HOME
TABLE
OF CONTENTS
Acknowledge
ments
Report Contributors
SECTION
1. SUMMARY
SECTION
2.
PROJECT
AND WATERSHED DESCRIPTION
SECTION
3.
VOLUNTEERS
AND COMMUNITY INVOLVEMENT
SECTION
4. MEDIA AND PUBLIC EVENTS
SECTION 5.
ACID MINE DRAINAGE
SECTION 6.
WATER MONITORING
SECTION
7. FISH HABITAT MAPPING PROGRAMS
SECTION 8.
REFUGE POND STUDIES
SECTION
9. RESTORATION PROJECTS
SECTION
10. FLOWS AND STORAGE REPORT
SECTION 11.
ENHANCEMENT
CONTACT US

|
SECTION 5
Acid Mine Drainage
Introduction
In the late 1950’s, pink and coho salmon escapements
in the Tsolum River started to decline. Despite enhancement efforts
initiated by DFO at Headquarters Creek (a tributary of the Tsolum River)
in 1968, fewer salmon returned to the river each year. By 1985, coho
salmon runs numbering 7500 in 1957, were reduced to 800 while only 1000
pink salmon returned from runs that historically numbered over 75,000 (Deniseger
et al 1995). Enhancement techniques that were successful in many other
river systems were not working in the Tsolum River.
Federal and provincial investigations into
the cause of the run declines began. Water samples revealed that copper
concentrations in the mainstem of the Tsolum River were very high during
the spring and fall. Researchers focused on the abandoned open-pit copper
mine that operated on Mt. Washington from 1964 to 1967. Kangasniemi and
Erickson (1986) stated that the failure of the Headquarters Creek salmon
enhancement efforts resulted from unacceptably high dissolved copper concentrations
in the Tsolum River. The high copper concentrations came from dissolved
copper leaching from the old mine site, located on the east slope of Mt.
Washington (Appendix A).
The now defunct Mt. Washington Copper Co.
Ltd. and Cumberland Mining Co. Ltd. jointly operated two main pits at an
elevation of approximately 1300 metres (Sierra Legal Defence Fund, 1998).
Drainage from the south pit flows into the McKay Creek watershed. The north
pit drains into the Pyrrhotite Creek watershed. The mined ore, chalcopyrite,
was trucked 5 km south and 400 m lower to a crushing and concentrating
mill on Murex Creek. The mill tailings were transferred via pipeline to
a pond draining primarily into Wolf Lake. Of these four potential acid
generating sites, to date only the north pit has been identified as a serious
problem, while the other three sites are minor contributors of copper.
The term ‘acid generating’ refers to the
production of sulphuric acid, which lowers the pH of surface and ground
water. Copper and iron are found as sulphides in chalcopyrite. When this
ore is exposed to oxygen rich water, the sulphide oxidises to sulphate,
the iron oxidises to iron oxide and/or hydroxide, and sulphuric acid is
released. Copper and other metals (aluminium, arsenic, iron, and zinc)
dissolve in water at the reduced pH and leach into the Tsolum River headwaters.
Drainage of this type from mine sites is called ‘acid mine drainage’ or
AMD. This process, when naturally occurring or from non-mine disturbances,
is known as ‘acid rock drainage’ or ARD.
The Effect of Copper on Salmon
There is little doubt that copper concentrations
found in the Tsolum River cause damage to salmon. Salmonid studies reported
by Deniseger et al (1995) indicate soluble copper concentrations
in the Tsolum River must be reduced to below 7 micrograms/L to allow recovery
of the salmon fishery. To achieve this result, approximately 95% of the
mine discharge would require elimination or treatment when dilution by
clean water in the lower watershed is lowest flow levels. Peak toxicity
occurs during the spring freshet, when there is rapidly melting snow and
little rainfall at lower elevations to dilute the copper dissolved in the
runoff water. A secondary peak of toxicity exists during autumn, as coho
salmon are entering the river. Dissolved copper levels are thought to cause
adult salmon to avoid spawning in the Tsolum River mainstem. Salmon smolts
migrating to the estuary are weakened or killed as high copper levels interfere
with their ability to adapt to salt water. The effects of copper contained
in sediments upon spawning salmon or incubating eggs are not well known.
Despite evidence of mechanical transport of copper to 18 km from the minesite,
the sediment-bound copper in the lower watershed appears to be highly stable
such that the copper-rich sediments are unlikely to become a secondary
source of dissolved copper (Deniseger and Kwong, 1996)
Evidence indicates that copper damages
salmon by interfering with liver function, allowing other more toxic materials
such as cadmium to cause further damage. In-stream bioassay studies have
shown that salmon held in the Tsolum River die when dissolved copper
concentrations are elevated by snowmelt or heavy rain at the minesite (Deniseger
et al 1995). These results can be duplicated in the laboratory, where an
LD-50 indicating the concentration of copper lethal to 50% of a sample
of salmon is calculated.
Remediation Work from 1987 to 1992
A 1987 report by Steffen Robertson and Kirsten
(BC) Inc. (SRK) documented a number of measures to eliminate or reduce
copper concentrations in the Tsolum River. This report recommended
consolidation of the acid producing mine waste rock, into a single pile
on the northeast side of the north pit. They further recommended covering
the pile with 1 to 1.5 metres of high silt glacial till. An additional
impermeable membrane could be sandwiched within the till cover. As well,
SRK recommended site monitoring for three years, to assess the effectiveness
of the till cover. The report suggested covering the pit and perhaps the
waste dump, if the pit also proved to be acid generating.
During 1988 and 1989, the north pit waste
rock was consolidated and covered with one metre of the glacial till. It
later became apparent that the north pit waste rock was not the only source
of AMD. Evidently, there is porosity in the bedrock and/or fractures
in the bedrock. A combination of these geological features and movement
of localized water table levels has contributed to the acid leaching in
the north pit proper.
Various measures were implemented during
1989 to 1992 (Galbraith, 1993). These measures included diversion of ground
and surface water, covering suspected ‘hot’ spots with concrete and asphalt
impregnated textiles, and in situ neutralization with lime (CaCO3 and Ca(OH)2).
Most of these procedures involved movement of potentially acid generating
material around the site.
Site monitoring also continued. Unfortunately,
as a result of the additional measures, the effectiveness of the till cover
is unclear. The provincial government spent approximately $1.5 million
dollars in attempts to control AMD by capping the mine waste and ditching
the surface water at the mine site. Despite these efforts, high copper
concentrations continue to limit fish production in the Tsolum River (Brandt
1997).
Remediation Options
Source control and water treatments are two
basic options for reducing copper concentrations to acceptable levels.
Source control
Source control involves halting the acid generating
reaction, or preventing reaction products from entering fish bearing streams.
Oxidative leaching can be slowed or stopped by preventing oxygen from contacting
the copper ore. One method employs underwater submersion of the ore, tailings
or waste. Oxygen, having a maximum solubility in water of 15 mg/L, is removed
by biological action in deep water. Opportunities for convective re-oxygenation
are limited. This method, successful so far at the Island Copper Mine near
Port Hardy, is not suitable for the Mt. Washington site because of the
elevation and the topography of the minesite.
Another source control method inhibits
the entry of water to the mineralized zones thereby limiting the extent
of leaching and the mobility of leached products. This is the rationale
behind covering mine sites. This plan begins with diverting water entering
the north pit by improving the diversion ditch that is located uphill from
the pit. A Multi-layer cover could then be placed over the entire
north pit (including the pit floor and the waste rock material).
The design suggested by Haug 1997 includes a water impermeable layer of
fine-grained material such as bentonite or fly ash (by product of pulp
and paper manufacturing). The purpose of this layer is to exclude water
and oxygen from coming in contact with the AMD. A second layer of
soil will be placed on top of the impermeable layer and vegetation will
be planted on top of the soil to protect the soil from erosion.
Water treatment
Treatment of contaminated water involves removal
of the copper cation. Anions, such as sulphide, carbonate or hydroxide,
will combine with the cation to form insoluble salts. These insoluble salts
can be removed from water by precipitation or filtration methods.
Wetlands have the ability to naturally
filter metals from water and neutralize AMD. Copper is initially removed
from the water by the wetland vegetation. The vegetation dies, sinks to
the bottom of the wetland and decays. The decomposition process removes
oxygen, whereby sulphate is reduced to sulphide, which immobilizes the
copper (Golder 1997). This natural phenomenon is limited to large wetlands
experiencing low flows, relatively mild temperatures and acidity.
It is not known if there is sufficient wetland area in the upper
Tsolum River watershed to handle the very high peak copper loads which
occur in the spring and fall.
Industrial treatment facilities employ
neutralization materials, which can be rigorously controlled. These treatment
facilities are readily available, but can be expensive. Long term
operational funding would be required and the sludge produced as a byproduct
of this process may endanger aquatic plants and animals downstream of the
minesite. The heavy snow pack (over 10 meters in 1999) and lack of hydro
power at the site may make it necessary for any treatment plant to be constructed
at a lower elevation with the acid drainage being carried by pipeline down
to the treatment plant (Golder 1997b).
Combination treatment options
Combined treatment systems involves in situ
neutralization and wetland enhancement, with or without neutralization.
Control of upstream surface water flow
should be added to source control and treatment options. Under certain
conditions (e.g. low flow rates downstream), it may be advantageous to
capture and store contaminated water for release when flow rates increase
downstream. Smaller treatment plants may also be feasible if peak
flows were stored and released more slowly, in effect, buffering the flow
rates.
Generally, source control solutions are
felt to be ‘permanent’. They will, however, require time to be effective
and will probably be expensive, $4 to $10 million. Treatment solutions,
meanwhile, require the ongoing expenses of materials, energy, sludge disposal.
An evaluation of options and costs is being considered by the Acid Mine
Drainage Work Group in the preparation of the AMD Action Plan.
TRTF Action Plan
Work on the mine problem since 1992 has, for
the most part, been limited to monitoring strategic sites in the watershed
and evaluating the options. Two local delegations lobbied provincial cabinet
ministers for action on the mine. The first delegation met in 1995 with
then Mines Minister, the Honourable Anne Edwards. In 1997, a second meeting
was held with Mines Minister, the Honourable Dan Miller and Environment
Minister, the Honourable Cathy McGregor. The Ministers suggested that funds
would be forthcoming only after an action plan could assure the government
that further work would be successful in lowering copper levels in the
river.
Since March 1997, the Tsolum River Task
Force’s AMD work group has been seeking to provide solid answers for the
Ministers. The work group began by examining two treatment options. One
option involves the feasibility of piping the concentrated mine run off
to a site more accessible year round (Golder Associates, 1997b). The other
involves the feasibility of passive/active wetland options (Golder Associates,
1997a).
The draft Action Plan produced by the work
group outlines their present position with regard to minesite remediation
(see Appendix B). The Action Plan will form the basis of the TRTF
remediation proposal. This draft plan is a work in progress, intended to
provoke discussion within the work group. It is subject to revision
and the author of the site welcomes ideas that would improve the plan (Ferguson
1998).
This draft document can be viewed on the
Internet website at
http://www.netcolony.com/members/wildwolf/actionplan/APtoc.htm.
A list of references relating to AMD from
the Mount Washington mine can be found in Appendix C.
REFERENCES
-
Brandt, Charles 1997. Reclaiming
a River published in the Comox Valley Echo;Friday September 26, 1997
-
Deniseger, J.H. McKean, C.J.P. and Chapman
A.R. 1995. Tsolum River Watershed Water Quality Assessment and Objectives;
Technical Appendix. B.C. Ministry of Environment, Lands and Parks,
Victoria, B.C.
-
Deniseger J. and Y.T. Kwong, 1996. Rish
assessment of Copper-Contaminated Sediments in the Tsolum River near Courtenay,
British Columbia. Water Qual. Res. J. Canada 31(4): 725-740.
-
Galbraith, D.M. 1993. Mt. Washington
mine reclamation project report on 1992 program—1992 post construction
report. Prepared for Mt. Washington Reclamation Project, Ministry
of Energy, Mines and Petroleum Resources.
-
Golder and Associated Ltd. 1997a. Passive
and/or wetland treatment options for acidic mine drainage at the Mount
Washington mine site, Courtenay, B.C. Final Report prepared for the
Environmental Protection Branch, Environment Canada.
-
Golder and Associated Ltd. 1997b. Pipeline
routing and conceptual design study for the diversion of Mt. Washington
acid rock drainage. Report prepared for the Environmental Protection
Branch, Environment Canada.
-
Deniseger, J.H. McKean, C.J.P. and Chapman
A.R. 1995. Tsolum River Watershed Water Quality Assessment and Objectives:
Technical Appendix. B.C. Ministry of Environment, Lands and Parks,
Victoria, B.C.
-
Ferguson, Dave 1998. Mount Washington
Action Plan, Tsolum River Task Force
-
Haug, M. and O’Kane M. 1998. Preliminary
Assessment of Conditions at the Mt. Washington Mine Site. A draft
report prepared for Canadian Pacific Railway, Calgary Alberta
-
Kangasniemi, B.J.and Erikson, L.J. 1986.
A preliminary assessment of acid mine drainage from an abandoned copper
mine on Mount Washington, B.C. Ministry of Environment, Lands and Parks.
-
Sierra Legal Defence Fund. 1998. Mt.
Washington: The Money Pit. In: Digging Up Trouble—The Legacy of Mining
in British Columbia. Sierra Legal Defence Fund, May 1998.
-
Steffen, Robertson and Kirsten (B.C.) Inc.
1987. Acid mine drainage abatement study, Mount Washington, Vancouver
Island, B.C. Report 62701/1 prepared for the B.C. Ministry of Environment
and Parks.
SECTION 5. APPENDIX A
Map of Mine Site

SECTION 5. APPENDIX B
Outline of Draft Action Plan
For remediation of Acid Mine Drainage at the Mt. Washington
Minesite
Action
|
When
|
Approximate
Max. Cost
|
1. Finish Action Plan |
February 1999 |
|
2. Divert Uphill Water |
Summer 1999 |
$0.5M - $1M |
3. Seal off Pit Floor |
Summer 1999 If necessary |
$0M - $2M |
4. Cover North Pit and Replant |
Fall 1999 |
$2M - $3M |
5. Enhance Wetlands |
2003 |
$0M - $1M |
6. Treatment Plant |
2003 Only if necessary |
$0 - $2M |
7. Restore Salmon Habitat |
1997 onward |
$0.5 - $2M |
8. Monitor on-going |
|
$1M |
TOTAL COSTS |
|
$4M - $12M |

SECTION 5. APPENDIX C
Bibliography from
AMD Draft Action Plan website.
-
Appendix C - Bibliography from AMD draft Action
Plan website.
-
Bibliography -- Mount Washington Mine Action
Plan
-
Coombs, David; Unpublished; "The Role
of Narrow-Leaved cotton Grass (Eriophorum angustifilium, Honck.) in the
Removal of Copper in a Sedge Fen receiving Acid Mine Drainage--Undated
draft"; 239 pps.
-
Deniseger, John and L.W. Pommen; of MELP;
"Tsolum River Watershed--Water Quality Assessment and Objectives"; Apr
21, 95; 96 pps for MELP.
-
Gadsby, John W.; Unpublished Proposal;
"Developing a Copper Contamination Control Strategy for the Mount Washington
Mine--"; Apr 01, 98; 25 pps for TRTF.
-
Galbraith, D.M.; of MEMPR; "Mt. Washington
Mine Reclamation Project Report on 1992 Program--1992 Post Construction
Report"; Mar 01, 93; 43 pps for Mt. Washington Reclamation Project.
-
Galbraith, D.M.; of MEMPR; "Mt. Washington
Acid Mine Drainage Control Project -- Project Overview Report"; Dec 14,
95.
-
Galbraith, D.M.; of MEMPR; "Results of September
7, 1995 Field Trip to Mt. Washington -- ; Oct 17, 95; 1 pps for Mt. Washington
Project Committee.
-
Kangasniemi, B.J. and Lloyd J. Erickson; of
MELP; "A Preliminary Assessment of Acid Mine Drainage from an Abandoned
Copper Mine on Mount Washington, B.C.--"; Apr 01, 86; 33 pps for MoE.
-
Mierzejewski, J. and T. P. Fitzell;
of Golder Associates; "Pipeline Routing and Conceptual Design for Diversion
of Mt. Washington Acid Rock Drainage--"; Apr 16, 97; 35 pps for EC-EPB.
-
Nix, Peter; of Golder Associates; "Passive
and/or Wetland Treatment Options for Acidic Mine Drainage at the Mount
Washington Mine Site, Courtenay, B. C. --"; Apr 03, 97; 62 pps for EC-EPB.
-
Olauson, Rodney C.; of SRK (Unpublished Proposal);
"development of a Copper Contamination Control Strategy for the Mount Washington
Mine--"; Apr 01, 98; 18 pps for TRTF.
-
Robertson, A., M. Eivemark, A. Brown, A.S.C.,
and J. Malick; of SRK; "Acid Mine Drainage Abatement Study, Mount Washington,
Vancouver Island, B.C.--"; Jul 01, 87; 120 pps for MELP.
-
Wendling, Gilles and Sue Baldwin; of
Levelton; "Mount Washington Copper Mine Data Review and Recommendations
on Mitigative Measures--"; Jul 02, 98; 31 pps for TRTF.
-
Wiens, John H. and Peter C. Lighthall; of
AGRA; "Opportunities Relating to the Remediation of acid Mine Drainage
at Mt. Washington and the Restoration of the Tsolum River Watershed--";
Jun 06, 96; 27 pps for MELP.
|
SECTION 5
Acid Mine Drainage
Introduction
Effect of Copper on Salmon
Remediation Work from 1987 to
1992
Remediation Options
TRTF Action Plan
References
Map of Mine Site
Draft Action Plan
Bibliography from
AMD Draft Action
Plan

|