Feb.1998:  The start of the project:  Shed extension constructed and some ribs put together sitting on top of a pile of cedar.
The clipper bow form clamped up with lofting table in the background of the  workshop.
The ribs and bulkheads going up.... The bow form with first rib. Note flair...
Mid ribs and Bulkheads...
All ribs and bulkheads in and stringers and temp. stringers holding it all together...... planking starting from gunnel up...
Planking continues.... max 3 planks all round per day, epoxy glued and nailed... chief glue lady taking a coffee break...approx 1.5 miles of glue line for the hull .....
Keel stub...
Last bit of planking from keel stub out...see 2 key planks about to go in where the 2 layers meet....as per tradition, we had a fantastic "key plank party" to celebrate.....the hull can now hold water...