Meeting of the Camberwell Grove working group
The meeting took place at 6pm on Thursday 31st January 2008.
The meeting was chaired by Paul Noblet, who has the final authority on whether the works should go ahead.
Andrew Downes, Street Scene Manager at Southwark Council, was present to explain the traffic planners' position.
The meeting was also attended by councillors representing both Camberwell Grove and The Lanes. In addition, about a dozen residents, mainly from Camberwell Grove, but also a few from Lyndhurst Grove and Grove Park were in attendence.
The purpose of the meeting was to conside a proposal put forward by the Camberwell Grove residents to consider the reopening of the bridge to one-way traffic only, from the top to the bottom of the Grove.
Mr Downes had been asked to consider and respond to this proposal, which he did. He conculded that one-way traffic was NOT viable for a number of reasons. These included:
- It would not allow traffic to go from the bottom to the top of the grove and therefore this traffic would continue to be forced to use nearby neighbouring roads as they do at the moment.
- Visibility problems for traffic coming out into the Grove carriageway at the McNeil Road junction. With one way traffic, the risk of consequent accidents was increased.
- Traffic islands are required at the MacNeil Road junction. As these cannot be big enough to allow pedestrians to paude in the middle (due to the size of the road), he expected hazardous conditions and the potential for accidents. Again, traffic lights (with green man crossing) were necessary to reduce this risk.
- Provision for cyclists to cross the multiple traffic streams was too complex and would lead to hazards.
- With one way flow across the bridge, excessive speed of traffic going from top to bottom would be likely to cause hazards and accidents at the McNeil Road junction.
- Visibility for vehicles exiting McNeil Road is inadequate because of the size of the barriers which have to be provided to confine the traffic to the West side of the bridge.
Andrew Downes also pointed out that these problems were largely the same as all proposals previously put forward not involving traffic lights.
He had therefore concluded, with reluctance, that the only way that Southwark can comply with its statutory duty to reopen the bridge as nearly as possible to its previous state was to install traffic lights.
Naturally the Camberwell Grove representatives were deeply unhappy about this conclusion, and the rare constructive criticism cited a lack of imagination by the council in trying to deal with the bridge restriction.
The discussion that followed achieved little save to allow all present to vent their undoubted frustration.
Prior to reopening, traffic cushions will be put in place at the top of the grove.
In addition, to prevent oversized traffic from entering the Grove to being with, width restrictors MAY be put in place at each end of the Grove. We must lobby Paul Noblet and Andrew Downes to get these width restrictors in place before the bridge opens. After all, if they had been put in back in the 1990s, then the bridge would not have been damaged by oversized traffic to begin with!!
The meeting then discussed how and when the bridge might be fully repaired. This is not as easy as simply lobbying Network Rail.
This is becasue although Network Rail has a responsibility to maintain the bridge, it can refuse to replace/fully repair it unless funds are made available from Transport for London (TfL). (Because it was a change in governement policy that required these Victorian bridges to take increased weight, a purpose for which they were not designed).
TfL dole out funds for bridge repairs / replacements in order of prioroty, and this is allocated on a London-wide basis through a working group on which every borough is represented.
So for example, the current repairs on the Red Post Hill bridge is further up the pecking order and has been funded because it has a bus route.