
week 1
week 2
week 3
week 4
week 5
week 6
week 7
week 8
week 9
week 10
|
  

Week 1 (15 Jan - 21 Jan)
- Established a team consisting of 8 members
and elected a Team Leader (Project Manager) to lead the team
- Team name set as 6row7
- Responsibilities and appointments were assigned. Namely: administrator,
analyst, programmer and web-designer
- Formulated project requirements and proposed
the project for another team
- Received project requirements from our client Freshmaker
Ltd
- Developed project schedule
- Developed preliminary use-case diagram
Week 2 (22 Jan - 28 Jan)
- Familiarized with Rational Rose as our project modeling software
- Decided on using ASP to implement our project
- Refined system specifications
Week 3 (29 Jan - 4 Feb)
Week 4 (5 Feb - 11 Feb)
- Modeled system design using Structure Charts
Week 5 (19 Feb - 25 Feb)
- Reallocated programming workload
- Started implementation using Visual Interdev and MS Frontpage
Week 6(5 March - 11 March)
- Continued implementation of system
Week 7 and 8 (12 March - 25 March)
- Completed implementation of system
- Testing in progress
- Compilation and generation of online report in progress
Week 9 (26 March - 1 April)
- Completed product demo to supervisor
- Completed online report
|