Day 1 - The Frame Raising Friday, October 13 |
||||||||||||||
|
Around 7:30 am, Mike from Adler Crane arrived and set up to unload the timbers. Approximately 8 am, the tractor trailer arrived with the timbers, along with Ron and Ritch from Atlantic Timberframes. |
|
|||
|
Ritch
took charge of the unloading process, determining which timbers should
be placed where.
|
![]() |
|||
|
Immediately
timbers were placed on the deck to layout the bents for assembling.
|
![]() |
|||
|
As
more timbers were placed on the deck, the bents started to come to life.
|
![]() |
|||
|
The view from a distance. By the end of the day, the four bents had been assembled and were ready for raising the next day. |
![]() |
|||