SEPARATE GARAGE (RCA BARN) CONSTRUCTION
Page 4
End Mar: time to work on the gravel underlayment for pad.  Local landscape supplier delivers 7 tons of rock.  Now I have to set the forms so I can move the rock to the excavation.
First week Apr:  forms are set, level checked with commercial laser borrowed from friend.  Measurements check out, including critical cross corner dimensions.  Gravel is placed.  Pic below is looking pretty much north through SOCAL haze.
17 Apr:  foundation building inspection: passed!!!!!

19 Apr:  began laying vapor barrier, to be followed by rebar.  Must finish by 20Apr as 2 concrete trucks and crew will arrive Monday morning, 21Apr. 
Sunday, 21 Apr: after mechanical tamping of gravel layer, laid 6mil vapor barrier and then set all the rebar.  Full 2 days of work.