Work Plan |
|
|
 |
|
 |
Equipment |
 |
|
Used grain sacks, 19
X 22 plastic bag, cable ties, cotton gloves, rubber gloves and Raffia string |
|
 |
|
 |
Group Size & allocation |
 |
1. |
Group is divided at the
ratio of 2:1:1:2 for Group A:B:C:D. Final grouping shall be finalized before the climb |
2. |
Also determined by fitness
level. Highest for group D |
|
|
|
|
Section Allocation |
|
1. |
Refer trail section statistics & group allocation
table |
2. |
Collection
starts at the Timpohon Gate by all |
3. |
Then group B,
C & D shall proceed to their destination while group A collect rubbish along the
Timpoon Gate and Carson Fall trail |
4. |
Group A shall
proceed to the next point and collect rubbish along the trail. The collection shall be
stored at the shelter for collection on the way back |
5. |
The cut off
point for Group A is about Ubah point. Once the collection completed, group A can now
proceed to Laban Rata/ Panar Laban |
6. |
For Group B,
collection starts about Ubuh Point and ends about mempening |
7. |
Group C starts
about Mempening and ends about Villosa |
8. |
Group D starts
about Villosa and ends at Panar Laban |
9. |
From Panar
Laban to Lows Peak all team shall be involved. All team shall bring the collection
to Panar Laban. Group D shall bring the collection down to Timpohon Gate |
10. |
All collection
shall be gathered at the allocated area near Timpohon Gate |
|
|
|
|
Collection Method |
|
1. |
Before the journey begins,
each group must decide the distribution of workload among team members. Team members may
decide to subdivide the allocated trail. All members must come to an agreement on the
workload before the journey begins |
2. |
Rubbish collection shall
be segregated by cans, and others |
3. |
The collected rubbish is
to be placed in the 19" X 26" plastic bag. Aluminium Soda Cans are to be crushed
(if you can) |
4. |
Once the plastic bag is
about full, fasten the bag by tying the handle together and keep in the sack |
5. |
Once the sack is about
full, fasten the sack using cable tie and then Raffia string. Ensure that the sack is
strongly fastened and TIED at nearest shelter |
6. |
When each group completed
the allocated trail, proceed to Laban Rata / Panar Laban |
7. |
Rubbish collection between
Panar Laban and Lows peak will be done on the way back. Each person shall carry one
plastic bag and the collection shall be under the responsibility of Group D for bringing
down top Timpohon Gate |
8. |
Each group shall then
proceed to their respective trail to pick up the sacks. Depending on the workload
agreement between group team members, the sack shall be brought down and kept at the
allocated area at Timpohon gate |
9. |
If the weight of each sack
is too heavy, it may be towed along the trail |
|
|
|
|
|
This method is not compulsory and each
group may decided otherw.ise as long as all collected rubbish are brought back to the
allocated area at Timpoon Gate. |
|
 |
|
|
Do |
|
1. |
Observe park rules &
regulation.
LEAVE ONLY FOOTPRINTS, TAKE ONLY PHOTOS and RUBBISH |
2. |
Inform team leader of any
special condition you have such as allergies , etc, etc |
3. |
Know your team mates |
4. |
Encourage your team mates
to exercise before the climb |
5. |
Do practise restraint when
mouthing off |
6. |
NEVER EVER trek ALONE!! |
|
|
|
|
Dont |
|
1. |
Do not attempt to pick up
rubbish where |
|
- Inaccessible
- Out of the planned route
- Hazardous condition
|
 |
|
2. |
Do not damage flora/fauna
in your zeal when collecting rubbish |
3. |
Do not attempt to pick up
human waste or any other waste associated with it |
|
 |
|
|
Contingencies |
|
1. |
Emergencies |
|
Should any team member be
unable to proceed, he or she must inform Group leader. |
|
|
2. |
Raining |
|
Group leader decides to
hold/call off collection if rain occurs. If collection is behind schedule, then members
should proceed to Laban Rata / Panar Laban. Collection can be continued on the way back. |
|
|
3. |
Ran out of
collection resources |
|
If there is insufficient
resources then team members shall stop collection and proceed to Laban Rata / Panar Laban.
Members shall make note and inform Group leader. Resources audit shall be done at Panar
Laban / Laban Rata. Further decisions shall be made there. |
|
 |
|
|
Emergency Plan |
|
|
Class 1: Injuries That
Cause Immobility (Cannot Move) |
 |
|
|
|
Scenario |
Action Plan |
 |
|
|
1. |
Unconscious,
Bleeding and Out of reach |
Inform the nearest available doctor |
Contact guide, any guide, for further
assistant |
Inform group leader |
|
 |
|
|
2. |
Unconscious & Bleeding |
Carry out necessary first aid |
Inform the nearest available doctor.
Ask help from anyone |
Contact guide, any guide, for further
assistant |
Inform group leader |
|
 |
|
|
|
Note |
|
|
During the
climb, there will be many tourists and their guides along the trail. Finding help under
such circumstances should not be too difficult. Doctors and the team leader shall decide
what to be done and if any rescue required leave it to experienced people. |
|
 |
|
|
Class 2: Ill /
Sick But Still Able To Proceed With Help |
|
|
|
|
Action plan |
|
|
Should class 2
emergency occurs, the other team member need to accompany the affected member to descend
(incase team leader is behind) until the group leader is met. Once the team leader is met,
a decision has to be made on whom to accompany the affected teammate to descend. If no
agreement can be made then the team leader will have to accompany the teammate to descend.
In doing so, the team leader shall appoint his successor and handover all resources
required for the collection. In case the original team leader is able to rejoin the group
then his position shall be reinstated. |
|
 |
|
|
Class 3: Persons
Need Coaxing (Kick In The Butt) |
 |
|
|
|
Action plan |
|
|
Should Class 3 emergency
occur then, its up to the team leader? He/she can either persuade the teammate to continue
or allow the person to return. However, the team leader must be satisfied without doubt
that the affected person is able to proceed to the park headquarters. |
|
|
|
|
|
Team Leader Responsibilities / Tasks |
 |
|
|
1. |
Ensure sufficient
resources for collection |
2. |
Emergency coordinator |
3. |
Schedule time keeper |
4. |
In-situ decision-maker |
5. |
Ensure sufficient Medkit |
6. |
Dissipate information to
team members |
7. |
Reports to Project Leader |
8. |
The Last person in the
group |
|
 |
|
|
Project Leader |
|
|
|
1. |
The project leader has the
overall responsibility of the project |
2. |
The Project Leader shall
have the final word should any dispute occur |
|
|
|
|
|
|
|
|
Last updated 1 August 2001 |