Day 1 - The Frame Raising

Friday, October 13

Around 7:30 am, Mike from Adler Crane arrived and set up to unload the timbers.

Approximately 8 am, the tractor trailer arrived with the timbers, along with Ron and Ritch from Atlantic Timberframes.

Ritch took charge of the unloading process, determining which timbers should be placed where.
Immediately timbers were placed on the deck to layout the bents for assembling.
As more timbers were placed on the deck, the bents started to come to life.

The view from a distance.

By the end of the day, the four bents had been assembled and were ready for raising the next day.