HOME
TABLE
OF CONTENTS
Acknowledge
ments
Report Contributors
SECTION
1. SUMMARY
SECTION
2.
PROJECT
AND WATERSHED DESCRIPTION
SECTION
3.
VOLUNTEERS
AND COMMUNITY INVOLVEMENT
SECTION
4. MEDIA AND PUBLIC EVENTS
SECTION 5.
ACID MINE DRAINAGE
SECTION 6.
WATER MONITORING
SECTION
7. FISH HABITAT MAPPING PROGRAMS
SECTION 8.
REFUGE POND STUDIES
SECTION
9. RESTORATION PROJECTS
SECTION
10. FLOWS AND STORAGE REPORT
SECTION 11.
ENHANCEMENT
CONTACT US

|
SECTION 9
Restoration Projects
Preserving Tsolum
River Salmon Habitat
In order to maintain salmon stocks in this
watershed, it is essential that fish habitat be restored and preserved.
In 1998 and 1999, eight habitat enhancement and restoration projects were
completed by the Tsolum River Task Force, as shown in Appendix A.
These projects included:
-
Digging in-stream and near-stream refuge ponds.
-
Stabilizing stream banks by constructing tiers
of willow wattles (Appendix B).
-
Planting streamside riparian vegetation to
provide shade, cover from predators, and filtering of runoff from upstream
runoff (Appendix C).
-
Complexing stream habitat by constructing
rock weirs and placement of habitat logs to increase pool scouring.
-
Hardening streambeds with gravel to allow
cattle to cross streams without causing erosion of soft substrate.
-
Constructing riparian rafts that provide shade,
cover and increase the food supply of refuge ponds (Appendix D).
-
Installing a culvert to improve access to
habitat previously inaccessible at low water.
-
Protecting side-channel habitat from erosion.
Planning of 1997 and 1998 Restoration Initiatives
Consultation with the Tsolum River Task Force
Habitat Work Group began in October 1997. Priorities for in-stream
projects were set and a work plan was developed for projects to be undertaken
in 1998. On the advice of the Habitat work group, it was agreed that
restoration work should begin in the tributaries that were not affected
by the adverse effects of copper pollution leaching into the Tsolum River
mainstem below Murex Creek. DFO Community advisor, Bryan Allen, and
Norm Sieffert of the Portuguese Creek Watershed Stewards, also provided
project advice.
In the spring and summer of 1998, mapping
crews used the Sensitive Habitat Inventory
and Mapping (SHIM) Methodology (Mason
et al, 1998. Version 3.1), to map stream habitat, and identify opportunities
for future restoration projects.
In the spring of 1998, the restoration
crew worked with landowners to develop project plans. These plans
were approved by the Habitat Work Group and by the appropriate government
agencies before in-stream work began.
Restoration Projects
Plans for the following projects completed
by TRTF in 1998 and 1999 are available in Chamberlain and Campbell 1999.
1) Streambank stabilization, Franklin property
The Franklin property was experiencing a lot
of flooding and streambank erosion. To alleviate the flooding, sod
and soil in the center of the channel were removed, and willow wattles
were constructed to protect streambanks from erosion. This project
was completed in four phases which are detailed in Appendix A, Table 1.
Tiered willow wattles were constructed
along 10 m of streambank in April 1998. Willow stakes were also planted
to stabilize the wattles and to provide cover on a low-lying area of the
bank. Designs for wattle construction were modeled after designs
presented in Polster, 1998. In July 1998, an island of sod
which was restricting fish passage at low water was removed from the center
of the channel. Once the island was removed, six more metres
of willow wattling were completed. Streambanks were later replanted
with riparian vegetation, which were tended by the landowner throughout
the summer. A further 15 meters of willow wattles will
be constructed to stabilization streambanks in March 1999.
2) Stream channel complexing, Finlay Creek
In 1994 and 1995, Comox Valley Project Watershed
Society installed boulders and woody debris in Finlay Creek, a tributary
to Portuguese Creek.
These structures were installed to combat
siltation following the clearing of an upstream wetland property.
The TRTF restoration crew revisited the sites in the third reach of the
stream and determined that additional stream complexing was needed.
In-stream structures that had been previously installed were stabilized
to encourage pool development.
3) Near-Stream Refuge Pond Construction, Bell
property
Water levels in Portuguese Creek rise quickly
after a rainfall due to runoff entering the creek from surrounding residential
and agricultural land. Water levels in the creek also drop to near
zero during the months of July and August. With few wetlands to buffer
changes in flow, fish in the creek must migrate to rearing habitat in other
creeks, or survive in refuge ponds.
Many landowners have worked with the Portuguese
Creek Watershed Stewards to develop refuge ponds on their properties.
These ponds provide a dual service to salmon, offering summer refuge to
coho and trout fry and providing shelter for adults returning to spawn
in the system.
In the spring of 1998, the TRTF worked
with a landowner and the Portuguese Creek Watershed Stewards to construct
a near-stream pond on the Bell property adjacent to Gunter Road. The pond
joined the creek at one site and was filled in the fall by high water.
Stumps from trees removed during pond construction were placed back into
the pond to provide cover for fish.
Riparian vegetation and grass seed was
planted to stabilize sloping pond banks and to provide cover for the fish.
In the fall of 1998, landowners observed adult coho holding in this pond
prior to spawning. In the spring of 1999, a catamaran style riparian
raft was installed in this pond.
4) In-stream ponds and riparian raft
construction, McWilliam’s property
Forsythe and Smit Creeks (tributaries to Dove
Creek) run dry during the summer and offer little refuge to salmon because
of lack of in-stream complexity. During November 1997, chum salmon were
observed spawning in Forsythe Creek. In the spring of 1998, coho
fry were salvaged from drying stream pools and transported to refuge ponds.
Groundwater in this area is in short supply
and much of the water resource available is utilized for domestic and agricultural
purposes. To provide refuge habitat, two in-stream refuge ponds were
constructed, and a series of rock weirs were constructed in Smit Creek
on the McWilliam property. In the fall of 1998, riparian vegetation
was planted on the streambanks and around a previously constructed irrigation
pond used as rearing habitat for salmonid fry.
To provide shade and cover for fry in this
pond, two riparian rafts were constructed (Appendix D). The
raft is anchored to the pond bottom and the vegetation on the raft provides
cover and shade for the fish. Insects that land along the raft edges
become a potential food source for the salmon fry when they drop off the
raft into the pond. To maximize the effect, the rafts were constructed
as small rectangles thereby providing the maximum edge area. Designs
for riparian rafts can be obtained from the TRTF.
5) Heidema pond and stream reconstruction
The Portuguese Creek Watershed Stewards had
reported large numbers of fry rearing in this branch of Portuguese Creek,
and had cooperated with the landowner to construct two small off channel
ponds that provide summer and winter refuge habitat for coho pre-smolts
and trout fry.
A site assessment determined that a larger
pond was needed, and that some channel reconstruction would alleviate flooding
occurring on an adjacent property. This channel would provide easy
access to the new pond. This area is used by coho spawners that rely
on the ponds to provide refuge from predators during times of low flow.
The Portuguese Creek Watershed Stewards
had established landowner contact, and were instrumental in assisting with
project planning and design. To alleviate flooding on the adjacent
property, a silt plug was removed and the stream was redirected into a
more stable outflow channel.
After the pond and channel reconstruction
was completed, riparian vegetation and grasses were planted to stabilize
streambanks and pond sides.
6) Culvert installation at Gark Creek
Gark Creek is an ephemeral tributary to the
Tsolum River. To enhance salmon habitat the owner of the property
had installed a culvert in the creek. Unfortunately this culvert
acts as a barrier at low water flows, and as the creek dried up salmon
fry became trapped in pools below the culvert.
The original plan was to remove the culvert
and install a bridge using donated timbers. When the timbers became
unavailable; a second plan was developed by an engineering technician to
design a culvert installation plan. In cooperation with DFO engineers
the plan was approved, and the culvert was installed between August 19
and September 8, 1998. The landowners supported the project by offering
a machine and operator to install the culvert. Root wads and boulders
were donated by the Vancouver Island Highway Project. These were
placed in the channel upstream of the culvert to provide cover for fry
and adults. Riparian vegetation was planted along the sides of the
creek to offer additional shade and cover.
7) Stream complexing and cattle crossing,
Pistell property
Previous projects completed by the Portuguese
Creek Watershed Stewards and Comox Valley Project Watershed’s “Stewardship
on the Farm” program brought this opportunity to the attention of the TRTF.
Coho salmon had have been seen rearing in the middle branch of Portuguese
Creek and in the pond downstream from the restoration site.
The stream channel had been degraded by
years of cattle crossing and lacked riparian cover and large woody debris.
Once fencing had been put in place to eliminate cattle, plans were prepared
with reference to Fish Habitat Restoration Procedures (Slaney and Zaldokas,1997)
and the Stream Enhancement Guide (Anon., 1980). Work began
at the property on August 14 after landowner and government approvals had
been received. The TRTF paid for the cost of the machine and materials
used for the project while the landowner provided stumps for stream complexing,
and a neighbour provided cedar logs for in-stream weirs.
Downstream from the weirs, a silt plug
was removed and a small pool was excavated. Gravel was placed
in the stream above the pool to provide cattle with access to an adjacent
field. This project will be monitored for structure stability, and
additional large woody debris will be added if necessary.
8) Side channel stabilization, Jorgensen property
The channel that borders the Jorgensen property
(downstream of Dove Creek) is one of only two known side channels in the
lower Tsolum River. In 1997, fall floods eroded the entrance to the
channel, and the mainstem of the river threatened to erode the entire area.
Adjacent landowners approached the Task
Force and DFO to arrange a site visit. A plan was developed, and following
DFO approval the work began. Boulders and rootwads were placed to
protect the outside of the channel. By the spring of 1999, some channel
modification had occurred, but most of the channel habitat was still intact.
The summer of 1998 was very long and dry, allowing an extension of the
prescribed fisheries window. This seasonal variation meant that we
were able to complete the project later in the season than would normally
have been allowed.
Recommendations for Further Work
-
To continue with streambank stabilization,
willow wattling should be completed in the eroding sections of lower Portuguese
Creek. Erosion control is also needed on sections of
Headquarters Creek above the hatchery and in areas which are being impacted
by the Vancouver Island Highway project.
-
Many small streams would benefit from increasing
the amount of riparian vegetation along the banks. This should be
undertaken on agricultural land only after streamside fencing is in place.
-
The addition of spawning gravel and weir construction
would benefit Portuguese Creek, Forsythe Creek and several other tributaries.
-
The addition of large woody debris (stream
complexing) is needed in several small streams, such as Forsythe, and some
of the tributaries to Dove Creek.
-
There is a shortage of summer and winter rearing
habitat and refuge for spawners. Construction of more refuge ponds,
and linking existing ponds into a network would improve salmon survival.
-
There is a need to provide additional shade
and cover in some of the refuge ponds. Installation of riparian rafts
in these areas would improve habitat quality.
-
Working with the agricultural community to
test the effectiveness of riparian bridges for improving fish habitat in
drainage ditches should be initiated. These bridges will provide
cover for fish and improve winter rearing habitat without blocking the
drainage capability of the ditches.
-
A culvert study should be undertaken to determine
whether existing culverts are barriers to fish passage. Culverts
that are limiting fish movement should be replaced or reinstalled.
-
A program of landowner contact and public
awareness would greatly assist habitat restoration efforts. By informing
landowners of the importance of maintaining streamside vegetation, we may
reduce the need for stream rehabilitation.
References
-
Anonymous 1980. Stream Enhancement
Guide. Salmonid Enhancement Program, Government of Canada, Department
of Fisheries and Oceans, Province of British Columbia, Ministry of Environment,
Kerr Wood Leidal Associates Ltd., and D.B. Lister & Associates Ltd.
DFO Vancouver, BC.
-
Chamberlain D., and Campbell K. 1999.
Tsolum River Restoration Project Plans. Internal Report to the Tsolum
River Task Force.
-
Mason B., 1998. Stream Mapping Procedures
for Land-Use Planning in Coastal Urban Watersheds 1998. Department
of Fisheries and Oceans in partnership with Ministry of Environment, Lands
and Parks and the Pacific Streamkeepers Federation. DFO Vancouver.
-
Polster D. 1998. Soil Bioengineering
for Forest land Reclamation and Stabilization
-
Prepared for British Columbia Ministry of
Forests. Resource Tenure & Engineering Branch Engineering Section.
BC Ministry of Forests. Victoria, BC.
-
Slaney P.A. and Zaldokas D. 1997 Fish Habitat
Rehabilitation Procedures. Watershed Restoration Technical Circular
No. 9 Watershed Restoration Program, Ministry of Environment, Lands
and Parks.
SECTION 9. APPENDIX A
Map and Table of Restoration
Project Locations
Appendix A. Completed Restoration Projects
|
Project Title
|
Location
|
UTM
Easting
|
UTM
Northing
|
Date Begun
|
Date
Com- pleted
|
1a |
Franklin Property
Streambank Stabilization |
Franklin Property
Carwithen Rd.
Lot 3 Sec 35 Comox Dist. |
352362 |
5515924 |
Mar. 25, 1998 |
April 29, 1998 |
1b |
Franklin Property
Channel Clearing |
Franklin Property
Carwithen Rd.
Lot 3 Sec 35 Comox Dist. |
352362 |
5515924 |
July 22, 1998 |
July 22, 1998 |
1c |
Franklin Property
Riparian Replanting |
Franklin Property
Carwithen Rd.
Lot 3 Sec 35 Comox Dist. |
352362 |
5515924 |
July 28, 1998 |
July 28, 1998 |
1d |
Franklin Property
Streambank Stabilization |
Franklin Property
Carwithen Rd.
Lot 3 Sec 35 Comox Dist. |
352362 |
5515924 |
Mar. 5, 1999 |
Mar. 26, 1999
(est) |
2 |
Stream Complexing
Finlay Creek |
Finlay Creek
Reach 3
Between. Wentworth & Caledon Rd. |
356536
upstream |
5508966
upstream |
July 18, 1998 |
July 22, 1998 |
3 |
Refuge Pond
Construction
Portuguese Creek |
Bell Property,
Gunter Rd. Merville
DL 147 Comox District |
352362 |
5515924 |
Aug. 8, 1998 |
Aug. 8, 1998 |
4a |
McWilliam Pond
Riparian Raft |
McWilliam Property
3465 Burns Rd
Section 73 Comox District |
353066 |
5508690 |
July 22, 1998 |
July 22, 1998 |
4b |
McWilliam Property
Stream Complexing,
Pond Construction |
McWilliam Property
3465 Burns Rd
Section 73 Comox District |
353066 |
5508656 |
Sept. 12, 1998 |
Oct. 8, 1998 |
4c |
McWilliam Property
Refuge Pond LW Placement |
McWilliam Property
3465 Burns Rd
Section 73 Comox District |
353066 |
5508656 |
Oct. 30, 1998 |
Oct. 30, 1998 |
5 |
Heidema Property
Refuge Pond, and
Stream Channel Re- construction |
Heidema Property
6850 N. Isl. Hwy |
351928 |
5517195 |
Aug. 17, 1998 |
Aug. 31, 1998 |
6 |
Gark Property
Culvert Installation
Stream Complexing |
Gark Property
4052 Dove Cr. Rd.
Lot B DL 122 Comox District
DD 34556-1 |
352483 |
5510479 |
Aug. 19, 1998 |
Sept. 8, 1998 |
7 |
Pistell Property
Stream Complexing |
Pistell Property
6669 N. Isl. Hwy. |
351300
upstream |
5516672
upstream |
Aug. 14, 1998 |
Aug. 20, 1998 |
8 |
Jorgensen Property
Sidechannel Armoring |
Jorgensen Property,
Todd Rd
Site 463 C5, RR #4 Courtenay |
Unkn |
Unkn |
Oct. 15, 1998 |
Oct. 22, 1998 |
Tsolum River Restoration Projects--Map
SECTION 9. APPENDIX B
Willow Wattling Photos
SECTION 9. APPENDIX C
List of Species Planted
Appendix C: Plants Used in Riparian
Replanting Projects
COMMON NAME |
SCIENTIFIC NAME |
Red Alder |
Alnus rubra |
Red osier Dogwood |
Cornus stolonifera |
Black Hawthorne |
Crataegus douglasii |
Ocean Spray |
Holodiscus discolor |
Black Twinberry |
Lonicera involucrata |
Pacific Crabapple |
Malus fusca |
Pacific Ninebark |
Physocarpos capitatus |
Cascara |
Rhammus purshiana |
Nootka Rose |
Rosa nootkana |
Hooker’s Willow |
Salix hookerania |
Sitka Willow |
Salix sitchensis |
Red Elderberry |
Sambucus racemosa |
SECTION 9. APPENDIX D
Photos of Riparian Rafts
Riparian Raft Photo Page
|

|