting an occasional auger hole. A few boulders occurred in the gravel. The water was pumped through 500 feet of 5-inch pipe to a height cf 225 feet. A working pressure of 65 pounds per square inch was maintained at the nozzle. Two geared pumps with 4-inch suction and 3 1/2-inch discharge, built for forest-fire fighting, were used. Each pump supplied 160 gallons of water per minute under the head used. One pump was driven by a 4-cylinder and the other by a 6-cylinder automobile engine. The engines together used 20 to 25 gallons of gasoline each shift. A 2 1/2-inch fire hose with nozzles from 5/8 to 3/4 inch in diameter was used for washing the gravel.
     The main sluice consisted of a 12-inch box 90 feet long, set on a grade of three fourths inch to the foot; pole and Hungarian riffles were used. The Hungarian riffles were 1 1/4 inches wide, 2 inches deep, iron-clad on top, and spaced 1 1/2 inches apart. At the edge of the pit the gravel from the sluice box went over a grizzly with 3/4-inch spacing between bars. The oversize was dumped down the side of the mountain, and the undersize went through two 12-foot boxes containing riffles consisting of holes bored in a 2-inch plank.
     Large boulders were rolled over the side of the hill. Others over 4 inches in size were either cast over the side or piled on cleaned-up bedrock. About half the time the hose was used for piping and the other half for washing the gravel through the sluice. A crew of 3 men operated the mine, 1 man with the nozzle, 1 working boulders, and 1 on the pumps. The pumpman also worked in the pit when his attention was not needed at the pumps. About 6 cubic yards was handled per man-shift. At $4 per day the labor cost was about 67 cents per cubic yard. The gasoline at 20 cents per gallon would have cost 22 cents per cubic yard; other supplies would have amounted to about 4 cents, making a total operating cost of 92 cents per cubic yard.
WEB PAGE ADDRESSES:
NWMPC Web Page:
http://www.Geocities.com/Yosemite/Gorge/6503/
NWMP Ore/Wash Gazette Newsletter:
http://www.Geocities.com/Yosemite/Gorge/7278/
OIM Web Page:
http://www.grantgg.com/-oim/

NEWSLETTER SUBMISSIONS:
Submissions to newsletter can be sent to Gary Klier at 8433 SE Lambert Street, Space #139 Portland, Oregon 97266.
E-mail address: glk@grpmack.com (day time) or gklier@juno.com (evenings and weekends)
Deadline for articles is the 15th of the month.

Visit Northwest Mineral Prospectors Newsletter home page

Visit Northwest Mineral Prospectors Club Web page