State of the Tsolum River
Section 8
Previous
Next
Section 10


HOME
TABLE OF CONTENTS
Acknowledge ments
Report Contributors
SECTION 1. SUMMARY
SECTION 2. 

PROJECT AND WATERSHED DESCRIPTION
SECTION 3. 

VOLUNTEERS AND COMMUNITY INVOLVEMENT
SECTION 4. MEDIA AND PUBLIC EVENTS
SECTION 5.  ACID MINE DRAINAGE
SECTION 6.  WATER MONITORING
SECTION 7.  FISH HABITAT MAPPING PROGRAMS
SECTION 8.  REFUGE POND STUDIES
SECTION 9.  RESTORATION PROJECTS
SECTION 10.  FLOWS AND STORAGE REPORT
SECTION 11.  ENHANCEMENT


CONTACT US

Click on the fish to swim to the top of the watershed
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Click on the fish to swim to the top of the watershed
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Click on the fish to swim to the top of the watershed
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Click on the fish to swim to the top of the watershed
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Click on the fish to swim to the top of the watershed
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Click on the fish to swim to the top of the watershed

 

SECTION 9
Restoration Projects

Preserving Tsolum River Salmon Habitat

In order to maintain salmon stocks in this watershed, it is essential that fish habitat be restored and preserved.  In 1998 and 1999, eight habitat enhancement and restoration projects were completed by the Tsolum River Task Force, as shown in Appendix A.

These projects included: 

  1. Digging in-stream and near-stream refuge ponds.
  2. Stabilizing stream banks by constructing tiers of willow wattles (Appendix B).
  3. Planting streamside riparian vegetation to provide shade, cover from predators, and filtering of runoff from upstream runoff (Appendix C).
  4. Complexing stream habitat by constructing rock weirs and placement of habitat logs to increase pool scouring.
  5. Hardening streambeds with gravel to allow cattle to cross streams without causing erosion of soft substrate.
  6. Constructing riparian rafts that provide shade, cover and increase the food supply of refuge ponds (Appendix D).
  7. Installing a culvert to improve access to habitat previously inaccessible at low water.
  8. Protecting side-channel habitat from erosion.

Planning of 1997 and 1998 Restoration Initiatives

Consultation with the Tsolum River Task Force Habitat Work Group began in October 1997.  Priorities for in-stream projects were set and a work plan was developed for projects to be undertaken in 1998.  On the advice of the Habitat work group, it was agreed that restoration work should begin in the tributaries that were not affected by the adverse effects of copper pollution leaching into the Tsolum River mainstem below Murex Creek.  DFO Community advisor, Bryan Allen, and Norm Sieffert of the Portuguese Creek Watershed Stewards, also provided project advice. 

In the spring and summer of 1998, mapping crews used the Sensitive Habitat Inventory 
and Mapping (SHIM) Methodology  (Mason et al, 1998. Version 3.1), to map stream habitat, and identify opportunities for future restoration projects. 

In the spring of 1998, the restoration crew worked with landowners to develop project plans.  These plans were approved by the Habitat Work Group and by the appropriate government agencies before in-stream work began.

Click on the fish to swim to the top of the watershed

Restoration Projects

Plans for the following projects completed by TRTF in 1998 and 1999 are available in Chamberlain and Campbell 1999. 

1) Streambank stabilization, Franklin property

The Franklin property was experiencing a lot of flooding and streambank erosion.  To alleviate the flooding, sod and soil in the center of the channel were removed, and  willow wattles were constructed to protect streambanks from erosion.  This project was completed in four phases which are detailed in Appendix A, Table 1. 

Tiered willow wattles were constructed along 10 m of streambank in April 1998.  Willow stakes were also planted to stabilize the wattles and to provide cover on a low-lying area of the bank.  Designs for wattle construction were modeled after designs presented in Polster, 1998.   In July 1998, an island of sod which was restricting fish passage at low water was removed from the center of the channel.   Once the island was removed, six more metres of willow wattling were completed.  Streambanks were later replanted with riparian vegetation, which were tended by the landowner throughout the summer.    A further 15 meters of willow wattles will be constructed to stabilization streambanks in March 1999.

2) Stream channel complexing, Finlay Creek

In 1994 and 1995, Comox Valley Project Watershed Society installed boulders and woody debris in Finlay Creek, a tributary to Portuguese Creek. 

These structures were installed to combat siltation following the clearing of an upstream wetland property.   The TRTF restoration crew revisited the sites in the third reach of the stream and determined that additional stream complexing was needed.  In-stream structures that had been previously installed were stabilized to encourage pool development.

3) Near-Stream Refuge Pond Construction, Bell property

Water levels in Portuguese Creek rise quickly after a rainfall due to runoff entering the creek from surrounding residential and agricultural land.  Water levels in the creek also drop to near zero during the months of July and August.  With few wetlands to buffer changes in flow, fish in the creek must migrate to rearing habitat in other creeks, or survive in refuge ponds. 

Many landowners have worked with the Portuguese Creek Watershed Stewards to develop refuge ponds on their properties.  These ponds provide a dual service to salmon, offering summer refuge to coho and trout fry and providing shelter for adults returning to spawn in the system.

In the spring of 1998, the TRTF worked with a landowner and the Portuguese Creek Watershed Stewards to construct a near-stream pond on the Bell property adjacent to Gunter Road. The pond joined the creek at one site and was filled in the fall by high water.  Stumps from trees removed during pond construction were placed back into the pond to provide cover for fish. 

Riparian vegetation and grass seed was planted to stabilize sloping pond banks and to provide cover for the fish.   In the fall of 1998, landowners observed adult coho holding in this pond prior to spawning.  In the spring of 1999, a catamaran style riparian raft was installed in this pond.

4)  In-stream ponds and riparian raft construction, McWilliam’s property

Forsythe and Smit Creeks (tributaries to Dove Creek) run dry during the summer and offer little refuge to salmon because of lack of in-stream complexity. During November 1997, chum salmon were observed spawning in Forsythe Creek.  In the spring of 1998, coho fry were salvaged from drying stream pools and transported to refuge ponds.

Groundwater in this area is in short supply and much of the water resource available is utilized for domestic and agricultural purposes.  To provide refuge habitat, two in-stream refuge ponds were constructed, and a series of rock weirs were constructed in Smit Creek on the McWilliam property.  In the fall of 1998, riparian vegetation was planted on the streambanks and around a previously constructed irrigation pond used as rearing habitat for salmonid fry.

To provide shade and cover for fry in this pond, two riparian rafts were constructed (Appendix D).   The raft is anchored to the pond bottom and the vegetation on the raft provides cover and shade for the fish.  Insects that land along the raft edges become a potential food source for the salmon fry when they drop off the raft into the pond. To maximize the effect, the rafts were constructed as small rectangles thereby providing the maximum edge area.  Designs for riparian rafts can be obtained from the TRTF. 

5) Heidema pond and stream reconstruction

The Portuguese Creek Watershed Stewards had reported large numbers of fry rearing in this branch of Portuguese Creek, and had cooperated with the landowner to construct two small off channel ponds that provide summer and winter refuge habitat for coho pre-smolts and trout fry. 

A site assessment determined that a larger pond was needed, and that some channel reconstruction would alleviate flooding occurring on an adjacent property.  This channel would provide easy access to the new pond.  This area is used by coho spawners that rely on the ponds to provide refuge from predators during times of low flow.

The Portuguese Creek Watershed Stewards had established landowner contact, and were instrumental in assisting with project planning and design.  To alleviate flooding on the adjacent property, a silt plug was removed and the stream was redirected into a more stable outflow channel. 

After the pond and channel reconstruction was completed, riparian vegetation and grasses were planted to stabilize streambanks and pond sides.

6) Culvert installation at Gark Creek

Gark Creek is an ephemeral tributary to the Tsolum River.  To enhance salmon habitat the owner of the property had installed a culvert in the creek.  Unfortunately this culvert acts as a barrier at low water flows, and as the creek dried up salmon fry became trapped in pools below the culvert. 

The original plan was to remove the culvert and install a bridge using donated timbers.  When the timbers became unavailable; a second plan was developed by an engineering technician to design a culvert installation plan.  In cooperation with DFO engineers the plan was approved, and the culvert was installed between August 19 and September 8, 1998.  The landowners supported the project by offering a machine and operator to install the culvert.  Root wads and boulders were donated by the Vancouver Island Highway Project.  These were placed in the channel upstream of the culvert to provide cover for fry and adults.  Riparian vegetation was planted along the sides of the creek to offer additional shade and cover. 

7) Stream complexing and cattle crossing,  Pistell property

Previous projects completed by the Portuguese Creek Watershed Stewards and Comox Valley Project Watershed’s “Stewardship on the Farm” program brought this opportunity to the attention of the TRTF.  Coho salmon had have been seen rearing in the middle branch of Portuguese Creek and in the pond downstream from the restoration site.

The stream channel had been degraded by years of cattle crossing and lacked riparian cover and large woody debris.  Once fencing had been put in place to eliminate cattle, plans were prepared with reference to Fish Habitat Restoration Procedures (Slaney and Zaldokas,1997) and the Stream Enhancement Guide  (Anon., 1980).  Work began at the property on August 14 after landowner and government approvals had been received.  The TRTF paid for the cost of the machine and materials used for the project while the landowner provided stumps for stream complexing, and a neighbour provided cedar logs for in-stream weirs.

Downstream from the weirs, a silt plug was removed and a small pool was excavated.   Gravel was placed in the stream above the pool to provide cattle with access to an adjacent field.  This project will be monitored for structure stability, and additional large woody debris will be added if necessary. 

8) Side channel stabilization, Jorgensen property

The channel that borders the Jorgensen property (downstream of Dove Creek) is one of only two known side channels in the lower Tsolum River.  In 1997, fall floods eroded the entrance to the channel, and the mainstem of the river threatened to erode the entire area. 

Adjacent landowners approached the Task Force and DFO to arrange a site visit. A plan was developed, and following DFO approval the work began.  Boulders and rootwads were placed to protect the outside of the channel.  By the spring of 1999, some channel modification had occurred, but most of the channel habitat was still intact. The summer of 1998 was very long and dry, allowing an extension of the prescribed fisheries window.  This seasonal variation meant that we were able to complete the project later in the season than would normally have been allowed.

Click on the fish to swim to the top of the watershed

Recommendations for Further Work 

  1. To continue with streambank stabilization, willow wattling should be completed in the eroding sections of lower Portuguese Creek.  Erosion control is also needed on   sections of Headquarters Creek above the hatchery and in areas which are being impacted by the Vancouver Island Highway project.
  2. Many small streams would benefit from increasing the amount of riparian vegetation along the banks.  This should be undertaken on agricultural land only after streamside fencing is in place.
  3. The addition of spawning gravel and weir construction would benefit Portuguese Creek, Forsythe Creek and several other tributaries.
  4. The addition of large woody debris (stream complexing) is needed in several small streams, such as Forsythe, and some of the tributaries to Dove Creek.
  5. There is a shortage of summer and winter rearing habitat and refuge for spawners.  Construction of more refuge ponds, and linking existing ponds into a network would improve salmon survival.
  6. There is a need to provide additional shade and cover in some of the refuge ponds.  Installation of riparian rafts in these areas would improve habitat quality.
  7. Working with the agricultural community to test the effectiveness of riparian bridges for improving fish habitat in drainage ditches should be initiated.  These bridges will provide cover for fish and improve winter rearing habitat without blocking the drainage capability of the ditches. 
  8. A culvert study should be undertaken to determine whether existing culverts are barriers to fish passage.  Culverts that are limiting fish movement should be replaced or reinstalled.
  9. A program of landowner contact and public awareness would greatly assist habitat restoration efforts.  By informing landowners of the importance of maintaining streamside vegetation, we may reduce the need for stream rehabilitation.
Click on the fish to swim to the top of the watershed

References

  • Anonymous 1980.   Stream Enhancement Guide.  Salmonid Enhancement Program, Government of Canada, Department of Fisheries and Oceans, Province of British Columbia, Ministry of Environment, Kerr Wood Leidal Associates Ltd., and D.B. Lister & Associates Ltd.   DFO Vancouver, BC.
  • Chamberlain D., and Campbell K. 1999.  Tsolum River Restoration Project Plans.  Internal Report to the Tsolum River Task Force. 
  • Mason B., 1998. Stream Mapping Procedures for Land-Use Planning in Coastal Urban Watersheds 1998.  Department of Fisheries and Oceans in partnership with Ministry of Environment, Lands and Parks and the Pacific Streamkeepers Federation. DFO  Vancouver. 
  • Polster D. 1998.  Soil Bioengineering for Forest land Reclamation and Stabilization
  • Prepared for British Columbia Ministry of Forests. Resource Tenure & Engineering Branch Engineering Section. BC Ministry of Forests. Victoria, BC.
  • Slaney P.A. and Zaldokas D. 1997 Fish Habitat Rehabilitation Procedures.  Watershed Restoration Technical Circular No. 9  Watershed Restoration Program, Ministry of Environment, Lands and Parks.
Click on the fish to swim to the top of the watershed

SECTION 9.  APPENDIX A
Map and Table of Restoration
Project Locations

Appendix A. Completed Restoration Projects
 
Project Title
Location
UTM 
Easting
UTM 
Northing
Date Begun
Date
Com- pleted
1a Franklin Property 

Streambank Stabilization 
Franklin Property

Carwithen Rd.

Lot 3 Sec 35 Comox Dist.

352362 5515924 Mar. 25, 1998 April 29, 1998
1b Franklin Property

Channel Clearing

Franklin Property

Carwithen Rd.

Lot 3 Sec 35 Comox Dist.

352362 5515924 July 22, 1998 July 22, 1998
1c Franklin Property

Riparian Replanting

Franklin Property

Carwithen Rd.

Lot 3 Sec 35 Comox Dist.

352362 5515924 July 28, 1998 July 28, 1998
1d Franklin Property

Streambank Stabilization

Franklin Property

Carwithen Rd.

Lot 3 Sec 35 Comox Dist.

352362 5515924 Mar. 5, 1999  Mar. 26, 1999 

(est)

2 Stream Complexing Finlay Creek Finlay Creek Reach 3

Between. Wentworth & Caledon Rd. 

356536

upstream

5508966

upstream

July 18, 1998 July 22, 1998
3 Refuge Pond Construction

Portuguese Creek

Bell Property, Gunter Rd. Merville

DL 147 Comox District

352362 5515924 Aug. 8, 1998 Aug. 8, 1998
4a McWilliam Pond Riparian Raft McWilliam Property 3465 Burns Rd

Section 73 Comox District

353066 5508690 July 22, 1998 July 22, 1998
4b McWilliam Property

Stream Complexing,

Pond Construction

McWilliam Property 3465 Burns Rd

Section 73 Comox District

353066 5508656 Sept. 12, 1998 Oct. 8, 1998
4c McWilliam Property

Refuge Pond LW  Placement

McWilliam Property 3465 Burns Rd

Section 73 Comox District

353066 5508656 Oct. 30, 1998 Oct. 30, 1998
5 Heidema Property

Refuge Pond, and 

Stream Channel Re- construction

Heidema Property 6850 N. Isl. Hwy 351928 5517195 Aug. 17, 1998 Aug. 31, 1998
6 Gark Property

Culvert Installation

Stream Complexing

Gark Property 4052 Dove Cr. Rd.

Lot B DL 122 Comox District

DD 34556-1

352483 5510479 Aug. 19, 1998 Sept. 8, 1998
7 Pistell Property

Stream Complexing

Pistell Property 6669 N. Isl. Hwy. 351300

upstream

5516672

upstream

Aug. 14, 1998 Aug. 20, 1998
8 Jorgensen Property

Sidechannel Armoring

Jorgensen Property, Todd Rd 

Site 463 C5, RR #4 Courtenay

Unkn Unkn Oct. 15, 1998 Oct. 22, 1998

Tsolum River Restoration Projects--Map

Click on the fish to swim to the top of the watershed

SECTION 9.  APPENDIX B
Willow Wattling Photos

Click on the fish to swim to the top of the watershed

SECTION 9.  APPENDIX C
List of Species Planted


Appendix C: Plants Used in Riparian Replanting Projects


 COMMON NAME SCIENTIFIC NAME
Red Alder  Alnus rubra
Red osier Dogwood Cornus stolonifera
Black Hawthorne Crataegus douglasii
Ocean Spray Holodiscus discolor
Black Twinberry Lonicera involucrata
Pacific Crabapple Malus fusca
Pacific Ninebark Physocarpos capitatus
Cascara Rhammus purshiana
Nootka Rose Rosa nootkana
Hooker’s Willow Salix hookerania
Sitka Willow Salix sitchensis
Red Elderberry Sambucus racemosa
Click on the fish to swim to the top of the watershed

SECTION 9.  APPENDIX D
Photos of Riparian Rafts

 Riparian Raft Photo Page


Previous
Top of Page
Click on the fish to swim to the top of the watershed
Next
Section 10
 


Restoration Projects
Preserving Habitat
Restoration Projects
Recommen- dations
References
 Restoration Map 
Willow Wattling Photos
Species Planted
Riparian Raft Photos

Click on the fish to swim to the top of the watershed
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Click on the fish to swim to the top of the watershed


 
 
 
 
 
 
 
 
 
 

Updated August 26 2001
DF