Electricians scheduled to fix the wires dangling from demolished
walls and to start wiring of the addition. They were no shows -- maybe next week.
Chimney started to be built up above the addition. Workers left
before noon when the snow started (and after they got paid for the materials).
They need to re-build some of the old chimney -- had a section where you could
see the flue from the inside.
Door onto porch scheduled to be cut out from Tim's bedroom window, but
delayed due to "snow storm" -- almost a whole inch of snow.
Selected the siding style and color for the upper part of the house.
(wood-grain 4" white)
|