September 22

Roof, Chimney and Insulation are finished


The roof is finished, despite yesterday's high winds and driving rain. And check out the new brick chimney, replacing the old cement block chimney you can see in this photo from a few weeks ago.

The insulation is installed...

...and below is the same window, tipped in to show how convenient they'll be to clean.