Mobilization
 |
Mobilization
lead time is contemplated to be two months from the date
of award of Contrast and/or from the date of
down/advance payment |
 |
Manpower
shall be deployed from the existing
available sources of Local and augmented
by the expatriate forces – as from the level of
Technician,
Supervisor, Engineer, Manger, Sr. Manger &
the General Manger |
 |
Other
resources like installation equipment, Vehicles,
Excavators/Backhoe, Skid loaders etc., shall be
imported/procured locally as per the
availability
|
Civil Works
 |
Ten
Crews; each comprising Supervisor(1), Foreman(1),
Carpenter(1),Riggers(4), Masons(2), Installer(2),
Helper(4), Bar Bender(2), Welder(1), Electrician(1),
Machine Operators(2) |
 |
These Crews shall be responsible for
trenching/excavating for the foundation of towers,
shelter & fence – beams and the Fuel tank as may be
necessary. Tower erection Chain link Fence, installation
of shelter & earthing making it available to take
over for installation transmission equipment |
 |
All
the Crews managed and controlled by Sr. Manager(Civil)
& Manager (civil) supported by Logistic manager and
PCD Manager from CO |
Telecom/Transmission
Works
 |
Six
Crews each comprising of supervisor(1), Technicians(2),
Installer(1), Rigger(2), Helper(2)
|
 |
All
the Crews managed by Sr.Manager (Trans) and Manger supported
by Logistic Manger and PCD Manager
|
 |
Two Crews each comprising
of Survey Engineer and CAD Operator shall conduct survey,
design & prepare Red Line Diagrams and ABD
|
Safety &
QA/QS
 |
Two
Crews each comprising Q/A Engineer(1), Safety
Supervisor(1) shall conduct QA/QS and safety procedures
complying to the client’s standards |
Electrical Power
Team
 |
Manpower
shall be deployed from the existing available sources in
Nigeria and augmented by the expatriate forces – as from
the level of Technician,
Supervisor, Engineer, Manger, Sr. Manger &
the General Manger
|
Testing
& Commissioning
 |
Two crews comprising of
Engineer(1) and Technician(2) will conduct all the
requisite tests and flag off for commissioning the
site
|
Import and
Procurement of Material & Equipment
 |
Procurement manager
supported by Warehouse manager shall plan for import &
procurement of material and equipment following the PERT
& PCM methods to see the requisite material is made
available for uninterrupted seamless implementation of
works
|
|