In the beginning, there was no room
That meant the shed had to go...
|
||
24.May 2002 The foundations are laid, and the brickwork can begin, at long last.
27th May, and the walls are going up.
28th May, and all of the ground floor is built
30th May The supports for the re-inforced concrete ceiling are up
June 3rd. The ceilings are in.
June 6th The scaffolding is up and work can begin on the 1st floor
June 7th. This is the way up (left), and view from the top (right)
June 11 1st floor nearly finished, second ceiling on soon.
Ceiling elements, being prepared
House without roof, and 2 days later with roof
at home in the office
|