Home
About us
Mission & Vision
About Senior Executives
Highlights
Strengths
Services
Clients
Technical Associates
Activities
Projects Handled
Implementation Plan
Glimpses of Projects
Careers
Contact Us
.

Mobilization   

 

Mobilization lead time is contemplated to be two months from the date of award of Contrast and/or from the date of down/advance payment

Manpower shall be deployed from the existing available   sources of Local and augmented by the expatriate forces – as from the level of Technician,       Supervisor, Engineer, Manger, Sr. Manger & the General Manger

Other resources like installation equipment, Vehicles, Excavators/Backhoe, Skid loaders etc., shall be imported/procured locally as per the availability  

Civil Works

 

Ten Crews; each comprising Supervisor(1), Foreman(1), Carpenter(1),Riggers(4), Masons(2), Installer(2), Helper(4), Bar Bender(2), Welder(1), Electrician(1), Machine Operators(2)

These Crews shall be responsible for trenching/excavating for the foundation of towers, shelter & fence – beams and the Fuel tank as may be necessary. Tower erection Chain link Fence, installation of shelter & earthing making it available to take over for installation transmission equipment

All the Crews managed and controlled by Sr. Manager(Civil) & Manager (civil) supported by Logistic manager and PCD Manager from CO  

Telecom/Transmission Works

 

Six Crews each comprising of supervisor(1),  Technicians(2), Installer(1), Rigger(2), Helper(2)

All the Crews managed by Sr.Manager (Trans) and Manger supported by Logistic Manger and PCD Manager

Two Crews each comprising of Survey Engineer and CAD Operator shall conduct survey, design & prepare Red Line Diagrams and ABD

Safety & QA/QS

Two Crews each comprising Q/A Engineer(1), Safety Supervisor(1) shall conduct QA/QS and safety procedures complying to the client’s standards

Electrical Power Team

Manpower shall be deployed from the existing available sources in Nigeria and augmented by the expatriate forces – as from the level of Technician,       Supervisor, Engineer, Manger, Sr. Manger & the General Manger  

Testing & Commissioning

 

Two crews comprising of Engineer(1)  and Technician(2) will conduct all the requisite tests and flag off for commissioning the site

Import and Procurement of Material & Equipment

 

Procurement manager supported by Warehouse manager shall plan for import & procurement of material and equipment following the PERT & PCM methods to see the requisite material is made available for uninterrupted seamless implementation of works

.